Revised EPIPs Including Rev 29 to 13.1.1 Classifying Emergency Rev 7 to 13.1.1A Classifying Emergency - Technical Bases Rev 15 to 13.2.1 Emergency Exposure Levels/Protective Action Guide & Replacement Pages r,27,29,31,33,35 & 37 to Rev 34 o
ML010610104
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 02/22/2001
From:
Energy Northwest
To:
Office of Nuclear Reactor Regulation
References
-RFPFR
Download: ML010610104 (218)


Text

{{#Wiki_filter:ENVERGY NORTH WEST INTEROFFICE MEMORANDUM DATE: February 22, 2001 TO: Distribution FROM: Procedure Control, Administrative Services, (927A)

SUBJECT:

PLANT PROCEDURES MANUAL - VOLUME 13 Distribution Package: 2001-106

REFERENCE:

The following Procedure(s) have been revised/approved and are to be inserted in your controlled copy of the Manual and the superseded revisions are to be removed and destroyed: Procedure Rev. Title 13.1.1 29 Classifying the Emergency 13.1. 1A 7 Classifying the Emergency - Technical Bases 13.2.1 15 Emergency Exposure Levels/Protective Action Guide Also included in this package are EDITORIAL CHANGES, please replace the pages located in your manual with the attached pages: Procedure Rev. Pa2e(s) 13.14.4 34 4, 27, 29, 31, 33, 35, 37 13.14.9 18 2, 3, 4 To verify receipt or cancellation of the subject Procedure(s), please sign, date and return this receipt to Procedure Control, MD 927A within TEN (10) WORKING DAYS of the date of this IOM. Or the receipt may be FAXED back to (509)377-2476 Energy Northwest Procedure Control (Mail Drop 927A) PO Box 968 Richland, WA 99352 Date Signature of Manual Holder Controlled Copy Number Abc 1

USE CURRENT REVISION ENERGY NORTHWEST COLUMBIA GENERATING STATION PLANT PROCEDURES MANUAL PROCEDURE NUMBER APPROVED BY DATE

  *13.1.1          -                                 DWC - Revision 29            -      02/22/01 VOLUME NAME EMERGENCY PLAN IMPLEMENTING PROCEDURES SECTION EMERGENCY CLASSIFICATION TITLE CLASSIFYING THE EMERGENCY TABLE OF CONTENTS Pa1e 1.0      PURPOSE........................................................                                 2

2.0 REFERENCES

        .............................                     ................... 2 3.0      RESPONSIBILITIES ..........................                          ................... 3 3.1    Emergency Classification Responsibilities ........                                       3 3.2    Use of Plant Instruments and Indications .........                                       4 3.3    Emergency Class Description ................                                             5 3.4    Recovery vs. Downgrading Emergency Classifications                                       5 3.5    Mode Applicability ......................                                                5 3.6    Emergency Classification Chart ..............                                            6 3.7    Transitory Event Classification ...............                                          6 4.0       PROCEDURE . ................................................                                   7 4.1    Initial Classification/Control Room Actions .......                                      7 4.2    Continued Classification/Emergency Director Actions                                      8 4.3    Terminating The Emergency Classification .......                                         8 4.4    Transitory Event Classification Notification .......                                     9 5.0      ATTACHMENTS ................................                                                    9 5.1    Columbia Generating Station Emergency Classification Table .. .............             10 5.2    Columbia Generating Station Emergency Classification Chart Distribution        ..... 34 PROCEDURE NUMBER                       REVISION                       PAGE 13.1.1                                    29                       1 1of 34

1.0 PURPOSE NOTE: Refer to PPM 13.1.1 .A for the Technical Bases for this procedure. The purpose of this procedure is to provide guidelines for identifying conditions for which specific emergency classifications must be made. This procedure should be referred to whenever conditions at or near the Plant are out of the ordinary.

2.0 REFERENCES

2.1 Letter G12-94-349, NRC to Energy Northwest, dated December 9, 1994, Emergency Action Level (EAL) Changes For Energy Northwest Nuclear Project No. 2 (WNP-2)(TAC No. M88504) 2.2 10CFR50 Appendix E, IV.B, Assessment Actions {R5727} 2.3 Internal NRC Letter, William Travors to W.D. Shafer, 6/6/88, Recovery vs. Downgrading 2.4 NUREG-1022, Rev. 1, Event Reporting Systems 2.5 NEI 99-01, Methodology for Development of Emergency Action Levels, Revision 4 2.6 Columbia Generating Station Emergency Plan, Section 4 2.7 PPM 13.1.1 .A, Classifying The Emergency - Technical Bases 2.8 PPM 13.2.2, Determining Protective Action Recommendations 2.9 PPM 13.4.1, Emergency Notifications 2.10 PPM 13.10.1, Control Room Operations and Shift Manager Duties 2.11 PPM 13.10.2, TSC Manager Duties 2.12 PPM 13.11.1, EOF Manager Duties 2.13 PPM 13.13.2, Emergency Event Termination and Recovery Operations 2.14 PPM 13.13.4, After Action Reporting PROCEDURE NUMBER REVISION PAGE 13.1.1 29 2 of 34

3.0 RESPONSIBILITIES 3.1 Emergency Classification Responsibilities 3.1.1 Emergency Director Responsibilities Maintain the sole responsibility for timely classification and declaration of any Columbia Generating Station emergency situation utilizing guidance specified in this procedure and the recommendations of the Operations Manager, Shift Manager, Control Room Supervisor, Shift Technical Advisor, Radiological Protection Manager, or other cognizant support personnel. Given abnormal conditions at or near the Plant, utilize Attachment 5.1, Emergency Classification Table or the Emergency Classification Chart for guidance in determining the proper emergency classification. The Shift Manager is responsible for the initial emergency classification and immediately becomes the Emergency Director. The TSC Manager or EOF Manager can then relieve the Shift Manager of the Emergency Director responsibilities once the Technical Support Center or Emergency Operations Facility is operational. Ultimately the Emergency Director responsibilities will reside with the EOF Manager. These responsibilities are presented in more detail in PPM 13.10.1 for the Shift Manager, PPM 13.10.2 for the TSC Manager, and PPM 13.11.1 for the EOF Manager. 3.1.2 Shift Manager Responsibilities Function as the Emergency Director until relieved. Maintain primary responsibility for monitoring the status of plant parameters and other initiating conditions upon which emergency classification depends. Recommend an appropriate emergency classification to the Emergency Director, i.e., TSC Manager or EOF Manager, for any observed Columbia Generating Station emergency conditions. Utilize guidance specified in this procedure, and the recommendations of the Control Room Supervisor, Shift Technical Advisor, and Reactor Operators. PROCEDURE NUMBER REVISION PAGE 13.1.1 29 3 of 34

3.1.3 Control Room Supervisor, Shift Technical Advisor, Reactor Operator Responsibilities Monitor the status of Plant parameters and other initiating conditions upon which the emergency classification depends, and inform the Shift Manager if any parameter approaches or exceeds emergency action levels as specified in this procedure. Refer to Attachment 5.1, Emergency Classification Table, or Emergency Classification Chart for guidance in determining the appropriate classification. Additional information describing the basis of each EAL may be found in PPM 13.1.1A. 3.1.4 Technical Support Center (TSC) and Emergency Operations Facility (EOF) Staff Responsibilities Recommend an emergency classification to the Emergency Director based upon plant conditions and the guidance provided in this procedure. 3.2 Use of Plant Instruments and Indications {R5727} Plant instrumentation described in each Emergency Action Level in Attachment 5.1 is the primary instrumentation to be used. This does not preclude use of other instruments as alternate indication, as appropriate, to properly classify the emergency. All conditions defined within the Emergency Action Levels are to be evaluated based on the existence of valid indications. An indication or reported condition is considered to be valid when it is conclusively verified by: An instrument channel check; or

  • Indications on related or redundant indicators; or By direct observation by plant personnel, such that doubt related to the indicator's operability, the conditiori's existence, or the report's truth is removed.

Implicit in this definition is the need for timely assessment. PROCEDURE NUMBER REVISION PAGE 13.1.1 29 4 of 34

3.3 Emergency Class Description The following is a description of the four classes of emergency: UNUSUAL EVENT: Unusual events are in progress or have occurred which indicate a potential degradation of the level of safety of the plant. No releases of radioactive material requiring offsite response or monitoring are expected unless further degradation of safety systems occur. ALERT: Events are in progress or have occurred which involve an actual or potential substantial degradation of the level of safety of the plant. Any releases are expected to be Iiinited to small fractions of the- EPA Protective Action Guideline exposure levels. SITE AREA EMERGENCY: Events are in progress or have occurred which involve actual or likely major failures of plant functions needed for protection of the public. Any releases are not expected to result in exposure levels which exceed EPA Protective Action Guideline exposure levels except near the site boundary. GENERAL EMERGENCY: Events are in progress or have occurred which involve actual or imminent substantial core degradation or melting with potential for loss of containment integrity. Releases can be reasonably expected to exceed EPA Protective Action Guideline exposure levels offsite for more than the immediate site area. 3.4 Recovery vs. Downgrading Emergency Classifications Emergency classifications should never be downgraded to a less severe classification. It is appropriate to terminate an emergency classification of Unusual Event or Alert, and exit the classification process because the emergency condition no longer exists and the plant is stable. When remaining as a Site Area Emergency or a General Emergency is no longer necessary, it is appropriate to terminate the classification and enter the Recovery Phase process described in 13.13.2. 3.5 Mode Applicability The operational conditions (modes) in which Emergency Action Levels are applicable are indicated by a series of boxes as follows: 1 1 2 1 3 4 1 5 1 Def:] where the numbers indicate operational conditions as defined in Technical Specifications and Def indicates "Defueled" or all fuel removed from the reactor vessel. PROCEDURE NUMBER REVISION PAGE 13.1.1 29 5 of 34

Mode 1 = Power Operations Mode 2 = Startup Mode 3 = Hot Shutdown, GT 200', head bolts tensioned Mode 4 = Cold Shutdown, LTE 200' Mode 5 = Refueling 3.6 Emergency Classification Chart Classifications can be made from either of two sources, the Emergency Classification Table, Attachment 5.1, or the Emergency Classification Chart. In order to maintain this capability, the Emergency Classification Chart must be controlled (i.e., verified, validated, and distributed) in a similar manner as the procedure, thus it is considered to be a part of the procedure. Due to its size, however, the actual chart is not physically attached to the procedure, but is instead issued to those locations that would actually need it during implementation of the procedure. As a minimum, controlled distribution of the Emergency Classification Chart is specified in Attachment 5.2. If using the Emergency Classification Chart to classify an emergency situation, it is advisable to ensure it is the most current version by comparing the revision number on the chart to the revision number of the procedure. 3.7 Transitory Event Classification A transitory event classification should be made whenever it is discovered that a condition had existed which met the emergency classification criteria of Attachment 5.1, but where no emergency had been declared and the basis for which no longer exists. This situation could occur due to a rapidly concluded event, an oversight in emergency classification made during the event, or through further assessments made during a post event review. Discoveries of this condition within 90 days following an event are: a) considered to fall into this category and require the transitory event notifications to be made in accordance with PPM 13.4.1. b) are to be included in the event's After Action Report in accordance with PPM 13.13.4. Transitory event classification discoveries made beyond 90 days of an event should only be included in the event's After Action Report. If the final After Action Report has already been completed, the discovery should be documented in an addendum to this report. PROCEDURE NUMBER REVISION PAGE 13.1.1 29 6 of 34

4.0 PROCEDURE N-OTE: The Emergency used during Action Levels described maintenance and/or in this procedure are NOT testing situations where equipment status is expected. They abnormal temperature,intended to be be made if the Plant's mode are also mode dependent and classifications pressure, or of operation at the time of the abnormal occurrence should only range indicated for the was in the particular initiating condition. 4.1 Initial Classifi ControlRoomActions NOTE: The Control Room Manager is NOT in the Supervisor may perform the following steps if the Shift Control Room or is incapable of performing these duties. 4.1.1 When indications of abnormal occurrences are received by the Control staff, the Shift Manager Room shall:

a. Verify the indications of the offnormal event or reported sighting.
b. Ensure that immediate actions in accordance Operating Procedures, with the Emergency Abnormal Operating Response Procedures Procedures, and Alarm are taken for the safe and proper operation Plant. of the NOTE: Decisions should be based on conservative definitions, and purposes principles, for event classification.
c. Compare the abnormal conditions with the nine Emergency Classification categories listed in the Classification Chart and Table, Attachment 5.1, determine which category or the Emergency the event falls into.
d. Compare the information available from valid indications the Emergency Action or reports to Levels in Attachment category and classify 5.1 for the appropriate the event, using the highest supported by the available level which is information.
e. When an event is classified, the Shift Manager shall Emergency Director assume the responsibilities until properly relieved.
f. Determine whether public protective action recommendations needed per PPM 13.2.2. are NOTE: Offsite notifications be completed within to state and local officials 15 minutes of event classification. are required to Regulatory Commission Nuclear following the state and notification should be made as soon as local notifications, but possible no longer than 60 minutes after event classification.
g. Make notifications per PPM 13.4.1.
h. Take additional actions per PPM 13.10.1.

4.2 Continued Classification/Emergenc Director Actions 4.2.1 Continually evaluate the plant conditions to ensure the proper classification is being emergency utilized. NOTE: Decisions should be based on conservative purposes for event classsification. principles, definitions, and 4.2.2 If Plant conditions change, compare the categories listed in the current conditions with Emergency Classification the nine Emergency Classification Table, Attachment 5.1, Chart and determine or the which category the conditions are applicable to. 4.2.3 Compare the information available Emergency Action Levels from valid indications in the appropriate category or reports to the using the highest level and reclassify the event, which is supported by the available information. to section 3.4 for additional Refer guidance. 4.2.4 Determine whether the public protective action recommendations change by checking need to the criteria in PPM 13.2.2. 4.2.5 Perform follow-up notifications in accordance with PPM 13.4.1. 4.3 TerminatinThe Emergency Classification NXOTE:. PPM 13.13.2 Emergency classificationallows direct termination of a Site Area without the formation Emergency or General of the Recovery Task significant property damage Force, if no has occurred. 4.3.1 If existing conditions appear Emergency Action Levels, to be below the minimum criteria of terminate the Emergency the guidance in PPM 13.13.2. Classification using the 4.3.2 Ensure reports are performed in accordance with PPM 13.13.4. 4.3.3 Ensure followup notification of offsite agencies is performed per PPM 13.4.1.

4.4 Transitory Event Classification Notification 4.4.1 If it is discovered that a classifiable event has occurred, but the basis for the classification (i.e., the Emergency Action Level condition) no longer exists; ORR that a previously classified event was misclassified and the basis for the classification no longer exists, then perform the following:

a. Do NOT declare the missed classification or implement the Emergency Plan response associated with that classification.
b. Perform a transitory event classification notification to state, local and federal agencies in accordance with PPM 13.4.1.

4.4.2 For EALs with time limits associated with the condition:

a. Upon discovery of the condition, the start time for the time limit for classification begins at the time of discovery.
b. If the condition cannot be corrected within this time limit, then classification must be made.
c. If the condition can be corrected in the time limit since discovery, but the condition existed for a period of time that exceeded the time limit, then a transitory event must be declared.

4.4.3 Ensure reports are performed in accordance with PPM 13.13.4. 5.0 ATTACHMENTS 5.1 Columbia Generating Station Emergency Classification Table 5.2 Columbia Generating Station Emergency Classification Chart Distribution

(r COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY [JNI lgI IAi. F.VI*NIT A I I*DI" _.............______ SITE AREA EMERGENCY GENERAL EMERGENCY I Reactor Fuel Loss or potential loss of any two 1.1 Coolant Activity Fuel Clad Degradation Loss OR potential loss of fuel clad fission product barriers A loss of any two fission product z 1.I.U.I I.l.S.i barriers and loss or potential loss of the 1'11213141 I.I.A.I 1112131 1 1 third 1112131 1 1 I.I.G.1 RCS sample activity GT Technical Coolant activity GT 300 pCi/gm W12E13 _< Coolant activity GT 300 pCi/gm dose Specification 3.4.8 for GT LCO dose equivalent iodine. equivalent iodine tu Action Statement time. AND ANY of the following: Coolant activity GT 300 pCi/gm dose

                                                                                                       "* Any RCS Loss Indicators, Table I   equivalent iodine
                                                                                                       "* Total RCS leakage GT 30 gpm          AND inside PC or EDR-FRS-623, Pen 2  Drywell pressure response not upscale high                     consistent with LOCA conditions
  \O0                                                                                                  "* Any PC Loss Indicators, Table 2 z                                                                                                 "* Cannot maintain plant parameters       1.1.G.2 within SRVTPLL, or PSP CtD                                                                                                                                Coolant activity GT 300 pCi/gm dose equivalent iodine AND Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2, upscale high AND Any PC Loss Indicators, Table 2 o    c "0                                                                                                                                               I.I.G.3 111273 Coolant activity GT 300 yCi/gm dose equivalent iodine AND Any RCS Loss Indicators, Table I AND either of the following:

Any PC Loss Indicators, Table 2 OR Cannot maintain plant parameters within I-ICTL, SRVTPLL, or PSP

( COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAL EMERGENCY I Reactor Fuel 1.2 Radiation Monitors Fuel Clad De rIT ti, b Loss UK potential loss of RCS Loss or potential loss of any two A loss of any two fission product fission product barriers H11.2.U.1 2131 1 ElI 1.2.A.] 1.2.S.1 barriers and loss or potential loss of the third 1.2.G.I SJAE CONDSR OUTLET RAD Containment Radiation Monitor HI-HI alarm (P602) CMS-RIS-27E and CMS-RIS-27F Containment Radiation Monitor reading GT 70 R/hr CMS-RIS-27E and CMS-RIS-27F Containment Radiation Monitor reading GT 3,600 R/hr CMS-RIS-27E and CMS-RIS-27F reading GT 14,000 R/hr 1.2.G.2 1123 flII7I Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 3,600 R/hr AND ANY of following:

                                                                                                                 "* Cannot maintain plant parameters within HCTL, SRVTPLL, or PSP.
                                                                                                                 "* Drywell pressure response not consistent with LOCA conditions.
                                                                                                                 - Any PC Loss Indicators, Table 2

( COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT AI ,ERT RUFF ARI*A I*NA*I*t'q.*NIC*V 7--0 ALEFRT SITEp APPA PXAPDCVXMCV IfluxiXcL1'l. I Reactor Fuel 1.3 Refueling Incidents Unexpected decrease in water Major damage to irradiated fuel OR z covering irradiated fuel assemblies loss of water level that has resulted or will result in the uncovering of W 1.3.U.1 irradiated fuel outside the RPV 11121314 5def 1.3.A.1 1213 14151 defI Uncontrolled water level decrease in the reactor cavity or SFP below the level of the weirs with all irradiated HIGH alarm on ARM-RIS-I (Fuel fuel assemblies remaining covered Pool ARM) resulting from an by water uncontrolled irradiated fuel handling process 0z t rni Loss of water level that has or will result in the uncovering of irradiated fuel outside the reactor vessel 1.3.A.2 1 12 31415 def Water level, when not intentionally lowered, observed to be below the top of the gate sill separating the reactor cavity and the SFP 1.3.A.3 l2 3 14 15 def Report of visual observation of irradiated fuel uncovered or uncovering imminent. I

(. COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT RIT* AR*A UMFR*FNCV AETSITE AREA EMERGEPNCY C'.iMDAI IPNAGi-rXIIl-V 2 RPV 2.1 RPV Water Level RCS Leakage Loss OR potential loss of RCS Loss or potential loss of any two fission A loss of any two fission product barriers product barriers and loss of potential loss of the third z 2.1.U.1 1112131 2.I.A.1 [11213111 T7 2.1.S.1 1112131 2.1.G.1 11 1112131415 Valid unidentified leakage GE 10 gpm Total RCS leakage GT 30 gpm inside PC or upscale high indicated on recorder or EDR-FRS-623, Pen 2 upscale high RPV level LT -161 inches (for ATWS Entry into Severe Accident Guidelines EDR-FRS-623, Pen I (P632) (Non conditions, RPV level LT - 192") or cannot RCC) be determined 2.1.G.2 OR Valid identified leakage GE 25 gpm 1112131 indicated on recorder EDR-FRS-623, Pen 2 (P632) "*0 RPV level LT -161 inches, (for ATWS t4 conditions, RPV level LT -192") or cannot be determined AND ANY of following:

                                                                                                                                                    "* Rapid unexplained decrease of PC pressure following an initial increase.
                                                                                                                                                    "* Drywell pressure response not consistent with LOCA conditions
                                                                                                                                                    "* Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists 0                          _________________                     I _________________                     __________________                         J__________________

4*.

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT glTF AllVA UIkAI*I*t".I*'M*V T ~ LR ALERT ~~ ~ RA PKAPP-SITE________________ AREA ~ ~ NPR1PIV PNO ~ ~ t-i 1:P inmkOA 1.LAIAXA.IANTUU7AL fPAffr'flX,- T I I 2 RPV 2.2 Reactivity Control Inadvertent Criticality Failure of Reactor Protection System Failure of RPS instrumentation to Failure of the RPS to complete an (RPS) instrumentation to complete or complete or initiate an automatic automatic scram AND manual scram 2.2.U.I 1' 121314151 i initiate a reactor scram AND manual reactor scram once a RPS setpoirpt has was NOT successful AND there is scram was successful. been exceeded AND manual scram was indication of an extreme challenge to NOT successful the ability to cool the core. 2.2.A. I An extended and unplanned EU21 IEIII 2.2.S.1 2.2.G.1 sustained positive period observed on NIs, while NOT performing a H1 221 1 Il21 JI I1I I reactor startup. Any RPS setpoint (including manual) has been exceeded per Technical Any RPS setpoint (including manual) Any RPS setpoint (including manual) Specification 3.3. 1.1 has been exceeded per Technical has been exceeded per Technical AND Specification 3.3.1.1 Specification 3.3. 1.1 RPS actuation failed to result in a AND AND control rod pattern which alone RPS actuation failed to result in a RPS actuation failed to result in a always assures reactor shutdown control rod pattern which alone always control rod pattern which alone under all conditions assures reactor shutdown under all always assures reactor shutdown AND conditions under all conditions Manual Actions (mode switch in AND either: AND shutdown, manual push buttons and Reactor power GT 5% or unknown Wetwell temperature cannot be ARI) result in reactor power LE 5%. OR maintained LT the HCTL Wetwell temperature GT I 10°F ________________________________ A- _________________________________ J ___________________________________I _________________________________ I I

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT A1 17R'l"

   .0                                                                UNUSUAL   EVETIVI~d'.xjrANI0 Al~~~~        ~~~         *lq'l*

CTT1 IR ADI*A A DIC [2*AIL213*l-*rr,'tr

                                                                                                                                           '~In'1i-x        T        GELNERAL EMERGELNCY 3 Primary Containment C)     3.1 Primary Containment   Loss or potential loss of primary     Loss or potential loss of either fuel   Loss or potential loss of any two        A loss of any two fission product z          Pressure              containment                           clad or RCS                             fission product barriers                 barriers and loss or potential loss of the third 3.1.U.1 MT                                 1'1121311                              3.1I.A. I                               3.1.S.1 1112131                                  12131          1                         3.1.G.1 I

1112131 1 Rapid unexplained decrease of PC Drywell pressure GT 1.68 psig with Drywell pressure response not pressure following an initial indications of RCS leakage inside consistent with LOCA conditions PC pressure exceeds PCPL increase drywell. 3.1.S.2 1112131 0 z Rapid unexplained decrease of PC pressure following an initial increase AND ANY of the following:'

                                                                                                                     "* Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high (J1
                                                                                                                     "* Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr
                                                                                                                     "* Drywell pressure GT 1.68 psig with indications of RCS leakage tit    C      3.2 Wetwell Temperature/ Loss or potential loss of primary                                             Loss or potential loss of any two Level                containment                                                                   fission product barriers 3.2.U.1 111n231_1        1 1                                                           3.2.S.1 1112131         11 Cannot maintain plant parameters                                              RPV pressure and wetwell temperature within SRVTPLL                                                                cannot be maintained below HCTL

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE "CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAL EMERGENCY

   .. 0
  • )3 Primary Containment Loss or potential loss of any two 3.2 Wetwell fission product barriers Temperature/Pressure 3.2.S.2 T S1112131 Cannot maintain plant parameters within SRVTPLL or PSP AND ANY of the following:
  • Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 to CA upscale high SO
  • Containment Radiation Monitor
          >                                                                      CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr
            -
  • Drywell pressure GT 1.68 psig with indications of RCS leakage

__inside drywell to 4*.

( COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAl. EMER GF.NC¥ ~. 0 3 Primary Containment A loss of any two fission product 3.3 Combustible Gas barriers and loss or potential loss of Concentration the third 3.3.G.1 11121311W1 PC H2 and 02 concentrations GT 6% FH2 and 5% 02 z 3.4 Containment Loss or potential loss of primary Main steam line break outside Loss or potential loss of any two A loss of any two fission product Isolation Status containment containment with isolation fission product barriers barriers and loss or potential loss of the third 3.4.U.I 11121311 3.4.A.I [II 1231I1 1 3.4.S.I 1112131 1T 3.4.G.1 1112131 II I] Failure of containment isolation Indications of a MSL break Failure of containment isolation valves valves (LCS Table 1.6.1.3-1) in any AND (LCS Table 1.6.1.3-1) in any one line Intentional venting of Primary one line to close following auto or MSIV closure has isolated the break to close following auto or manual Containment to prevent failure. manual initiation initiation AND downstream pathway AND outside primary containment exists. downstream pathway outside AND ANY of following: 14 primary containment exists 0 Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high

                                                                                                  "* Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr 0                                                                                                "* Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell 3.4.S.2 1112   131 Indications of a MSL break AND MSIV closure has not isolated the break

COLUMBIA GENERATING STATION EMERGENCY Secondary CLASSIFICATION TABLE UNUSUAL EVENT ALERT SITE AREA EMERGENCY Containment GENERAL EMERGENCY 4.1 Reactor Building Temperature/ Radiation Levels Loss or potential loss of any two fission Product barriersAlosOantwfiinprdcA loss of any two fission product 4.1.S.1 barriers and loss of potential loss of the third M ir= 4.I.G.1 Unisolable primary system outside PC resultingjn any discharging area Unisolable primary system temperature or radiation level above discharging outside PC resligi Maximum Safe Operating Values (as any area temperature or defined in the Emergency radiation Operating level above Maximum Safe Procedures). Operating Values (as defined in the Emergency Operating Procedures). AND ANY of the following:

  • Containment Radiation Monitor CMS-RIS-27E and CMS-RIS 27F reading GT 3,600 R/hr RPV level LT -161 inches (for ATWS conditions, RPV level LT -192 inches) or cannot be determined Coolant activity GT 300,uCi/gm dose equivalent iodine I ý

(ii TABLE COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION SITE AREA EMERGENCY GENERAL EMERGENCY UNUSUAL EVENT ALERT CATEGORY 0 5 Radioactivity Release from an actual or Offsite dose resulting from an actual or Any unplanned release of gaseous Any unplanned release of gaseous or Offsite dose resulting 5.1 Offsite Release imminent release of gaseous imminent release of gaseous or liquid radioactivity to the liquid radioactivity to the frLaemradioactivity that exceeds 1000 mrem that 200 times radioactivity that exceeds 100 xeeeeds environm ttthat exceeds environment two Limesc the radiological specifications for 15 TEDE OR 500projected mrem thyroid CDE total effective dose equivalent thyroid committed dose OR 5000 ODCM limits for 60 minutes or the actual OR duration offor the mrem minutes or longer equivalent for the actual OR projected zI longer release duration of the release using actual 5.1.A.1 meteorology 5.1.U.I 1 l21314151defl 5.1.S.1 0 112 13 14151 def 1[2 3J 4L5def 5.I.G.I 111213 415def A valid reading exists which exceeds A valid reading exists which A valid reading exists which exceeds or is expected to exceed Table 3 exceeds or is expected to exceed or is expected to exceed Table 3 column "Alert" for GT 15 minutes A valid reading exists which exceeds or Table 3 column "UE" for GT 60 column "Site Area" for GT 15 minutes is expected to exceed Table 3 column minutes 5.1.A.2 "General" for GT 15 minutes 5.1.S.2 5.1.U.2 1 213 415 de f [1 2 3 4 5 defl 1 12 314151defl Offsite dose calculations indicate 1112131415[defl 5.12G.2 "D Offsite dose calculations indicate dose rates GT Table 4 colum n UIIsNIC uud c a ....................

                                                                            "Alert"                                 or dose rates GT Table 4 column "Site offsite dose rates GT Table 4                                                  Area"                                       Offsite dose calculations indicate doses OR OR "UE" column                                 Sample analysis indicates release GT         OR                                     or dose rates GT Table 4 column 200 times ODCM 6.2.1.1 limits for       Field survey or survey sample analysis      "General" Sample analysis indicates release                                                                                               OR GT 15 minutes                           indicates offsite dose rates GT Table 4 GT 2 times ODCM 6.2.1.1 limits                                                                                             Field survey or survey sample analysis column "Site Area" for GT 60 minutes                                                                                                          indicates offsite dose rates GT Table 4 column "General".

t.*

( COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAL EMERGENCY 5 Radioactivity Release 5.2 Area Radiation Unexpected increase in plant Release of radioactive material or radiation levels increases in radiation levels within the facility that impedes operation of 5.2.U.1 systems required to maintain safe S1213 445 def operation or to establish or maintain cold shutdown Valid reading GT 5E3 mR/hr on 5.2.A. I ANY of the following ARMs: [1 2 3 45 def]

                          "* ARM-RIS-4 thru ARM-RIS 18
                          "* ARM-RIS-20 thru            Valid reading GT 15 mR/hr on ARM-RIS-30               ARM-RIS-19 (CR)
                          "* ARM-RIS-32 thru              OR ARM-RIS-34               Valid reading GT IE4 mR/hr on ANY (High Range)             of the following ARMs:
                                                        "* ARM-RIS-4 thru ARM-RIS-18
                                                        "* ARM-RIS-23
                                                        "* ARM-RIS-24
                                                        "* ARM-RIS-32 thru ARM-RIS-34 (High Range)

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE SA TP*.ORV ITINII 1*I AT FVF.NTI Al .,ERT SITE AREA EMERGENCY GENERAL EMERGENCY Li. I'AT~t~nD 0 6 Electrical Failures 6.1 AC Power Loss Loss of all offsite power to critical Loss of all offsite power and loss of Loss of all offsite power and loss of all Prolonged loss of all offsite power and all onsite power to critical AC busses onsite power to critical AC busses for prolonged loss of all onsite power to AC busses for greater than 15 for greater than 15 minutes greater than 15 minutes critical AC busses minutes 6.I.A.I 6.1.S.1 6.1.G.1 6.I.U.1 1112131 1 1 1 12131 1 1 I 112 131415def I I 1415efl trl Complete loss of all AC power to Complete loss of all AC power to SM Complete loss of all AC power to SM-7 Power is unavailable to SM-7 and SM-7 and SM-8 GT 15 minutes 7 and SM-8 GT 15 minutes and SM-8 SM-8 from offsite AC sources GT 15 minutes Power capability to critical AC AND either of the following: busses reduced to a single power source for greater than 15 minutes In the judgement of the Emergency such that any additional single failure Director, AC power to either SM-7 or would result in station blackout. SM-8 is not likely to be restored within 4 hours 6.!.A.2 OR 1112131 1 1 1 RPV level LT -161 inches (for ATWS conditions, RPV level LT -192 inches) 0 'o Available emergency bus AC power CD has been reduced to only one of the following sources for GT 15 min

                                                                          "* TR-NI (SM-7 and/or SM-8)
                                                                          "* TR-S (SM-7 and/or SM-8)
                                                                          "* TR-B (SM-7 and/or SM-8)
                                                                          "* DG-I (SM-7)
  • DG-2 (SM-8)

I T 6.2 DC Power Loss Degradation of all critical DC Degradation of all critical DC power power for greater than 15 minutes. for greater than 15 minutes 6.2.U.1 6.2.S.1 I I I I def 1112131 J Degradation of both Division I and Degradation of both Division I and Division 2 critical DC voltage as Division 2 critical DC voltage as indicated by bus voltage LT 110 indicted by bus voltage LT 110 VDC VDC on both 125 V Dist. Panels on both 125 V Dist. Panels SI-I and SI-I and S1-2 voltmeters (Bd. C) SI-2 voltmeters (Bd. C) for GT 15 for GT 15 minutes minutes I

I COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT AI FI*'U 7 Equipment Failures UNUSUAL EVENT A IIXI PdI PT~lI. YUNmA

                                                                                                                                                                       -GNEA EMREC LMREC
   )* 07 7.1 System Failures             Inability to reach required shutdown Inability to maintain plant in cold within technical specification limits shutdown C

7.1.U.1 1112 13 1 1 1 1 7.l.A.1 [_I 1 14 151 01 Plant is not brought to required Inability to restore and maintain operating mode within T.S. LCO reactor coolant temp LT 200OF action statement time 7.1.A.2 7.1.U.2 12 314[51def z 111213 4[ 5 def] Report by plant personnel confirming Uncontrolled flooding in a safe the occurrence of plant uncontrolled shutdown building, Table 5, that has internal flooding in a safe shutdown the potential to affect safety related building, Table 5 equipment needed for the current AND operating mode Affected safe shutdown system parameters indicate degraded I performance i I I 7.2 Control Room Control room evacuation has been Control room evacuation has been i0 Evacuation initiated initiated, but plant control CANNOT be established 7.2.A.1 11T21314151 7.2.S.I 112131415 L 4-' The decision to evacuate the Control Room has been made. CR evacuation initiated AND Control of plant equipment ndeded to maintain adequate core cooling cannot be established at either the Remote Shutdown Panel or Alternate Remote Shutdown panel within 15 minutes of the SRO in charge of the CR physically _______________I__ ____________________ I leaving the CR

t COLUMBIA GENERATING STATION (CEMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAl. EMERGENCY SITEAREAEMERENCYGENERAL. EMERGENCY 7 Equipment Failures z 7.3 Loss of Indications/ Unplanned loss of most or all safety Unplanned loss of most or all safety Inability to monitor a significant tz Communications Mr system annunciators or indication in system annunciators or indications in transient in progress. the control room for greater than 15 the control room with EITHER: 1) a minutes significant transient in progress; 7.3.S.1 OR 1112131 1 7.3.U.I 2) Compensatory non-alarming 1112131 indicators are unavailable Loss of most or all annunciators on 7.3.A. 1 P601, P602, P603 and Bd. C associated Unplanned loss of most or all 1112131 I I with safety related equipment annunciators on P601, P602, P603, AND and Bd. C associated with safety Compensatory nonalarming indications related equipment GT 15 minutes Unplanned loss of most or all are unavailable (process computer annunciators on P601, P602, P603, system and GDS) z and Bd C associated with safety AND Significant loss of onsite OR offsite related equipment GT 15 minutes Significant transient in progress communications capabilities AND AND either of the following: Loss of indications needed to monitor C) 7.3.U.2 A significant plant transient is in ANY of the following plant critical 112 131415def progress safety parameters: OR "* Reactor power Compensatory non-alarming "* RPV level Unplanned loss of ALL of the indications are not available (plant "* RPV pressure following onsite communications computer system and GDS) "* Drywell pressure capability: "* Drywell temperature

                                "* Plant Public Address (PA)
  • Wetwell pressure System
  • Wetwell/Drywell H2/02
                                "* Plant Telephone System                                                         Concentrations
                                "* Plant Radio System Operations
  • Wetwell level and Security Channels . Wetwell temperature I* Radinai-tl'v U.. ýx

('nPAnI maumma Pffiu hnt, Uku a I

( ~( COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAL EMERGENCY "7 Equipment Failures 7.3 Loss of Indications/ Significant loss of onsite or offsite Communications communications capabilities

  *tJ 7.3.U.3 111213     415 defI Unplanned loss of ALL of the following offsite communications capability:

0 State/County Notification (CRASH) System

  • Offsite calling capability from 0*the Control Room via direct telephone and fax lines 0 Long distance calling capability
        >"                               on the Plant ("2000") Switch and Kootenai (Plant Support Facility)/Deschutes (Plant Engineering Center) ("8000")

Switch Lu t'N 40

Ill COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE( CATEGORY UNUSUAL EVENT AlE'RT SITE AREA EMERGENCY GENERAL EMERGENCY 0 r I r 1 8 Hazards 8.1 Security Threats Confirmed security event which Security event in a Plant Protected Security event in a Plant Vital Area Security event resulting in loss of 01 indicates a potential degradation in Area ability to reach and maintain cold the level of safety of the plant 8.1.S.1 shutdown 8.1.A.1 8.1.U.1 213 14215 def] 11 2131415 def 8.1.G.1 111213 4[ def 112 13 14 15 def Bomb device discovered or detonated 0 Confirmed report of an intrusion by a within a Safe Shutdown Building, z Bomb device discovered within hostile force into the Plant Protected Table 5 Loss of physical control of the CR due plant protected area but outside a Area OR to security event Safe Shutdown Building, Table 5 Confirmed report of intrusion by a OR OR hostile force into a Safe Shutdown Loss of physical control of the remote Confirmed report of an attempted Building, Table 5 shutdown capability due to security tN) entry, sabotage or security threat event that cannot be properly compensated for within 10 minutes t 1 1 4 4ý, 8.2 Fire/Explosion Fire within the Protected Area Fire or explosion affecting the Caused by Boundary not extinguished within operability of plant safety systems Equipment Failure 15 minutes of detection OR an required to establish or maintain safe explosion within Protected Area shutdown

,o                                       Boundary LA                                                                        8.2.A.1 I-.                                8.2.U.1                               [[213 1415 def 1112131451 defI Confirmed fire or explosion in a safe Fire within or adjacent to any Safe     shutdown building, Table 5 Shutdown Building, Table 5, which        AND either of the following:

is not extinguished within 15 Affected safe shutdown system minutes of either CR notification by parameters indicate degraded plant personnel or receipt of an performance alarm OR OR Report by plant personnel of visible Report by plant personnel of an damage to the affected safe shutdown unplanned explosion within the building or equipment contained Protected Area boundary resulting within the affected safe shutdown in visible damage to permanent building structures or equipment ____________________________ .1. ______________________________ L ______________________________

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE -. 0 C) CATEGORY UNUSUALEVENT ALERT RITE ARFA 171k/IFR*I*NIf*V ('W'KIPDAI WXAPDC'PXJr1V r1 ALERTSITE AREA EMERGENCY 0 I-. 8 Hazards z 8.3 Man-Made Events Natural and destructive phenomena Natural and destructive phenomena C affecting the Protected Area affecting Safe Shutdown Buildings w Boundary ni 8.3.A.1 8.3.U.I 1112131415def 1112 13 14 5 def] Vehicle crash or projectile impact Vehicle crash into or projectile which impedes access to or damages which impacts a Safe Shutdown equipment in a Safe Shutdown Building, Table 5 Building, Table 5 8.3.U.2 8.3.A.2 1112131 I I I 1112131 1 1 C) Turbine failure resulting in casing Missiles generated from a turbine penetration or damage to turbine or failure have resulted in visible generator seals structural damage to or penetration of to a safe shutdown building, Table 5 0 i Release of toxic or flammable gases Release of toxic or flammable gases affecting the Protected Area within a facility structure which Boundary deemed detrimental to jeopardizes operation of systems safe operation of the plant. required to maintain safe operations or to establish or maintain cold Q 8.3.U.3 shutdown. 1[2 314151 defI 8.3.A.3 1121314151 defl Report or detection of toxic or flammable gases that could enter or have entered within the Protected Report or detection of toxic or Area Boundary in amounts that flammable gases within a safe could affect the health of plant shutdown building, Table 5, in personnel or safe plant operation concentrations that will be life OR threatening to plant personnel or Report by local, county or state impede access to equipment needed officials for evacuation or shelter of for safe plant operation. site personnel based on offsite event

                                    -                                 .1. ___________________                     1 ___________________                1

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAL EMERGENCY p.. 0 8 Hazards 8.4 Natural Events Natural and destructive phenomena Natural and destructive phenomena affecting the Protected Area affecting Safe Shutdown Buildings Boundary 8.4.A. I 8.4.U.1 112131415 def] k O 11121 4 5 OPERATING BASIS Z: MINIMUM SEISMIC EARTHQUAKE alarm EARTHQUAKE alarm (H13-P85 1-S1-5. 1) (H13-P851-SI-2.5) AND AND CR receives report from plant CR receives report from plant personnel who have felt an earthquake personnel who have felt an

 ~.o0                           earthquake                                8.4.A.2 1112134 54d 8.4.U.2 11121 3415def Weather Service projected winds GT 100 mph Weather Service projected winds GT       OR 80 mph                                 CR measured winds GT 76 mph ( 5 (D.

OR minute average at 33 ft) CR measured winds GT 66 mph (5 OR minute average at 33 ft) Report by plant personnel confirming OR the occurrence of a tornado striking a Report by plant personnel confirming plant safe shutdown building, Table 5 0 the occurrence of a tornado striking 0 within the Protected Area Boundary 8.4.A.3 1112131415def Ash fallout from volcanic activity is severe enough to warrant plant 8.4.U.3 shutdown 111213 4 5 def Range fires near the plant which threaten to reduce the level of safety

                                                                                                                                                          /

COLUMBIA GENERATING STATION ( EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT ALERT SITE AREA EMERGENCY GENERAL EMERGENCY S0 8 Hazards 8.4 Natural Events Natural and destructive phenomena Natural and destructive phenomena

z affecting the Protected Area affecting Safe Shutdown Buildings Boundary 8.4.A.4 8.4.U.4 l21 31451 defI 112 13 14 e Z

Report by plant personnel of an event Visible ash fallout from volcanic causing visible structural damage to a activity safe shutdown building, Table 5 8.4.U.5 1112 13 415 ef River level increase which threatens to flood the river pumphouse

   .z

______________________________ n .5. ________________________________ t!

( COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE CATEGORY UNUSUAL EVENT AlIERT SITE AREA EMERGENCY GENERAL EMERGENCY 0 C- 9 Other Other conditions existing which, in Other conditions existing which, in the Other conditions existing which, in the Other conditions existing which, in the 9.1 Other the judgement of the Emergency judgement of the Emergency Director, judgement of the Emergency Director, judgement of the Emergency Director, z Director, warrant declaration of an warrant declaration of an Alert warrant declaration of a Site Area warrant declaration of a General Unusual Event. Emergency Emergency 9.I.A.1 9.1.G.1 9.1.U.I 1112131415def 9.I.S.1 12 13 4 5 def 12 13 141 5def] 11121314151def In the judgement of the Emergency In the judgement of the Emergency In the judgement of the Emergency Director, events are in progress or have In the judgement of the Emergency Director, other conditions exist which Director, events are in progress or occurred which indicate actual or Director, events are in progress or have indicate either of the following: have occurred, which indicate a potential substantial degradation of the occurred which involve actual or likely Actual or imminent substantial core potential degradation of the level of level of safety of the plant major failures of plant functions needed degradation or melting with the potential safety of the plant for protection of the public for loss of containment integrity OR z S0 Potential for uncontrolled radionuclide releases which can reasonably be expected to exceed EPA PAG plume exposure 4 4 levels outside the site boundary r) Loss OR potential loss of Primary Loss OR potential loss of fuel clad or Loss or potential loss of any two fission A loss of any two fission product barriers Containment RCS product barriers and loss or potential loss of the third 9.1.A.2 9.1.G.2 9.1.U.2 C-,' 1112131 1 1112131WI I 9.1.S.2 1112131 1 1112131 1 1 Any event, in the judgement of the Any event, in the judgement of the Any event, in the judgement of the Emergency Director, that could lead or Any event, in the judgement of the Emergency Director, that could lead or has Emergency Director, that could lead has led to a loss or potential loss of Emergency Director, that could lead or led to a loss of any two fission product to or has led to a loss or potential either fuel clad or RCS barrier as has led to a loss or potential loss of any barriers and loss or potential loss of the 0 loss of primary containment as indicted by Fission Product Barrier two fission product barriers as indicted by third as indicated by Fission Product indicted by Fission Product Barrier Degradation Table, Table 6 Fission Product Barrier Degradation Barrier Degradation Table, Table 6 Degradation Table, Table 6 Table, Table 6 ________ a __________________ J ____________________ .L _____________________ ______________________

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE TABLE 6 FISSION PRODUCT BARRIER DEGRADATION TABLE Fuel Clad Loss Fuel Clad Potential Loss RCS Loss RCS Potential Loss PC Loss PC Potential Loss 0 1 r r r S C Coolant activity GT 300 RPV level LT-161 inches Containment Radiation Total RCS leakage GT 30 Rapid unexplained decrease Containment Radiation ALCi/gm dose equivalent (for ATWS conditions, RPV Monitor CMS-RIS-27E and gpm inside PC or EDR-FRS of PC pressure following an Monitor CMS-RIS-27E 01 iodine level LT -192 inches) CMS-RIS-27F reading GT 623, Pen 2 upscale high initial increase and CMS-RIS-27F 70 R/hr reading GT 14,000 R/hr Unisolable primary system Containment Radiation RPV level LT -161 inches discharging outside PC Drywell pressure response PC [12 and 02 Monitor CMS-RIS-27E and (for ATWS conditions, RPV resulting in any area not consistent with LOCA concentrations GT 6% 112 CMS-RIS-27F reading GT level I.T-192 inches) temperature or radiation level conditions and 5% 02 3,600 R/hr above Maximum Safe Operating Values (PPM 5.3.1, "Secondary Containment Control") 14 Entry into Severe Accident Failure of containment Entry into Severe Guidelines Drywell pressure GT 1.68 isolation valves Accident Guidelines psig with indications of RCS (LCS Table 1.6.1.3-1) in any leakage inside drywell one line to close following auto or manual initiation Loss of pressure AND suppression function v

    >o CD                                                                                                                                    downstream pathway outside 0                                                                                                                                         primary containment exists OR t4.                                                                                                                                       Unisolable primary system discharging outside PC            Cannot maintain plant resulting in any area             parameters within IICTIL temperature or radiation level    or SRVTPLL above Maximum Safe "C                                                                                                                                           Operating Values (PPM 5.3.1,"Secondary Containment Control")

Intentional venting per Wetwell pressure exceeds PPM 5.2.1, "Primary PSP Containment Control" PC pressure exceeds PCPL Any event, in the judgement of the Emergency Director, that Any event, in the judgement of the Emergency Director, that Any event, in the judgement of the Emergency Director, could lead or has led to a loss or potential loss of the fuel could lead or has led to a loss or potential loss of the RCS that could lead to or has led to a loss or potential loss of clad barrier I barrier primary containment barrier

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION TABLE I-. z Table 1 RCS Barrier Loss Indicators

  • Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr
  • RPV level LT -161 inches (for ATWS conditions, RPV level LT -192 inches)
                              ,    Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell z  !

Table 2 PC Barrier Loss Indicators __° Rapid unexplained decrease of PC pressure following an initial increase

  • Failure of containtnent isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND 0

downstream pathway outside primary containment

1 0*

COLUMBIA GENERATING STATION ( EMERGENCY CLASSIFICATION TABLE TABLE 3 _0 Table 3 Effluent Monitor Classification Thresholds C1 Monitor UE Alert Site Area General NOTE: If a dose projection cannot be performed, and the monitor reading is sustained for longer than the specified time then the declaration must be made based on the valid reading. 1, 0 60 minutes 15 minutes 15 minutes 15 minutes z PRM-RE-1B 1.35E4 cps N/A N/A N/A Reactor Bldg. Exhaust Inter. PRM-RE- IC N/A 1.14E3 cps 9.65E3 cps 9.35E4 cps Reactor Bldg. Exhaust Hi TEA-RI S- 13 1.7E4 cpm 4.4E4 cpm 4.4E5 cpm N/A Turbine Bldg. Exhaust. Low TEA-RIS- 13A N/A N/A N/A II PMU Turbine Bldg. Exhaust, Int. 0 WEA-RIS-14 1.2E5 cpm 1.7E5 cpm 1.7E6 cpm N/A Rad Waste Bldg. Exhaust JI WEA-RIS- 14A N/A N/A N/A 29 PMU Rad Waste Bldg. Int. TSW-RIS-5 3.9E3 cpm 3.9E5 cpm N/A N/A TSW Effluent "01 FDR-RIS-606 2 x Hi-Hi alarm 200 x Hi-Hi alarm N/A N/A t0 t'. Rad. Waste Effluent SW-RIS-604 2.0E2 cps 2.0E4 cps N/A N/A SW 'A' Process SW-RIS-605 2.0E2 cps 2.0E4 cps N/A N/A SW 'B' Process

COLUMBIA GENERATING STATION (C EMERGENCY CLASSIFICATION TABLE TABLES 4 & 5

. 0 cps = counts per second      cpm = counts per minute        PMU = panel meter units       N/A = not applicable (outside of meter range)

Table 4 Offsite Dose Calculation/Field Survey Samnie Analysis Classification Thresholds at 1 2 miles z UE Alert Site Area General TEDE N/A N/A 100 mrem 1000 mrem CDE Thyroid N/A N/A 500 mrem 5000 mrem TEDE rate 0.1 mrem/hr 10 mrem/hr 100 mrem/hr (projected GT 1000 mrem/hr (projected GT 60 min) 60 min) CDE Thyroid rate 0.3 mrem/hr 50 mrem/hr 500 mrem (for GT 1 hr 5000 mrem (for GT 1 hr inhalation) inhalation) o z Table 5 Safe Shutdown Buildings

                                                        "*   Vital portions of the RadWaste/Control Building
                                                        "*   Reactor Building 0
                                                        "*   Vital portions of the Turbine Building
                                                        "*   Standby Service Water Pump Houses 0h                                                       "*   Diesel Generator Building
                                                        "*   Diesel Generator Fuel Oil Storage Area

COLUMBIA GENERATING STATION EMERGENCY CLASSIFICATION CHART DISTRIBUTION NOTE: The Emergency Classification Chart is provided in a separate, controlled distribution to the following locations: Location No. Of Copies Control Room 2 Technical Support Center 2 Emergency Operations Facility 2 Control Room Simulator 2 Remote Shutdown Room 1 Simulator Remote S/D Room 1 Attachment 5.2 PROCEDURE NUMBER REVISION PAGE 13.1.1 29 1 34of 34

USE CURRENT REVISION ENERGY NORTHWEST COLUMBIA GENERATING STATION PLANT PROCEDURES MANUAL PROCEDURE NUMBER APPROVED BY DATE

  "*13.1.1A                                          DWC - Revision 7                                      02/22/01 VOLUME NAME EMERGENCY PLAN IMPLEMENTING PROCEDURES SECTION EMERGENCY CLASSIFICATION TITLE CLASSIFYING THE EMERGENCY - TECHNICAL BASES TABLE OF CONTENTS Page 1.0      PU RPO SE ...................................................                                                      2

2.0 REFERENCES

       ................................................                                                 2 3.0      PROCEDURE .................................................                                                        4 3.2    Use Of Plant Instruments And Indications ...........................                                        4 3.3    Emergency Class Description ...................................                                            4 3.4    M ode Applicability          .........................................                                     5 4.0      ATTACHM ENTS ...............................................                                                      5 4.1     EAL Technical Bases ........................................                                               6 4.2     Fission Product Barrier Degradation Table Bases .......................                                  151 PROCEDURE NUMBER                      REVISION                                      PAGE 13.1.1A                                                  7                            1 of 157

1.0 PURPOSE The purpose of this procedure is to provide Plant Emergency Response Organization personnel tasked with classifying the emergency the technical bases for the Emergency Action Levels (EAL) listed in PPM 13.1.1, "Classifyring The Emergency". It is not necessary to refer to this procedure to classify the emergency. The emergency classification may be determined by utilizing the guidance contained within PPM 13.1.1. However, Plant Emergency Response Organization personnel may refer to this procedure for supplementaltinformation or clarification of EAL interpretation.

2.0 REFERENCES

2.1 Columbia Generating Station Technical Specifications 2.2 Columbia Generating Station Offsite Dose Calculation Manual 2.3 Columbia Generating Station FSAR Section 1.5.2, SBO Coping Study 2.4 Columbia Generating Station FSAR Section 8.3.2.1, Batteries 2.5 Columbia Generating Station FSAR Table 9.5-8, Location of Emergency Lighting 2.6 Columbia Generating Station FSAR Chapter 3.2, Classification of Structures, Components and Systems 2.7 Calculation CE-02-93-16 (Wind Speed Triggers for UE/Alert Declaration) 2.8 Calculation 2.05.01 (Battery Size Calc) 2.9 NEI 99-01, rev. 4, "Methodology for Development of Emergency Action Levels" 2.10 NUMARC/NRC, "Questions & Answers", June 1993 2.11 NUREG/CR-4982, "Severe Accident in Spent Fuel Pools in Support of Generic Safety Issue 82" 2.12 NUREG-0737, "Clarification of TMI Action Plan Requirements" 2.13 10CFR20, Standards for Protection Against Radiation 2.14 10CFR50, Domestic Licensing of Production and Utilization Facilities 2.15 EPA 400, "Manual of Protective Action Guidelines and Protective Actions for Nuclear Incidents" 2.16 FSAR, Chapter 13.3, Columbia Generating Station Emergency Plan, Section 6 PROCEDURE NUMBER REVISION PAGE 13.1.1A 72 of 157

2.17 NUREG-0654/FEMA-REP-1, Rev. 1, Appendix 1 ("Basis For Emergency Action Levels For Nuclear Power Facilities") 2.18 Columbia Generating Station Safeguards Contingency Plan 2.19 PPM 4.12.1.1, Control Room Evacuation and Remote Cooldown 2.20 PPM 4.12.4.2, Flood 2.21 PPM 4.12.4.8, Tornado/High Winds 2.22 PPM 4.12.4.10, Reactor Building 422' Area Flooding 2.23 PPM 5.0.10, EOP Flowchart Training Manual 2.24 PPM 5.1.2, RPV Control-ATWS 2.25 PPM 5.1.7, Primary Containment Flooding 2.26 PPM 9.3.22, Core Damage Evaluation PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 3 of 157

3.0 PROCEDURE 3.1 Plant Emergency Response Personnel Responsibilities Plant Emergency Response Personnel may refer to the Technical Bases in this procedure for emergency classification and after-the-fact review of emergency action levels. 3.2 Use Of Plant Instruments And Indications Plant instrumentation described in each EAL in Attachment 4.1 is the primary instrumentation to be used. This does not preclude use of other instruments as alternate indication, as appropriate, to properly classify the emergency. All conditions defined within the EALs are to be evaluated based on the existence of valid indications. An indication or reported condition is considered to be valid when it is conclusively verified by:

            "*    An instrument channel check; or
            "*    Indications on related or redundant indicators; or
            "     By direct observation by plant personnel, such that doubt related to the indicator's operability, the condition's existence, or the report's truth is removed.

Implicit in this definition is the need for timely assessment. 3.3 Emergency Class Description The following is a description of the four classes of emergency: UNUSUAL EVENT: Unusual events are in process or have occurred which indicate a potential degradation of the level of safety of the plant. No releases of radioactive material requiring offsite response or monitoring are expected unless further degradation of safety systems occurs. ALERT: Events are in process or have occurred which involve an actual or potential substantial degradation of the level of safety of the plant. Any releases are expected to be limited to small fractions of the EPA Protective Action Guideline exposure levels. SITE AREA EMERGENCY: Events are in process or have occurred which involve actual or likely major failures of plant functions needed for protection of the public. Any releases are not expected to result in exposure levels which exceed EPA Protective Action Guideline exposure levels except near the site boundary. PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 4 of 157

GENERAL EMERGENCY: Events are in process or have occurred which involve actual or imminent substantial core degradation or melting with potential for loss of containment integrity. Releases can be reasonably expected to exceed EPA Protective Action Guideline exposure levels offsite for more than the immediate site area. 3.4 Mode Applicability The operational conditions (modes) in which Initiating Conditions are applicable are indicated by a series of boxes as follows: Operating Conditions 11 2 1 3 4 1 5 1de~f where the numbers indicate operational conditions as defined in Technical Specifications and Def indicates "Defueled" or all fuel removed from the reactor vessel. 4.0 ATTACHMENTS 4.1 EAL Technical Bases 4.2 Fission Product Barrier Degradation Table Bases PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 5 of 157

1 REACTOR FUEL The reactor fuel cladding serves as the primary fission product barrier. Over the useful life of a fuel bundle, the integrity of this barrier should remain intact as long as fuel cladding integrity limits are not exceeded. Should fuel damage occur (breach of the fuel cladding integrity) radioactive fission products are released to the reactor coolant. The magnitude of such a release is dependent upon the extent of the damage as well as the mechanism by which the damage occurred. Once released into the reactor coolant, the highly radioactive fission products can pose significant radiological hazards in plant from reactor coolant process streams. If other fission product barriers were to fail, these radioactive fission products can pose significant offsite radiological donsequences. The following parameters/indicators are indicative of possible fuel failures: Coolant Activity: During normal operation, reactor coolant fission product activity is very low. Small concentrations of fission products in the coolant are primarily from either the fission of tramp uranium in the fuel cladding or minor perforations in the cladding itself. Any significant increase from these base-line levels is indicative of fuel failures. Radiation Monitors: As with coolant activity, any fuel failures will release fission products to the reactor coolant. Those products which are gaseous or volatile in nature will be carried over with the steam and eventually be detected by the air ejector off-gas radiation monitors. Although not a direct indication or measurement of fuel damage, exceeding predetermined limits on containment high range radiation monitors under LOCA conditions is indicative of possible fuel failures. In addition, this indicator is utilized as an indicator of RCS loss and potential containment loss. Refueling Incidents: Both area and process radiation monitoring systems designed to detect fission products during refueling conditions as well as visual observation can be utilized to indicate loss or potential loss of spent fuel cladding integrity. Attachment 4.1 PROCEDURE N-UMBER REV[SION PAGE 13.1.1A 76 of 157

1 Reactor Fuel 1.1 Coolant Activity 1.1 .U. 1 Unusual Event NUMARC IC: SU4 - Fuel Clad Degradation. APPLICABILITY: Operating Conditions I 12 13 14 1 1 1 EMERGENCY ACTION LEVEL: RCS sample activity GT Technical Specification 3.4.8 for GT LCO Action Statement time. BASES: This Initiating Condition is considered to be a potential degradation in the level of safety of the plant and a potential precursor of more serious problems. Coolant activity in excess of allowable Technical Specifications reflects a degraded or degrading core condition and represent a decrease in plant safety. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU4 WNP-2 Plant Specific EAL Guideline, SU4.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 7 of 157

I Reactor Fuel 1.1 Coolant Activity 1.l.A.l Alert NUMARC IC: Loss or potential loss of fuel clad APPLICABILITY: Operating Conditions 11 2 13 1 1 1 EMERGENCY ACTION LEVEL: Coolant activity GT 300 RCi/gmr dose equivalent iodine BASES: This EAL is indicative of the loss of the fuel clad barrier. Fuel Clad barrier damage is indicated by a coolant activity of 300 piCi/gm dose equivalent 1-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates clad heating and, thus, the Fuel Clad barrier is considered lost. Ssignificant REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC 1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 8 of 157

1 Reactor Fuel 1.1 Coolant Activity 1.1.S.1 Site Area Emergency NUMARC IC: Loss or~potential loss of any two fission product barriers APPLICABILITY: Operating Conditions 11 12 13 1 1 EMERGENCY ACTION LEVEL: Coolant activity GT 300 pCi/grn dose equivalent iodine AND ANY of the following: S Any RCS Loss Indicators, Table 1

  • Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high S Any PC Loss Indicators, Table 2
  • Cannot maintain plant parameters within SRVTPLL or PSP BASES:

This EAL represents loss of the fuel clad barrier (coolant activity GT 300 ACi/gm dose equivalent iodine) in combination with indications of a loss of RCS (Table 1) or potential loss of RCS (Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high) or loss of PC (Table 2) or potential loss of PC (Cannot maintain plant parameters within SRVTPLL or PSP). Fuel Clad barrier damage is indicated by a coolant activity of 300 .tCi/gm dose equivalent I-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates significant clad heating and, thus, the Fuel Clad barrier is considered lost. Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623 pen 1 (unidentified - Floor Drain Sump Fill Rate) and pen 2 (identified - Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (pen 2) in the Control Room at WNP-2 is 30 gpm, therefore 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. The inability to maintain plant parameters within the SRVTPLL or PSP represents a potential loss of PC. The SRV Tail Pipe Level Limit (SRVTPLL) is the highest wetwell water level at which the opening of an SRV will not result in exceeding the code allowable stresses in the tailpipe, tailpipe supports, quenchers or quencher supports. This level is a function of RPV pressure and the Limit is utilized to preclude SRV system failure and containment failure. The consequences of operating SRVs when wetwell water level exceeds SRVTPLL may include direct pressurization of the containment from a break in the SRV tailpipe. The resulting primary containment pressurization could cause containment failure. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 79 of 157

Entry into the unsafe region of the Pressure Suppression Pressure curve (PPM 5.2.1, "Primary Containment Control", Figure F, PSP) is included as a potential primary containment barrier loss. A rapid depressurization of the RPV (e.g., occurrence of a large break LOCA or initiation of ADS) at wetwell pressures in excess of the PSP may cause either: Wetwell pressure responses indicative of failure in the drywell-to-wetwell boundary, or Wetwell pressure increases to or beyond the Primary Containment Pressure Limit (PPM 5.2.1, "Primary Containment Control", Figure B, PCPL). Refer to Attachment 4.2 for the bases of each of the following referenced barrier loss/potential loss indicators. Table 1 RCS Barrier Loss Indicators

  • Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr
  • RPV level LT -161 in. (For ATWS conditions, RPV level LT -192 inches)
  • Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell Table 2 PC Barrier Loss Indicators
  • Rapid unexplained decrease of PC pressure following an initial increase
  • Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists REFERENCE(S):

WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC1.1 + RCS3.1, RCS2.1, RCS1.2, PC1.1, PC2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE

13. 1.1A 7 1 l10of 157

1 Reactor Fuel 1.1 Coolant Activity 1.1.G.1 General Emergency NUMARC IC: A lo ss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Coolant activity GT 300 gCi/gm dose equivalent iodine AND Drywell pressure response not consistent with LOCA conditions BASES: This EAL represents loss of the fuel clad barrier (coolant activity GT 300 gCi/gm dose equivalent iodine) in combination with an indication of a loss of both RCS and PC (Drywell pressure response not consistent with LOCA conditions). Fuel Clad barrier damage is indicated by a coolant activity of 300 ýtCi/gmr dose equivalent 1-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates significant clad heating and, thus, the Fuel Clad barrier is considered lost. Containment or drywell pressure responses not consistent with LOCA conditions indicate a loss of the Primary Containment barrier. This may be noticed as a decrease in drywell pressure when no operation action (e.g., starting drywell cooling fans) has been taken. It would also include a failure of the drywell pressure to increase as expected during a LOCA. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FCI.1 + PC 1.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 11 of 157

I Reactor Fuel 1.1 Coolant Activity 1.1.G.2 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 11 22 13 I I EMERGENCY ACTION LEVEL: Coolant activity GT 300 VCi/gm dose equivalent iodine AND Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high AND Any PC Loss Indicators, Table 2 BASES: This EAL represents loss of the fuel clad barrier (coolant activity GT 300 j.Ci/gm dose equivalent iodine) in combination with an indication of a potential loss of RCS (Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high) and loss of PC (Ay PC Loss Indicators, Table 2). Fuel Clad barrier damage is indicated by a coolant activity of 300 gCi/gm dose equivalent 1-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates significant clad heating and, thus, the Fuel Clad barrier is considered lost. Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623 pen I (unidentified - Floor Drain Sump Fill Rate) and pen 2 (identified - Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (pen 2) in the Control Room at WNP-2 is 30 gpm, therefore 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 12 of 157

Refer to Attachment 4.2 for the bases of each of the following PC barrier loss indicators: Table 2 PC Barrier Loss Indicators

"*     Rapid unexplained decrease of PC pressure following an initial increase
"*     Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists REFERENCE(S):

WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC1.1 + RCS1.2 + PC1.1, PC2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 13 of 157

1 Reactor Fuel 1.1 Coolant Activity 1.1 .G.3 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 11 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Coolant activity GT 300 RCi/gm dose equivalent iodine AND AnU RCS Loss Indicators, Table 1 AND either of the following: AU PC Loss Indicators, Table 2 OR Cannot maintain plant parameters within HCTL, SRVTPLL, or PSP BASES: This EAL represents loss of the fuel clad barrier (coolant activity GT 300 ýLCi/gm dose equivalent iodine) in combination with any of the Table 1 RCS loss indications and either a potential loss of PC (Cannot maintain plant parameters within HCTL, SRVTPLL, or PSP) or any of the Table 2 PC loss indicators. Fuel Clad barrier damage is indicated by a coolant activity of 300 ýtCi/gm dose equivalent 1-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates significant clad heating and, thus, the Fuel Clad barrier is considered lost. The Heat Capacity Temperature Limit (HCTL) is the highest wetwell temperature at which initiation of RPV depressurization will not result in exceeding the Primary Containment Pressure Limit (PCPL) before the rate of energy transfer to the containment is within the capacity of the containment vent. The HCTL is used to preclude failure of the containment or equipment necessary for safe shutdown by assuring that RPV blowdown does not cause containment pressure to exceed the PCPL. The potential loss occurs when RPV pressure and wetwell temperature cannot be maintained below HCTL. The SRV Tail Pipe Level Limit (SRVTPLL) is the highest wetwell water level at which opening of an SRV will not result in exceeding the code allowable stresses in the tailpipe, tailpipe supports, quenchers or quencher supports. This level is a function of RPV pressure and the Limit is utilized to preclude SRV system failure and containment failure. The consequences of operating SRVs when wetwell water level exceeds the SRVTPLL may include direct pressurization of the containment from a break in the SRV tail pipe. The resulting primary containment pressurization could cause containment failure. Entry into the unsafe region of the Pressure Suppression Pressure curve (PPM 5.2.1, "Primary Containment Control", Figure F, PSP) is included as a potential primary containment barrier loss. A Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 714 of 157

rapid depressurization of the RPV (e.g., occurrence of a large break LOCA or initiation of ADS) at wetwell pressures in excess of the PSP may cause either:

  • Wetwell pressure responses indicative of a failure in the drywell-to-wetwell boundary, or
  • Wetwell pressure increases to or beyond the Primary Containment Pressure Limit (PPM 5.2.1, "Primary Containment Control", Figure B, PCPL).

Refer to Attachment 4.2 for the bases of each of the following referenced barrier loss/potential loss indicators. Table 1 RCS Barrier Loss Indicators

  • Containment Radiation Monitor CMS-RIST-27E and CMS-RIS-27F readifig GT 70 R/hr 0 RPV level LT -161 in. (For ATWS conditions, RPV level LT -192 inches)
  • Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell Table 2 PC Barrier Loss Indicators
  • Rapid unexplained decrease of PC pressure following an initial increase
  • Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists REFERENCE(S):

"-..._j WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC1.1 + (RCS2.1, 3.1, 4.1) + (PC1.1, PC2.1, PC 1.5, PC5.2) Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 15 of 157

I Reactor Fuel 1.2 Radiation Monitors 1.2.U.1 Unusual Event NUMARC IC: SU4 - Fuel Clad Degradation APPLICABILITY: Operating Conditions Il1 1 2 13 -t 1 EMERGENCY ACTION LEVEL: SJAE CONDSR OUTLET RAD HI-HI alarm (P602) BASES: This Initiating Condition is considered to be a potential degradation in the level of safety of the plant and a potential precursor of more serious problems. SJAE CONDSR OUTLET RAD HI HI monitor and alarm reflects the offgas effluent and, therefore, may be one of the first indicators of degrading fuel conditions. The alarm is confirmed by verification of greater than current alarm setpoint on Recorder OG RIS-612 on Panel P604 or high offgas pre treatment air activity [determined by sample results] greater than limits specified in Technical Specification 3.7.5. The Hi alarm setpoint corresponds to a fraction of the Technical Specification limit thereby alerting the plant of the need to sample prior to exceeding limits. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU4 Instrument Master Data Sheet(s) for instrument(s) listed in the EAL(s) WNP-2 Plant Specific EAL Guideline, SU4.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 716 of 157

I Reactor Fuel 1.2 Radiation Monitors 1.2.A.1 Alert NUMARC IC: Loss or potential loss of RCS APPLICABILITY: Operating Conditions 1 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 Rihr BASES: This indicator is considered to be a loss of the RCS barrier. A 70 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a loss of the Reactor Coolant System barrier. This value assumes a 0.1% clad damage and the instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. The value of 0.1% clad damage was assumed to be the greatest amount of fuel failure under which power operation could occur. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation Engineering Calculation No. NE-02-94-57 WNP-2 Plant Specific EAL Guideline, RCS3.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 17 of 157

I Reactor Fuel 1.2 Radiation Monitors 1.2.S.1 Site Area Emergency NUMARC IC: Loss or potential loss of any two fission product barriers APPLICABILITY: Operating Conditions 11 2 13 I I EMERGENCY ACTION LEVEL: Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 3,600 R/hr BASES: This indicator is considered to be a loss of both the RCS and fuel clad barriers. A 3,600 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a release of reactor coolant, with elevated activity indicative of fuel damage, into the drywell. Therefore, this condition represents loss of both the fuel clad and RCS barriers. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory associated with coolant concentration associated with 5% clad failures into the drywell atmosphere. WNP-2 has elected to provide an example dealing with the top end of the 2-5% range discussed in NESP-007. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation Engineering Calculation No. NE-02-94-57 WNP-2 Plant Specific EAL Guideline, FC3.1 (RCS3.1) Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 18 of 157

1 Reactor Fuel 1.2 Radiation Monitors 1.2.G.1 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1112 13 1 1 7 ] EMERGENCY ACTION LEVEL: Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 14,000 R/hr BASES: This indicator is considered to be a loss of both the RCS and fuel clad barriers with the potential loss of PC. A 14,000 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate potential failure of the primary containment barrier. It is a value that indicates significant fuel damage well in excess of that associated with the loss of both Fuel Clad and RCS barriers. A major release of radioactivity requiring offsite protective actions is not possible unless a major failure of fuel cladding allows radioactive material to be released from the core into the reactor coolant. Regardless of whether containment is challenged, this amount of activity in containment, if released, could have such severe consequences that it is prudent to treat this as a potential loss of containment, such that a General Emergency declaration is warranted. This level of activity is indicative of approximately 20% clad failure. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation Engineering Calculation No. NE-02-94-57 WNP-2 Plant Specific EAL Guideline, PC3.1 (FC3.1, RCS3.1) 1 Reactor Fuel 1.2 Radiation Monitors Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 19 of 157

1.2.G.2 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1 12 13 1 1 1 EMERGENCY ACTION LEVEL: Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 3,600 R/hr AND ANY--of following:

  • Cannot maintain plant parameters within HCTL, SRVTPLL, or PSP
  • Drywell pressure response not consistent with LOCA conditions
  • An PC Loss Indicators, Table 2 BASES:

This combination of conditions is considered to be a loss of both the RCS and fuel clad barriers with the loss or potential loss of PC. A 3,600 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a release of reactor coolant, with elevated activity indicative of fuel damage, into the drywell. Therefore, this condition represents loss of both the fuel clad and RCS barriers. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory associated with coolant concentration associated with 5% clad failures into the drywell atmosphere. WNP-2 has elected to provide an example dealing with the top end of the 2-5% range discussed in NESP-007. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. The Heat Capacity Temperature Limit (HCTL) is the highest wetwell temperature at which initiation of RPV depressurization will not result in exceeding the Primary Containment Pressure Limit (PCPL) before the rate of energy transfer to the containment is within the capacity of the containment vent. The HCTL is used to preclude failure of the containment or equipment necessary for safe shutdown by assuring that RPV blowdown does not cause containment pressure to exceed the PCPL. The potential loss occurs when RPV pressure and wetwell temperature cannot be maintained below HCTL. The SRV Tail Pipe Level Limit (SRVTPLL) is the highest wetwell water level at which opening of an SRV will not result in exceeding the code allowable stresses in the tailpipe, tailpipe supports, quenchers or quencher supports. This level is a function of RPV pressure and the Limit is utilized to preclude SRV system failure and containment failure. The consequences of operating SRVs when wetwell water level exceeds the SRVTPLL may include direct pressurization of the containment from a break in the SRV tail pipe. The resulting primary containment pressurization could cause containment failure. Entry into the unsafe region of the Pressure Suppression Pressure curve (PPM 5.2.1, "Primary Containment Control", Figure F, PSP) is included as a potential primary containment barrier loss. A rapid depressurization of the RPV (e.g., occurrence of a large break LOCA or initiation of ADS) at wetwell pressures in excess of the PSP may cause either: Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 720 of 157

  • Wetwell pressure responses indicative of a failure in the drywell-to-wetwell boundary, or Wetwell pressure increases to or beyond the Primary Containment Pressure Limit (PPM 5.2.1, "Primary Containment Control", Figure B, PCPL).

Containment or drywell pressure responses not consistent with LOCA conditions indicate a loss of the Primary Containment barrier. This may be noticed as a decrease in drywell pressure when no operation action (e.g., starting drywell cooling fans) has been taken. It would also include a failure of the drywell pressure to increase as expected during a LOCA. Refer to Attachment 4.2 for the bases of each of the following referenced PC barrier loss indicators. Table 2 PC Barrier Loss Indicators

 "*    Rapid unexplained decrease of PC pressure following an initial increase
 "*    Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists REFERENCE(S):

NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation Engineering Calculation No. NE-02-94-57 WNP-2 Plant Specific EAL Guideline, FC3.1 + PCl.5, PC5.2, PC1.1, PC1.2, PC2.1

1 Reactor Fuel 1.3 Refueling Incidents 1.3.U.1 Unusual Event NUMARC IC: AU2 - Unexpected decrease in water covering irradiated fuel assemblies APPLICABILITY: Operating Conditions Ii1 2 13 14 15 Idef - EMERGENCY ACTION LEVEL: Uncontrolled water level decrease in the reactor cavity or SFP below the level of the weirs with all irradiated fuel assemblies remaining covered by water BASES: The SFP cooling system weirs were chosen as a readily identifiable level. In addition to being readily visible from the refueling floor, dropping below the level of the weir, only a few inches, impairs the operability of the SFP cooling system with subsequent alarms. These events tend to have long lead times relative to potential for radiological release outside the site boundary thus, the impact to public health and safety is very low. Uncontrolled water level decrease may result in unplanned increases in in plant radiation levels represent a degradation in the control of radioactive material and represent a potential degradation in the level of safety of the plant. This EAL escalates to an ALERT per EAL 1.3.A.2 if the water level drops lower to the level of the gates. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event AU2 WNP-2 Plant Specific EAL Guideline, AU2. 1, AU2.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 22 of 157

1 Reactor Fuel 1.3 Refueling Incidents 1.3.A. 1 Alert NUMARC IC: AA2 - Major damage to irradiated fuel or loss of water level that has resulted or will result in the uncovering of irradiated fuel outside the RPV APPLICABILITY: Operating Conditions I1 12 13 14 K Idef I EMERGENCY ACTION LEVEL: HIGH alarm on ARM-RIS-1 (Fuel Pool ARM) resulting from an uncontrolled irradiated fuel handling process BASES: Due to the decreased amount of decay heat present, there is time available to take corrective actions and little potential for substantial fuel damage. In addition, NUREG/CR-4982, "Severe Accident in Spent Fuel Pools in Support of Generic Safety Issue 82," July 1987, indicates that even if corrective actions are not taken, no prompt fatalities are predicted, and that risk of injury is low. The setpoint for the listed ARM is given in PPM 4.602.A5 1-1. After review of refuel floor radiation monitoring calpability it was determined that three of the four ARMs included in this EAL should not be listed for the following reasons. ARM-RIS-3 and ARM-RIS-3A detect radiation near the bottom of the new fuel storage pit and, therefore, would not provide adequate indication of radiation levels associated with decreasing water level above irradiated fuel. ARM-RIS-2, Fuel Pool Area Radiation Monitor, alarm setpoint is arbitrarily adjusted to a level slightly above normal background to monitor operator performance during fuel handling and would, therefore, not be indicative of a potential refueling accident. Its high alarm setpoint is typically 15 mrem/hr. The high alarm on ARM-RIS-1, Fuel Pool Area Radiation Monitor, is the threshold condition for this EAL. Its setpoint is nominally 300 mrem/hr. The EAL is worded so that the alarm must be the result of an uncontrolled irradiated fuel handling process avoiding an unnecessary declaration if the condition were caused by a spurious alarm signal or condition not related to fuel handling. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 23 of 157

REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, AA2 NUTREG/CR-4982, Severe Accident in Spent Fuel Pools in Support of Generic Safety, Issue 82, July 1987 WNP-2 Plant Specific EAL Guideline, AA2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 24 of 157

1 Reactor Fuel 1.3 Refueling Incidents 1.3.A.2 Alert NUMARC IC: AA2 - Loss of water level that has or will result in the uncovering of irradiated fuel outside the reactor vessel. APPLICABILITY: Operating Conditions 1 2 3 4 15 def EMERGENCY ACTION LEVEL: Water level, when not intentionally lowered, observed to be below the top of the gate sill separating the reactor cavity and the SFP BASES: Unintentional water level decrease may result in unplanned increases in in plant radiation levels which represent a degradation in the control of radioactive material and represent a potential degradation in the level of safety of the plant. No level indication is available in Reactor Cavity or spent fuel pools for monitoring pool level outside of a narrow band around the normal operating range. In lieu of using a visual observation of pool level below top of fuel racks, the bottom of the water gates between the pools were chosen as a reference point for classification purposes. The intent of this EAL is to allow observations from plant personnel to be factored into the declaration and is not intended to direct an entry into an area solely to observe pool level. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, AA2 NUREG 0818, Emergency Action Levels for Light Water Reactors NUREG/CR-4982, Severe Accident in Spent Fuel Pools in Support of Generic Safety, Issue 82, July 1987 WNP-2 Plant Specific EAL Guideline, AA2.4

1 Reactor Fuel 1.3 Refueling Incidents 1.3.A.3 Alert NUMARC IC: AA2 - Loss of water level that has or will result in the uncovering of irradiated fuel outside the reactor vessel. APPLICABILITY: Operating Conditions 11 12 13 14 15 Idef I EMERGENCY ACTION LEVEL: Report of visual observation of irradiated fuel uncovered or uncovering imminent BASES: Unintentional water level decrease may result in unplanned increases in in plant radiation levels which represent a degradation in the control of radioactive material and represent a potential degradation in the level of safety of the plant. No level indication is available in Reactor Cavity or spent fuel pools for monitoring pool level outside of a narrow band around the normal operating range. The intent of this EAL is to allow observations from plant personnel to be factored into the declaration and is not intended to direct an entry into an area solely to observe pool level. The terminology "uncovering imminent" is intended to address conditions in which water level decrease mitigative actions are not being successful. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, AA2 NUREG 0818, Emergency Action Levels for Light Water Reactors NUREG/CR-4982, Severe Accident in Spent Fuel Pools in Support of Generic Safety, Issue 82, July 1987 WNP-2 Plant Specific EAL Guideline, AA2.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 26 of 157

2 REACTOR PRESSURE VESSEL (RPV) The reactor pressure vessel provides a volume for the coolant which covers the reactor core. The RPV and associated pressure piping (reactor coolant system) together provide a barrier to limit the release of radioactive material should the reactor fuel cladding integrity fail. There are two RPV parameters which are indicative of conditions which may pose a threat to RPV or fuel cladding integrity: RPV Water Level: RPV water level is directly related to the status of adequate core cooling, and therefore fuel cladding integrity. Excessive reactor coolant to drywell leakage indications are utilized-io indicate potential pipe cracks which may propagate to an evtent threatening fuel clad, RPV and primary containment integrity. Conditions under which all attempts at establishing adequate core cooling have failed require primary containment flooding. Reactivity Control: The inability to control reactor power below certain levels can pose a direct threat to reactor fuel, RPV and primary containment integrity. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 27 of 157

2 RPV 2.1 RPV Water Level 2.1.U.1 Unusual Event NUMARC IC: SU5 - RCS Leakage APPLICABILITY: Operating Conditions 1 12 13 t 1 1 1 EMERGENCY ACTION LEVEL: Valid unidentified leakage GE 10 gpm or upscale high indicated on recorder EDR-FRS-623, Pen 1 (P632) (non-RCC) OR Valid identified leakage GE 25 gpm indicated on recorder EDR-FRS-623, Pen 2 (P632) BASES: This Initiating Condition may be a precursor of more serious conditions and, as a result, is considered to be a potential degradation in the level of safety of the plant. The value for identified leakage is set at a higher value due to the lesser significance of identified leakage in comparison to unidentified and pressure boundary leakage. RCC is not considered part of RCS leakage for this EAL. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU5 WNP-2 Plant Specific EAL Guideline, SU5.1

2 RPV 2.1 RPV Water Level 2.1 .A. 1 Alert NUMARC IC: Loss or potential loss of RCS APPLICABILITY: Operating Conditions 11 12 13 1 1 1 EMERGENCY ACTION LEVEL: Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high BASES: Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623 pen 1 (unidentified - Floor Drain Sump FillRate) and pen 2 (identified - Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (pen 2) in the Control Room at WNP-2 is 30 gpm, therefore 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, RCS1.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 29 of 157

2 RPV 2.1 RPV Water Level 2.1.S.1 Site Area Emergency NUMARC IC: Loss or potential loss of any two fission product barriers APPLICABILITY: Operating Conditions 1 2 13 14 15 EMERGENCY ACTION LEVEL: RPV level LT-161 inches (for ATWS conditions, RPV level LT -192") or cannot be determined. I BASES: This EAL represents a loss of RCS barrier and potential loss of fuel clad. Indicating fuel clad barrier potential loss at -161" (Top of Active Fuel) or -192" (for ATWS conditions) ensures that an emergency is declared before fuel perforation occurs. A level decrease to below -161" or -192" (for ATWS conditions) is also indicative of a large RCS break, or a smaller break with loss of high pressure makeup. This also represents conditions where RPV level cannot be determined, such as entry into PPM 5.1.4, RPV Flooding. During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192" (minimum steam cooling RPV water level). REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, SS5.1, FC2.2/RCS4.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 30 of 157

2 RPV 2.1 RPV Water Level 2.1.G.1 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Entry into Severe Accident Guidelines BASES: This EAL represents loss of both fuel clad and RCS in conjunction with a potential loss of containment. Entry into Severe Accident Guidelines is indicative of both a loss of fuel clad and RCS barriers because:

1) RPV water level cannot be restored and maintained above -161 inches, or
2) For ATWS conditions, RPV water level cannot be maintained above -192", or
3) If RPV water level cannot be determined, RPV flooding for ATWS or non-ATWS conditions cannot be established or maintained.

During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192" (minimum steam cooling RPV water level). Entry into PPM 5.1.7, "PC Flooding" is indicative of a potential loss of primary containment because actions to flood the containment may jeopardize the pressure suppression capability of the containment or result in the need to vent the RPV or primary containment. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC2. l/PC4.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 31 of 157

2 RPV 2.1 RPV Water Level 2.1.G.2 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1112 13 1 1 EMERGENCY ACTION LEVEL: RPV level LT -161 inches (for ATWS conditions, RPV level LT -192") or cannot be determined I AND ANY of following:

  • Rapid unexplained decrease of PC pressure following an initial increase Drywell pressure response not consistent with LOCA conditions Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists BASES:

This EAL represents loss of both RCS and PC in conjunction with a potential loss of fuel clad. Indicating fuel clad barrier potential Loss at -161" (Top of Active Fuel) or -192" (for ATWS conditions) ensures that an emergency is declared before fuel perforation occurs. An unintentional level decrease to below -161" (or -192" during ATWS conditions) is also indicative of a large RCS break, or a smaller break with loss of high pressure makeup. During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192" (minimum steam cooling RPV water level). Rapid unexplained loss of pressure (i.e., not attributable to drywell spray or condensation effects) following initial pressure increase indicates a loss of containment integrity. In interpreting this EAL, an initial increase is any PC pressure increase above 1.68 psig. A rapid decrease should be considered any decrease which occurs faster than the initial increase. Containment or drywell pressure responses not consistent with LOCA conditions indicate a loss of the Primary Containment barrier. This may be noticed as a decrease in drywell pressure when no operation Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 17 32 of 157

action (e.g., starting drywell cooling fans) has been taken. It would also include a failure of the drywell pressure to increase as expected during a LOCA. The failure to isolate condition is intended to cover containment isolation failures allowing a direct flow path to the environment such as a failure of MSIVs to close with open valves downstream to the turbine or condenser. Downstream path outside primary containment does not mean leakage incident to normal system integrity. Only those penetrations required to isolate per Technical Specifications should be considered. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC2.2/RCS4.1 + PCI.1, PCl.2, PC2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 33 of 157

2 RPV 2.2 Reactivity Control 2.2.U. 1 Unusual Event NUMARC IC: SU8 - Inadvertent Criticality. An extended and unplanned positive period or sustained positive period observed on nuclear instrumentation while not performing a reactor startup. APPLICABILITY: Operating Conditions 1 12 13 14 15 1 EMERGENCY ACTION LEVEL: An extended and unplanned sustained positive period observed on NIs while NOT performing a reactor startup. BASES: Inadvertent criticalities indicate a potential degradation of the level of safety of the plant. This EAL excludes inadvertent criticalities that occur during planned reactivity changes associated with reactor startups, such as achieving criticality earlier than estimated. The term extended is used in order to allow exclusion of expected short term positive periods from planned fuel bundle or control rod movement during core alterations. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, final draft rev 3, Unusual Event SU8. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 1 34 of 157

2 RPV 2.2 Reactivity Control 2.2.A.1 Alert NUMARC IC: SA2 - Failure of Reactor Protection System (RPS) instrumentation to complete or initiate a reactor scram AND manual scram was successful. APPLICABILITY: Operating Conditions 1 1 2 1 1 1 - EMERGENCY ACTION LEVEL:

&y RPS setpoint (including manual) has been exceeded per T.S. 3.3.1.1 AND RPS actuation failed to result in a control rod pattern which alone always assures reactor shutdown under all conditions AND Manual actions (mode switch in shutdown, manual push buttons, and ARI) result in reactor power LE 5%.

BASES: This condition indicates a failure of the automatic protection system to scram the reactor sufficient to achieve shutdown under all conditions without boron but the reactor was successfully manually scrammed sufficient to achieve shutdown under all conditions without boron. A manual scram is any set of actions by the reactor operator(s) which results in a scram. These actions include placing the reactor mode switch in shutdown, depressing the RPS Manual Scram push buttons and/or placing ARI switches to trip. Failure of a manual scram to reduce reactor power below APRM downscale levels or resulting in exceeding 110 degrees F in the suppression pool would escalate this event to Site Area Emergency 2.2.S. 1. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert SA2 WNP-2 Emergency Operating Procedure Flowchart Training Manual, PPM 5.0.10 WNP-2 Plant Specific EAL Guideline, SA2.1

2 RPV 2.2 Reactivity Control 2.2.S.1 Site Area Emergency NUMARC IC: SS2 - Failure of RPS instrumentation to complete or initiate an automatic reactor scram once a RPS setpoint has been exceeded AND manual scram was NOT successful. APPLICABILITY: Operating Conditions 11 12 1 -1 EMERGENCY ACTION LEVEL:

&y RPS setpoint (including manual) has been exceeded per T.S. 3.3.1.1 AND RPS actuation failed to result in a control rod pattern which alone always assures reactor shutdown under all conditions AND either:

Reactor power GT 5% or unknown OR Wetwell temperature GT 110 'F BASES: This condition indicates a failure of both the automatic protection system and manual efforts to scram the reactor with continued power generation. A manual scram is any set of actions by the reactor operator(s) which results in a scram. These actions include placing the reactor mode switch in shutdown, depressing the RPS Manual Scram push buttons and/or placing ARI switches to trip. Injection of boron is not considered in reducing reactor power below 5%. A concurrent challenge to the ability to cool the core or a significant challenge to decay heat removal capability would escalate this event to General Emergency 2.2.G. 1. As specified in the NUMARC/NESP-007 Questions and Answers, January 1993, ... a scram is considered unsuccessful if it does not result in achieving a state in which the reactor will remain shutdown under all conditions without boron injection." For 2.2.A.1, if manual actions result in the reactor being shutdown under all conditions without boron injection, an ALERT is declared. Escalation to a Site Area Emergency (2.2.S.1) is not required. If sufficient control rods are not inserted to reduce reactor power to below the APRM downscale setpoints, an immediate Site Area Emergency (2.2.S. 1) is declared. If the APRM downscale setpoint is achieved, but suppression pool temperature is greater than Boron Injection Initiation Temperature (1l17°), a precursor exists for a threat to containment and thus a "Site Area Emergency is warranted." APRM downscale trip setpoint for WNP-2 is 5%, the Boron Injection Initiation Temperature is defined as 1 10°F. The conditions "... control rod pattern which alone always assures reactor shutdown" is defined to mean that the reactor is shutdown under all conditions without boron. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 36 of 157

REFERENCE(S): WNP-2 Emergency Operating Procedure RPV Control-ATWS, PPM 5.1.2 WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site General Emergency SS2 WNP-2 Plant Specific EAL Guideline, SS2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 37 of 157

2 RPV 2.2 Reactivity Control 2.2.G.1 General Emergency NUMARC IC: SG2 - Failure of the RPS to complete an automatic scram AND manual scram was NOT successful AND there is indication of an extreme challenge to the ability to cool the core. APPLICABILITY Operating Condittions 1 1 12 1 1 1 1 1 EMERGENCY ACTION LEVEL: AW RPS setpoint (including manual) has been exceeded per T.S. 3.3.1.1 AND RPS actuation failed to result in a control rod pattern which alone always assures reactor shutdown under all conditions AND Wetwell temperature cannot be maintained LT the HCTL BASES: This condition indicates a failure of both the automatic protection system and manual efforts at Control Room Panel P-603 to scram the reactor concurrent with a challenge to the ability to cool the core or a significant challenge to decay heat removal capability. Heat removal capability is extremely challenged if the wetwell temperature cannot be maintained below the Heat Capacity Temperature Limit curve. A manual scram is any set of actions by the reactor operator(s) which results in a scram. These actions include placing the reactor mode switch in shutdown, depressing the RPS Manual Scram push buttons and/or placing ARI switches to trip. Injection of boron is not considered in reducing reactor power below 5%. REFERENCE(S): WNP-2 Emergency Operating Procedure RPV Control-ATWS, PPM 5.1.2 WNP-2 Emergency Operating Procedure Primary Containment Flooding, PPM 5.1.7 WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, General Emergency SG2 WNP-2 Plant Specific EAL Guideline, SG2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 38 of 157

3 PRIMARY CONTAINMENT (PC) The primary containment structure is a pressure suppression system. It forms a fission product barrier designed to limit the release of radioactive fission products generated from any postulated accident so as to preclude exceeding offsite exposure limits. The primary containment structure is a low leakage pressure suppression system housing the reactor pressure vessel (RPV), the reactor coolant recirculation piping and other branch connections of the reactor primary system. The primary containment is equipped with isolation valves for most systems which penetrate the containment boundary. These valves automatically actuate to isolate systems under emergency conditions. There are four primary containment parameters which are indicative of conditions which may pose a threat to primary containment integrity or indicate degradation of RPV or reactor fuel integrity. Primary Containment Pressure: Excessive primary containment pressure is also indicative of either primary system leaks into containment or loss of containment cooling function. Primary containment pressures at or above specified limits pose a direct threat to primary containment integrity and the pressure suppression function. Wetwell Temperature/Level: Excessive suppression pool water temperatures or abnormally high or low wetwell levels can result in a loss of the pressure suppression capability of containment and thus be indicative of severely degraded RPV and containment conditions. Combustible Gas Concentration: The existence of combustible gas concentrations in containment pose a severe threat to containment integrity and are indicative of severely degraded reactor core and RPV conditions. Containment Isolation Status: The existence of an unisolable steam line break outside containment constitutes a loss of containment integrity as well as a loss of RCS boundary. Should a loss of fuel cladding integrity occur, the potential for release of large amounts of radioactive materials to the environment exists. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 39 of 157

3 Primary Containment 3.1 Primary Containment Pressure 3.1.U.1 Unusual Event NUMARC IC: Loss or potential loss of primary containment APPLICABILITY: Operating Conditions 11 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Rapid unexplained decrease of PC pressure following an initial increase BASES: This indicator is considered to be a loss of the PC barrier. Rapid unexplained loss of pressure (i.e., not attributable to drywell spray or condensation effects) following initial pressure increase indicates a loss of containment integrity. In interpreting this EAL, an initial increase is any PC pressure increase above 1.68 psig. A rapid decrease should be considered any decrease which occurs faster than the initial increase. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC1.1

3 Primary Contaimnment 3.1 Primary Containment Pressure 3.1.A.1 Alert NUMARC IC: Loss or potential loss of either fuel clad or RCS APPLICABILITY: Operating Conditions 1 12 13 1 1 T-EMERGENCY ACTION LEVEL: Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell BASES: This indicator is considered to be a loss of the RCS barrier. The 1.68 psig drywell pressure for the Reactor Coolant System barrier loss is based on the drywell pressure scram and isolation setpoint and indicates a Loss of Coolant Accident (LOCA). A potential loss of the Reactor Coolant System barrier would not result in an increasing drywell pressure and, therefore, no indicator is provided. The qualifier of "with indications of RCS leak inside drywell" is included as an indicator of RCS boundary degradation and eliminates a drywell pressure increase due to a loss of drywell ventilation. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, RCS2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 1 41 of 157

3 Primary Containment 3.1 Primary Containment Pressure 3.1.S.1 Site Area Emergency NUMARC IC: Loss or potential loss of any two fission product barriers APPLICABILITY: Operating Conditions I11 2 13:- EMERGENCY ACTION LEVEL: Drywell pressure response not consistent with LOCA conditions BASES: This indicator is considered to be a loss of both the RCS and PC barriers. Containment or drywell pressure responses not consistent with LOCA conditions indicate a loss of the Primary Containment barrier. This may be noticed as a decrease in drywell pressure when no operation action (e.g., starting drywell cooling fans) has been taken. It would also include a failure of the drywell pressure to increase as expected during a LOCA. Also, a loss of suppression function in conjunction with a LOCA would indicate a loss of the Primary Containment barrier. Exceeding PSP is an indication of loss of pressure suppression function. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC2.1

3 Primary Contaimnment 3.1 Primary Containment Pressure 3.1.S.2 Site Area Emergency NUMARC IC: Loss or potential loss of either fuel clad or RCS barrier in conjunction with a loss of containment APPLICABILITY: Operating Conditions 11 12 13 1 1I EMERGENCY ACTION LEVEL: Rapid unexplained decrease of PC pressure following an initial increase AND ANY of the following:

  • Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high
  • Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr
  • Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell BASES:

This indicator is considered to be a loss of both the RCS and PC barriers. Rapid unexplained loss of pressure (i.e., not attributable to drywell spray or condensation effects) following initial pressure increase indicates a loss of containment integrity. In interpreting this EAL, an initial increase is any PC pressure increase above 1.68 psig. A rapid decrease should be considered any decrease which occurs faster than the initial increase. Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623 pen 1 (unidentified - Floor Drain Sump Fill Rate) and pen 2 (identified - Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (pen 2) in the Control Room at WNP-2 is 30 gpm, therefore 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. A 70 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a loss of the Reactor Coolant System barrier. This value assumes a 0.1% clad damage and the instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. The value of 0.1% clad damage was assumed to be the greatest amount of fuel failure under which power operation could occur. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 43 of 157

The 1.68 psig drywell pressure for the Reactor Coolant System barrier loss is based on the drywell pressure scram and isolation setpoint and indicates a Loss of Coolant Accident (LOCA). A potential loss of the Reactor Coolant System barrier would not result in an increasing drywell pressure and, therefore, no indicator is provided. The qualifier of "with indications of RCS leak inside drywell" is included as an indicator of RCS boundary degradation and eliminates a drywell pressure increase due to a loss of drywell ventilation. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC1.1 + RCS1.2, RCS3.1, RCS2.1

3 Primary Containment 3.1 Primary Containment Pressure 3.1.G.1 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1 12 13 1 1 EMERGENCY ACTION LEVEL: PC pressure exceeds PCPL BASES: This indicator is considered to be a loss of both the Fuel Clad and RCS barriers in conjunction with the potential loss of PC. Containment pressures that exceeds 34.7 psig, the maximum expected pressure following a LOCA, have the potential to result in a loss of the containment barrier. Preparations to vent containment are required by PPM 5.2.1, "Primary Containment Control" before the Wetwell pressure reaches the Primary Containment Pressure Limit (PCPL). Therefore this condition is considered a potential loss of containment. With PC pressure GT PCPL and increasing, a loss of the RCS barrier has occurred due to the elevated containment pressure. Continued wetwell pressure increase could result in complete and uncontrolled loss of the primary containment due to containment failure. With no assurance as to where the containment may fail, an attendant loss of the suppression pool should be assumed with a consequent complete and unrecoverable loss of core cooling whereby the degraded core condition and loss of containment integrity releases substantial amounts of radioactivity to the general environment. Therefore, this condition is also considered to be a loss of both fuel clad and RCS. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC 1.3 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 45 of 157

3 Primary Containment 3.2 Wetwell Temperature/Level 3.2.U. 1 Unusual Event NUMARC IC: Loss or potential loss of primary containment APPLICABILITY: Operating Conditions 11 122 133 ] EMERGENCY ACTION LEVEL: Cannot maintain plant parameters within SRVTPLL BASES: This indicator is considered to be a potential loss of the PC barrier. The SRV Tail Pipe Level Limit (SRVTPLL) is the highest wetwell water level at which opening of an SRV will not result in exceeding the code allowable stresses in the tailpipe, tailpipe supports, quenchers or quencher supports. This level is a function of RPV pressure and the Limit is utilized to preclude SRV system failure and containment failure. The consequences of operating SRVs when wetwell water level exceeds the SRVTPLL may include direct pressurization of the containment from a break in the SRV tail pipe. The resulting primary containment pressurization could cause containment failure. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC1.5

3 Primary Contaimnment 3.2 Wetwell Temperature/Level 3.2.S.1 Site Area Emergency NUMARC IC: Loss or potential loss of any two fission product barriers SS4 - Complete loss of functions needed to achieve and maintain hot shutdown. APPLICABILITY: Operating Conditions I112 13 1 1 1 1 EMERGENCY ACTION LEVEL: RPV pressure and wetwell temperature cannot be maintained below HCTL BASES: This indicator is considered to be a loss of the RCS in conjunction with a potential loss of the PC barrier. This condition also is representative of a loss of ability to maintain the plant in hot shutdown. This EAL addresses complete loss of functions, including ultimate heat sink and reactivity control, required for hot shutdown with the reactor at pressure and temperature. Under these conditions, there is an actual major failure of a system intended for protection of the public. Thus, declaration of a Site Area Emergency is warranted. Escalation to a General Emergency would occur by Abnormal Rad Levels/Radiological Effluent, Fission Product Barrier Degradation, or Emergency Director Judgment Initiating Conditions. Functions required for hot shutdown consist of the ability to achieve reactor shutdown and to discharge decay heat energy from the reactor to the ultimate heat sink. Appropriate emergency declarations required by the inability to achieve reactor shutdown are addressed by EALs 2.2.A. 1, 2.2.S. 1 and 2.2.G. 1. Inability to remove decay heat energy is reflected in an increase in suppression pool temperature. Elevated suppression pool temperature is addressed by the Heat Capacity Temperature Limit (HCTL). The HCTL is a function of RPV pressure and suppression pool temperature. If RPV pressure and suppression pool temperature cannot be maintained below the HCTL, the ultimate heat sink is threatened and declaration of a Site Area Emergency is warranted. The Heat Capacity Temperature Limit (HCTL) is the highest wetwell temperature at which initiation of RPV depressurization will not result in exceeding the Primary Containment Pressure Limit (PCPL) before the rate of energy transfer to the containment is within the capacity of the containment vent. The Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 47 of 157

HCTL is used to preclude failure of the containment or equipment necessary for safe shutdown by assuring that RPV blowdown does not cause containment pressure to exceed the PCPL. The potential loss occurs when RPV pressure and wetwell temperature cannot be maintained below HCTL. This indicator is also considered to be a loss of RCS barrier in that a wetwell temperature rise sufficient to exceed the HCTL could only be the result of a sustained discharge of a primary system into the wetwell. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency, SS4 WNP-2 Plant Specific EAL Guideline, SS4.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 48 of 157

3 Primary Containment 3.2 Wetwell Temperature/Level 3.2.S.2 Site Area Emergency NUMARC IC: Loss or potential loss of any two fission product barriers APPLICABILITY: Operating Conditi-ons 11 2 213 1 71 EMERGENCY ACTION LEVEL: Cannot maintain plant parameters within SRVTPLL, or PSP AND ANY of the following:

  • Total RCS leakage GT 30 GPM inside PC or EDR-FRS-623, Pen 2 upscale high
  • Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr
  • Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell BASES:

This indicator is considered to be a potential loss of PC in combination with a loss or potential loss of RCS barrier. The inability to maintain plant parameters within the SRVTPLL, or PSP represents a potential loss of PC. The SRV Tail Pipe Level Limit (SRVTPLL) is the highest wetwell water level at which the opening of an SRV will not result in exceeding the code allowable stresses in the tailpipe, tailpipe supports, quenchers or quencher supports. This level is a function of RPV pressure and the Limit is utilized to preclude SRV system failure and containment failure. The consequences of operating SRVs when wetwell water level exceeds SRVTPLL may include direct pressurization of the containment from a break in the SRV tailpipe. The resulting primary containment pressurization could cause containment failure. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 49 of 157

Entry into the unsafe region of the Pressure Suppression Pressure curve (PPM 5.2.1, "Primary Containment Control", Figure F, PSP) is included as a potential primary containment barrier loss. A rapid depressurization of the RPV (e.g., occurrence of a large break LOCA or initiation of ADS) at wetwell pressures in excess of the PSP may cause either:

  • Wetwell pressure responses indicative of failure in the drywell-to-wetwell boundary, or Wetwell pressure increases to or beyond the Primary Containment Pressure Limit (PPM 5.2.1, "Primary Containment Control", Figure B, PCPL).

Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623, Pen 1 (unidentified Floor Drain Sump Fill Rate) and Pen 2 (identified Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (Pen 2) in the Control Room at Columbia Generating Station is 30 gpm, therefore, 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. A 70 R/hr reading on CMS-RIS-27e and CMS-RIS-27F is used to indicate a loss of the Reactor Coolant System barrier. This value assumes a 0.1% clad damage and the instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. The value of 0.1% clad damage was assumed to be the greatest amount of fuel failure under which power operation could occur. The 1.68 psig drywell pressure for the Reactor Coolant System barrier loss is based on the drywell pressure scram and isolation setpoint and indicates a Loss of Coolant Accident (LOCA). A potential loss of the Reactor Coolant System barrier would not result in an increasing drywell pressure and, therefore, no indicator is provided. The qualifier of "with indications of RCS leak inside the drywell" is included as an indicator of RCS boundary degradation and eliminates a drywell pressure increase due to loss of drywell ventilation. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC1.5/PC5.2 + RCS1.2, RCS3.1, RCS2.1

3 Primary Containment 3.3 Combustible Gas Concentrations 3.3.G.1 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 11 2 133 21 EMERGENCY ACTION LEVEL: PC H2 and 02 concentrations GT 6% H2 and 5% 02 BASES: This indicator represents a loss of both the fuel clad and RCS with a potential loss of the PC barrier. Hydrogen and Oxygen concentrations at or above PPM 5.2.1, "Primary Containment Control", Table 19, Combustible Limits, in the drywell or wetwell represent a potential for a deflagration with a subsequent containment failure. When hydrogen and oxygen concentrations approach or exceed combustible limits (6% hydrogen and 5% oxygen, respectively), the fuel clad barrier has been lost because, in order to reach such hydrogen concentration levels, it would have been necessary to overheat the fuel to metal-water reaction temperatures. For these concentrations to be detected in the primary containment would also indicate that, as a minimum, a potential loss of the RCS barrier has occurred. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC1.4 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 51 of 157

3 Primary Containment 3.4 Containment Isolation Status 3.4.U. 1 Unusual Event NUMARC IC: Loss or potential loss of primary containment APPLICABILITY: Operating Conditions 11 12 13 1 1 1 EMERGENCY ACTION LEVEL: Failure of containment isolation valves (LCS Table 1.6.1.3-1) in any one line to close following auto or manual initiation AND downstream pathway outside primary containment exists BASES: This indicator is considered to be a loss of the PC barrier. The failure to isolate condition is intended to cover containment isolation failures allowing a direct flow path to the environment such as a failure of MSIVs to close with open valves downstream to the turbine or condenser. Downstream path outside primary containment does not mean leakage incidental to normal system integrity. Only those penetrations required to isolate per Technical Specifications should be considered. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 52 of 157

3 Primary Containment 3.4 Containment Isolation Status 3.4.A.1 Alert NUMARC IC: Main steam line break outside containment with isolation APPLICABILITY: Operating Conditions 11 12 13 1 1 EMERGENCY ACTION LEVEL: Indications of a MSL break AND MSIV closure has isolated the break BASES: This EAL is based on design basis accident analyses which show that even if MSIV closure occurs within design limits, offsite (Exclusion Area Boundary) dose consequences from a "puff' release could exceed 50 but less than 100 mrem total effective dose equivalent (TEDE). Specifically FSAR Table 15.6-9 demonstrates 53 mrem TEDE. Only MSIV isolation signals that definitely indicate leakage outside primary RCS boundary with a path to the environment are included. Examples of indications of Main Steam Line breaks are, but not limited to: Main Steam Line Tunnel temperature greater than 156'F on LD-TR-608, P-632 and "LEAK DET MSL TUNNEL TEMP HI-HI" alarm(s) on P-601-A2 &/or A3. Main Steam Line Tunnel delta temperature greater than 80'F on LD-TR-61 1, P-632 and "LEAK DET MSL TUNNEL HI-HI" alarm(s) on P601-A2 &/or A3. Main Steam Line flow greater than 140% as indicated by "MSL ISOL MAIN STEAM LINE FLOW HIGH" alarm on P-601-A 11 &/or A12. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Plant Specific EAL Guideline, RCS 1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 53 of 157

3 Primary Contaimnment 3.4 Containment Isolation Status 3.4.S.1 Site Area Emergency NUMARC IC: Loss or potential loss of either fuel clad or RCS barrier in conjunction with a loss or potential loss of containment APPLICABILITY: Operating Conditions 11 2 13 1 1 1 1 EMERGENCY ACTION LEVEL: Failure of containment isolation valves (LCS Table 1.6.3.1-1) in any one line to close following auto or manual initiation AND downstream pathway outside of primary containment exists AND ANY of following:

  • Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high

° Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 70 R/hr

  • Drywell pressure GT 1.68 psig with indications of RCS leakage inside drywell BASES:

This indicator is considered to be a loss of the PC barrier in conjunction with a loss or potential loss of RCS barrier. The failure to isolate condition is intended to cover containment isolation failures allowing a direct flow path to the environment such as a failure of MSIVs to close with open valves downstream to the turbine or condenser. Downstream path outside primary containment does not mean leakage incidental to normal system integrity. Only those penetrations required to isolate per Technical Specifications should be considered. Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623 pen 1 (unidentified - Floor Drain Sump Fill Rate) and pen 2 (identified - Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (pen 2) in the Control Room at WNP-2 is 30 gpm, therefore, 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. A 70 R"hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a loss of the Reactor Coolant System barrier. This value assumes a 0.1% clad damage and the instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. The value

of 0.1% clad damage was assumed to be the greatest amount of fuel failure under which power operation could occur. The 1.68 psig drywell pressure for the Reactor Coolant System barrier loss is based on the drywell pressure scram and isolation setpoint and indicates a Loss of Coolant Accident (LOCA). A potential loss of the Reactor Coolant System barrier would not result in an increasing drywell pressure and, therefore, no indicator is provided. The qualifier of "with indications of RCS leak inside drywell" is included as an indicator of RCS boundary degradation and eliminates a drywell pressure increase due to a loss of drywell ventilation. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC2.1 + RCS 1.2, RCS3.1, RCS2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 55 of 157

3 Primary Containment 3.4 Containment Isolation Status 3.4.S.2 Site Area Emergency NUMARC IC: Loss or potential loss of either fuel clad or RCS barrier in conjunction with a loss or potential loss of containment APPLICABILITY: Operating Conditions 111 2 13 1 EMERGENCY ACTION LEVEL: Indications of a MSL break AND MSIV closure has not isolated the break BASES: This indicator is considered to be a loss of the PC barrier in conjunction with a loss or potential loss of RCS barrier. Examples of indications of Main Steam Line breaks are, but not limited to:

  • Main Steam Tunnel temperature greater than 156°F on LD-TR-608, P-632 and "LEAK DET MSL TUNNEL TEMP HI-HI" alarm(s) on P-601-A2 or A3, or both.
  • Main Steam Line Tunnel delta temperature greater than 80'F on LD-TR-61 1, P-632 and "LEAK DET MSL TUNNEL HI-HI" alarm(s) on P-701-A2 or A3, or both.
  • Main Steam Line flow greater than 140% as indicated by "MSL ISOL MAIN STEAM LINE FLOW HI" alarm on P-601-A 11 or A12, or both.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Plant Specific EAL Guideline, RCS 1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 56 of 157

3 Primary Containment 3.4 Containment Isolation Status 3.4.G. 1 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 1 12 13 1 1 EMERGENCY ACTION LEVEL: Intentional venting of Primary Containment to prevent failure. BASES: This indicator represents a loss of both the fuel clad and RCS with a loss of the PC barrier. Venting, if necessary to prevent failure of primary containment, is included as a loss of primary containment. This is specified in Emergency Operating Procedures when containment hydrogen and oxygen concentrations are in excess of, or cannot be determined to be below, combustible limits or when wetwell pressure approaches PCPL. However, routine venting per PPM 2.3.1, as long as radioactivity release rates are maintained, is not considered a loss of primary containment. For either condition, a loss of the primary containment barrier exists because the containment is being vented. Additional losses and potential losses of fission product barriers that must also occur when either of these conditions occur are discussed below.

a. When wetwell pressure approaches or exceeds the PCPL, a prior loss of the RCS barrier has occurred due to the elevated containment pressure and the requirement to emergency depressurize the RPV at pressures below 39 psig (Pressure Suppression Pressure). Continued wetwell pressure increase could result in complete and uncontrolled loss of the primary containment due to containment failure. With no assurance as to where the containment may fail, an attendant loss of the suppression pool should be assumed with a consequent complete and unrecoverable loss of core cooling whereby the degraded core condition and loss of containment integrity releases substantial amounts of radioactivity to the general environment.
b. When hydrogen and oxygen concentrations approach or exceed combustible limits (6%

hydrogen and 5% oxygen, respectively), the fuel clad barrier has been lost because, in order to reach such hydrogen concentration levels, it would have been necessary to overheat the fuel to metal-water reaction temperatures. For these concentrations to be detected in the primary containment would also indicate that, as a minimum, a potential loss of the RCS barrier has occurred.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC2.1

4 SECONDARY CONTAINMENT (SC) The secondary containment is comprised of the reactor building and associated ventilation, isolation and effluent systems. The secondary containment serves as an effective fission product barrier and is designed to minimize any ground level release of radioactive materials which might result from a serious accident. The reactor building provides secondary containment during reactor operation and serves as primary containment when the reactor is shutdown and the drywell is open, as during refueling. Because the secondary containment is an integral part of the complete containment system, conditions which pose a threat to vital equipment located in the secondary containment are classifiable as emergencies. There are two secondary containment parameters which are indicative of conditions which may pose a threat to secondary containment integrity or equipment located in secondary containment or are indicative of a direct release by a primary system into secondary containment: Secondary Containment Temperatures: Abnormally high secondary containment area temperatures can also pose a threat to the operability of vital equipment located inside secondary containment including RPV water level instrumentation. High area temperatures may limit personnel accessibility to vital areas. High area temperatures may also be indicative of either primary system discharges into secondary containment or fires. Secondary Containment Area Radiation Levels: Abnormally high area radiation levels in secondary containment, although not necessarily posing a threat to equipment operability, may pose a threat to personnel safety and the ability to operate vital equipment due to a lack of accessibility. Abnormally high area radiation levels may also be the result of a primary system discharging into the secondary containment and be indicative of precursors to significant radioactivity release to the environment. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 59 of 157

4 Secondary Containment 4.1 Reactor Building Temperature/Radiation Levels 4.1.S.1 Site Area Emergency NUMARC IC: Loss or potential loss of either fuel clad or RCS barrier in conjunction with a loss or potential loss of containment APPLICABILITY: Operating Conditions 11 2 13 1 1 1 EMERGENCY ACTION LEVEL: Unisolable primary system discharging outside PC resulting in any area temperature or radiation level above Maximum Safe Operating Values (as defined in the Emergency Operating Procedures). BASES: This indicator is considered to be a loss of the PC in conjunction with a potential loss RCS barrier. The presence of elevated area temperatures and/or radiation levels in the secondary containment may be indicative of an unisolable primary system leakage outside the primary containment. These conditions represent a loss of the containment barrier and a potential loss of the RCS barrier. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, RCS 1.3/PC2.3 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 60Oof 157

4 Secondary Containment 4.1 Reactor Building Temperature/Radiation Levels 4.1.G.1 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions 11 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Unisolable primary system discharging outside PC resulting in any area temperature or radiation level above Maximum Safe Operating Values (as defined in the Emergency Operating Procedures). AND ANY of the following: Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 3,600 R/hr RPV level LT -161 inches (for ATWS conditions, RPV level LT -192 inches) or cannot be determined Coolant activity GT 300 iCi/gm dose equivalent iodine BASES: This indicator is considered to be a loss of the PC in conjunction with a loss or potential loss RCS barrier and loss or potential loss of the fuel clad barrier. The presence of elevated area temperatures and/or radiation levels in the secondary containment may be indicative of an unisolable primary system leakage outside the primary containment. These conditions represent a loss of the containment barrier and a potential loss of the RCS barrier. A 3,600 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a release of reactor coolant, with elevated activity indicative of fuel damage, into the drywell. Therefore, this condition represents loss of both the fuel clad and RCS barriers. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory associated with coolant concentration associated with 5% clad failures into the drywell atmosphere. WNP-2 has elected to provide an example dealing with the top end of the 2-5% range discussed in NESP-007. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 61 of 157

Indicating fuel clad barrier potential Loss at -161" (Top of Active Fuel) or -192 inches (for ATWS conditions) ensures that an emergency is declared before fuel perforation occurs. An unintentional level decrease to below -161" or -192 inches is also indicative of a large RCS break, or a smaller break with loss of high pressure makeup. During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192 inches (minimum steam cooling RPV water level. Fuel Clad barrier damage is indicated by a coolant activity of 300 gCi/gm dose equivalent 1-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates significant clad heating and, thus, the Fuel Clad barrier is considered lost. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation Engineering Calculation No. NE-02-94-57 WNP-2 Plant Specific EAL Guideline, RCS1.3/PC2.3 + FCI.1, FC3.1, RCS4.1

5 RADIOACTIVITY RELEASE Many EALs are based on actual or potential degradation of fission product barriers because of the increased potential for offsite radioactivity release. Degradation of fission product barriers though, is not always apparent via non-radiological symptoms. Therefore, direct indication of increased radiological effluents are appropriate symptoms for emergency classification. At lower levels, abnormal radioactivity releases may be indicative of a failure of containment systems or precursors to more significant releases. At higher release rates, offsite radiological conditions may result which require offsite protective actions. There are two basic indications of radioactivity release rates which warrant emergency classifications. Offsite Release: Direct indication of effluent radiation monitoring systems provides a rapid assessment mechanism to determine releases in excess of classifiable limits. Projected offsite doses (based on effluent monitor readings) or actual offsite field measurements indicating doses or dose rates above classifiable limits. Area Radiation: Radiation monitoring systems are specifically designed to provide indication of loss of control of radioactive material in the plant which may impede personnel access to safe shutdown areas. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 63 of 157

5 Radioactivity Release 5.1 Offsite Release 5.1.U.1 Unusual Event NUMARC IC: AU1 - Any unplanned release of gaseous or liquid radioactivity to the environment that exceeds two times ODCM limits for 60 minutes or longer. APPLICABILITY: Operating Conditions I1 12 13 14 15 Idef I EMERGENCY ACTION LEVEL: A valid reading exists which exceeds or is expected to exceed Table 3 column "UE" for GT 60 min. BASES: Unplanned releases that continue for 60 minutes or longer represent an uncontrolled situation and, hence, a potential degradation in the level of safety. The final integrated dose (which is very low in the Unusual Event emergency class) is not the primary concern here; rather, it is the degradation in plant control implied by the fact that the release was not isolated within 60 minutes. It is not intended that the release be averaged over 60 minutes. Further, the ED should not wait until 60 minutes has elapsed, but should declare the event as soon as it is determined that the release will exceed 60 minutes. It is expected that the offsite dose analysis will be performed on the Emergency Dose Projection System (EDPS) using actual meteorology. If the monitor reading(s) is sustained for longer than 60 minutes and the required assessments cannot be completed within this period, then the declaration should be made based on the valid reading. Monitor indications and alarms are based on the methodology of the ODCM which demonstrates compliance with 10 CFR 20 and 10 CFR 50, Appendix I, requirements. The six year average meteorology is also used for basing alarm setpoints. REFERENCE(S): WNP-2 Technical Specifications WNP-2 Offsite Dose Calculation Manual NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event AU1 WNP-2 Plant Specific EAL Guideline, AU 1.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 64 of 157

5 Radioactivity Release 5.1 Offsite Release 5.1 .U.2 Unusual Event NUMARC IC: AU1 - Any unplanned release of gaseous or liquid radioactivity to the environment that exceeds two times ODCM limits for 60 minutes or longer. APPLICABILITY: Operating Conditions I1 12 13 14 15 1def I EMERGENCY ACTION LEVEL: Offsite dose calculations indicate offsite dose rates GT Table 4 column "UIE" OR Sample analysis indicates release GT 2 times ODCM 6.2.1.1 limits for GT 60 min. BASES: Unplanned releases that continue for 60 minutes or longer represent an uncontrolled situation and, hence, a potential degradation in the level of safety. The final integrated dose (which is very low in the Unusual Event emergency class) is not the primary concern here; rather, it is the degradation in plant control implied by the fact that the release was not isolated within 60 minutes. It is not intended that the release be averaged over 60 minutes. Further, the ED should not wait until 60 minutes has elapsed, but should declare the event as soon as it is determined that the release will exceed 60 minutes. It is expected that the offsite dose analysis will be performed on the Emergency Dose Projection System (EDPS) using actual meteorology. REFERENCE(S): WNP-2 Technical Specifications WNP-2 Offsite Dose Calculation Manual NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event AU1 WNP-2 Plant Specific EAL Guideline, AUl.1

5 Radioactivity Release 5.1 Offsite Release 5.1.A.1 Alert NUMARC IC: AA1 - Any unplanned release of gaseous or liquid radioactivity to the environment that exceeds 200 times the radiological specifications for 15 minutes or longer. APPLICABILITY: Operating Conditions I112 13 14 15 Idef I EMERGENCY ACTION LEVEL: A valid reading exists which exceeds or is expected to exceed Table 3 column "Alert" for GT 15 min. BASES: The required release duration has been reduced to 15 minutes in recognition of the decreased plant safety, and to provide prompt classification. It is expected that the offsite dose analysis will be performed on the Emergency Dose Projection System (EDPS). If the monitor reading(s) is sustained for longer than 15 minutes and the required assessments cannot be completed within this period, then the declaration should be made based on the valid reading. REFERENCE(S): WNP-2 Technical Specifications WNP-2 Offsite Dose Calculation Manual NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event AA1 WNP-2 Plant Specific EAL Guideline, AA1.2

5 Radioactivity Release 5.1 Offsite Release 5.1.A.2 Alert NUMARC IC: AA1 - Any unplanned release of gaseous or liquid radioactivity to the environment that exceeds 200 times the radiological specifications for 15 minutes or longer. APPLICABILITY: Operating Conditions I1 12 13 14 5I def I EMERGENCY ACTION LEVEL: Offsite dose calculations indicate dose rates GT Table 4 column "Alert" OR Sample analysis indicates release GT 200 times ODCM 6.2.1.1 limits for GT 15 min. BASES: The required release duration has been reduced to 15 minutes in recognition of the decreased plant safety, and to provide prompt classification. It is expected that the offsite dose analysis will be performed on the Emergency Dose Projection System (EDPS). If a dose projection cannot be performed and the monitor reading is sustained for longer than the specified time, then the declaration must be made based on the valid reading. REFERENCE(S): WNP-2 Technical Specifications WNP-2 Offsite Dose Calculation Manual NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event AA I WNP-2 Plant Specific EAL Guideline, AA1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 67 of 157

5 Radioactivity Release 5.1 Offsite Release 5.1.S.1 Site Area Emergency NUMARC IC: AS 1 - Offsite dose resulting from an actual or imminent release of gaseous radioactivity that exceeds 100 mrem TEDE or 500 mrem thyroid CDE for the actual or projected duration of the release. APPLICABILITY Operating Conditions 1 2 13 14 15 de EMERGENCY ACTION LEVEL: A valid reading exists which exceeds or is expected to exceed Table 3 column "Site Area" for GT 15 min. BASES: Effluent readings may be used for the classification of fast breaking events until actual dose projections can be made. Dose assessment, since it uses current plant values, will be more accurate and should be used. The 100 mrem integrated dose in this Initiating Condition is based on 10 CFR 20 annual average population exposure. This value also provides a desirable gradient (one order of magnitude) between the Alert, Site Area Emergency and General Emergency classes. It is calculated that exposures less than this time limit are not consistent with the Site Area Emergency class description. The 500 mrem integrated thyroid CDE dose was established in consideration of the 1:5 ratio of the EPA Protection Action Guidelines for TEDE and Thyroid Committed Dose Equivalent. In establishing the emergency action levels, a release duration of one hour is assumed. If an emergency dose projection cannot be performed and the monitor reading(s) is expected to exceed 15 minutes, then the declaration should be made based on the valid reading. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 1 68 of157

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency AS 1 10 CFR 20 WNP-2 Offsite Dose Calculation Manual Environmental Protection Agency 400, Manual of Protective Action Guides and Protective Actions for Nuclear Incidents, October 15, 1991 WNP-2 Plant Specific EAL Guideline, AS 1.3, AS 1.4 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 69 of 157

5 Radioactivity Release 5.1 Offsite Release 5.1.S.2 Site Area Emergency NUMARC IC: AS 1 - Offsite dose resulting from an actual or imminent release of gaseous radioactivity that exceeds 100 mrem TEDE or 500 mrem thyroid CDE for the actual or projected duration of the release. APPLICABILITY-Operating Conditions 1 2 13 14 15 def EMERGENCY ACTION LEVEL: Offsite dose calculations indicate doses or dose rates GT Table 4 column "Site Area" OR Field survey or survey sample analysis indicates offsite dose rates GT Table 4 column "Site Area" BASES: The 100 mrem integrated dose in this Initiating Condition is based on the proposed 10 CFR 20 annual average population exposure. This value also provides a desirable gradient (one order of magnitude) between the Alert, Site Area Emergency and General Emergency classes. It is calculated that exposures less than this time limit are not consistent with the Site Area Emergency class description. The 500 mrem integrated thyroid CDE dose was established in consideration of the 1:5 ratio of the EPA Protection Action Guidelines for TEDE and Thyroid Committed Dose Equivalent. In establishing the emergency action levels, a release duration of one hour is assumed. If an emergency dose projection cannot be performed and the monitor reading(s) is expected to exceed 15 minutes and the required assessments cannot be completed within this period, then the declaration should be made based on the valid reading. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 70 of 157

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency AS 1 10 CFR 20 WNP-2 Offsite Dose Calculation Manual Environmental Protection Agency 400, Manual of Protective Action Guides and Protective Actions for Nuclear Incidents, October 15, 1991 WNP-2 Plant Specific EAL Guideline, AS 1.1

5 Radioactivity Release 5.1 Offsite Release 5.1.G.1 General Ennergency NUMARC IC: AG1 - Offsite dose resulting from an actual or imminent release of gaseous radioactivity that exceeds 1000 mrem TEDE or 5000 mrem thyroid CDE for the actual or projected duration of the release using actual meteorology. APPLICABILITY: Operating Conditions 1112 13 14 15 1def I EMERGENCY ACTION LEVEL: A valid reading exists which exceeds or is expected to exceed Table 3 column "General" for GT 15 min. BASES: Effluent readings may be used for the classification of fast breaking events until actual dose projections can be made. Dose assessment, since it uses current plant values, will be more accurate and should be used. In establishing the emergency action levels, a release duration of one hour is assumed. If an emergency dose projection cannot be performed and the monitor reading(s) is expected to exceed 15 minutes, then the declaration should be made based on the valid reading. The 1000 mrem Total Effective Dose Equivalent or 5000 mrem thyroid Committed Dose Equivalent integrated dose are based on the EPA protective action guidance which indicates that public protective actions are indicated if the dose exceeds I rem Total Effective Dose Equivalent or 5 rem thyroid Committed Dose Equivalent. This logic is consistent with the emergency class description for a General Emergency and constitutes the upper level of the desirable gradient for the Site Area Emergency. Actual meteorology is specifically identified in the Initiating Condition since it gives the most accurate dose assessment.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency AS 1 10 CFR 20 WVNP-2 Offsite Dose Calculation Manual Environmental Protection Agency 400, Manual of Protective Action Guides and Protective Actions for Nuclear Incidents, October 15, 1991 WNP-2 Plant Specific EAL Guideline, AG1.3, AG1.4

5 Radioactivity Release 5.1 Offsite Release 5.1.G.2 General Emergency NUMARC IC: AGI - Boundary dose resulting from an actual or imminent release of gaseous radioactivity that exceeds 1000 mrem TEDE or 5000 mrem thyroid CDE equivalent for the actual or projected duration of the release using actual meteorology. APPLICABILITY: Operating Conditions I11 113 14 5I def I EMERGENCY ACTION LEVEL: Offsite dose calculations indicate doses or does rates GT Table 4 column "General" OR Field survey or survey sample analysis indicates offsite dose rates GT Table 4 column "General". BASES: The 1000 mrem Total Effective Dose Equivalent or 5000 mrem thyroid Committed Dose Equivalent integrated dose are based on the EPA protective action guidance which indicates that public protective actions are indicated if the dose exceeds 1 rem Total Effective Dose Equivalent or 5 rem thyroid Committed Dose Equivalent. This logic is consistent with the emergency class description for a General Emergency and constitutes the upper level of the desirable gradient for the Site Area Emergency. Actual meteorology is specifically identified in the Initiating Condition since it gives the most accurate dose assessment. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency AS 1 10 CFR 20 WNP-2 Offsite Dose Calculation Manual Environmental Protection Agency 400, Manual of Protective Action Guides and Protective Actions for Nuclear Incidents, October 15, 1991 WNP-2 Plant Specific EAL Guideline, AG 1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 74of 157

Table 3 Effluent Monitor Classification Thresholds Monitor UE Alert Site Area General NOTE: If a dose projection cannot be performed and the monitor reading is sustained for longer than the specified time, then the declaration must be made based on the valid reading. 1 60 min. 1 15 min. 1 15 min 15 min PRM-RE-lB 1.35E4 cps N/A N/A N/A Reactor Bldg. Exhaust Inter. PRM-RE- 1C N/A 1.14E3cps 9.65E3 cps 9.35E4 Reactor Bldg. Exhaust Hi cps TEA-RIS-13 1.7E4 cpm 4.4E4 cpm 4.4E5 cpm N/A Turbine Bldg. Exhaust, low TEA-RIS-1 3A N/A N/A N/A 11 PMU Turbine Bldg. Exhaust, Int WEA-RIS-14 1.2E5 cpm 1.7E5 cpm 1.7E6 cpm N/A Radwaste Bldg. Exhaust, low WEA-RIS-14A N/A N/A N/A 29 PMU Radwaste Bldg. Exhaust, Int TSW-RIS-5 3.9E3 cpm 3.9E5 cpm N/A N/A TSW Effluent FDR-RIS-606 2 x Hi-Hi alarm 200 x Hi-Hi alarm N/A N/A Rad. Waste Effluent SW-RIS-604 2.0E2 cps 2.0E4 cps N/A N/A SW 'A' Process SW-RIS-605 2.0E2 cps 2.0E4 cps N/A N/A SW 'B' Process cps=counts per second cpm=counts per minute PMU=panel meter units N/A=not applicable (outside of meter range)

Table 4 Offsite Dose Calculation/Field Survey Sample Analysis Classification Thresholds at 1.2 miles _IE Alert Site Area General TEDE N/A N/A 100 mrem 1000 mrem CDE Thyroid N/A N/A 500 mrem 5000 mrem TEDE rate 0.1 mrem/hr 10 mrem/hr 100 mrem/hr' 1000 mremihr' CDE Thyroid rate 0.3 mrem/hr 50 mrem/hr 500 mrem/hr' 5000 mremihr2 GT 60 min) 2 (For GT 1 HR inhalation)

5 Radioactivity Release 5.2 Area Radiation 5.2.U. 1 Unusual Event NUMARC IC: AU2 - Unexpected increase in plant radiation levels. APPLICABILITY: Operating Conditions 11 12 13 14 15 1def I EMERGENCY ACTION LEVEL: Valid reading GT 5E3 mR/hr on ANY of the following ARMs:

  • ARM-RIS-4 thru ARM-RIS-18
  • ARM-RIS-20 thru ARM-RIS-30
  • ARM-RIS-32 thru ARM-RIS-34 (High Range)

BASES: This Initiating Condition is not applicable for alarms resulting from the controlled movement of radioactive materials in the plant or expected increases in radiation levels due to the backwashing of demineralizer filters or other planned operation. Unplanned increases in in plant radiation levels represent a degradation in the control of radioactive material and represent a potential degradation in the level of safety of the plant. This EAL escalates to an ALERT per 5.2.A. 1 if the radiation level increase impairs safe operation of the plant. REFERENCE(S): WNP-2 Technical Specifications WNP-2 Instrument Master Data Sheets for referenced instruments NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event AU2 WNP-2 Plant Specific EAL Guideline, AU2.4 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 77 of 157

5 Radioactivity Release 5.2 Area Radiation 5.2.A.1 Alert NUMARC IC: AA2 - Release of radioactive material or increases in radiation levels within the facility that impedes operation of systems required to maintain safe operations or to establish or maintain cold shutdown. APPLICABILITY: Operating Conditions I1 12 13 14 5I def I EMERGENCY ACTION LEVEL: Valid reading GT 15 mR/hr on ARM-RIS-19 (CR) OR Valid reading GT 1E4 mR/hr on ANY of the following ARMs:

  • ARM-RIS-4 thru ARM-RIS- 18
  • ARM-RIS-23
  • ARM-RIS-24
  • ARM-RIS-32 thru ARM-RIS-34 (High Range)

BASES: Areas requiring continuous occupancy include the Control Room. The value of 15 mrenrhr is derived from the Generic Design Criteria (GDC) 19 value of 5 rem in 30 days with adjustment for expected occupancy times. Although Section III.D.3 or NUREG 0737, "Clarification of TMI Action Plan Requirements", provides that the 15 mremihr value can be averaged over the 30 days, the value is used here without averaging, as a 30-day duration implies an event potentially more significant than an Alert. This Initiating Condition addresses increased radiation levels that impede necessary access to operating stations or other areas containing equipment that must be operated manually in order to maintain safe operation or perform a safe shutdown. It is this impaired ability to operate the plant that results in the actual or potential substantial degradation of the level of safety of the plant. The cause and/or magnitude of the increase in radiation levels is not a concern of this Initiating Condition.

This Initiating Condition is not meant to apply to increases in the containment radiation monitors as these events are addressed in the fission product barrier Initiating Conditions, nor is it intended to apply to anticipated temporary increases due to planned events (e.g., incore detector movement, Radwaste container movement, depleted resin transfers, etc.). The Emergency Director should determine the cause of the increase in radiation levels and review other Initiating Conditions for applicability. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, AA3 NUREG 0737, Clarification of TMI Action Plan Requirements WNP-2 Instrument Master Data Sheets for referenced instruments WNP-2 Plant Specific EAL Guideline, AA3.1, AA3.2 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 79 of 157

6 ELECTRICAL FAILURES Loss of vital plant electrical power can compromise plant safety system operability including decay heat removal and emergency core cooling systems which may be necessary to ensure fission product barrier integrity. The events of this category have been grouped into the following two loss of electrical power types: Loss of AC Power Sources: This category includes losses of onsite and/or offsite AC power sources including station blackout events. Loss of DC Power Sources: This category involves total losses of vital plant 125 VDC power sources. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 80 of 157

6 Electrical Failures 6.1 AC Power Loss 6.1 .U. I Unusual Event NUMARC IC: SU1 - Loss of all offsite power to critical AC busses for greater than 15 minutes. APPLICABILITY: Operating Conditions 1 112 13 14 15 1def I EMERGENCY ACTION LEVEL: Power is unavailable to SM-7 and SM-8 from offsite AC sources GT 15 min. BASES: Even though power may still be available from offsite sources, there must be a functional flowpath to the Critical busses. Prolonged loss of offsite AC power reduces the required redundancy and potentially degrades the level of safety by rendering the plant more vulnerable to a complete loss of AC power (Station Blackout). Fifteen minutes was selected as a threshold to exclude transient or momentary power losses. Credit is not taken in this EAL for the Division 3 Standby Diesel Generator because it only supplies power to the High Pressure Core Spray (HPCS) pump and associated loads, but not for any long-term decay heat removal systems and, in particular, wetwell cooling mechanisms that would be essential subsequent to a station blackout. Failure of either the Division 1 or Division 2 Standby Diesel Generator would escalate this event to Alert 6.1.A.2. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU1 WNP-2 Plant Specific EAL Guideline, SU1.6

6 Electrical Failures 6.1 AC Power Loss 6.1 .A.1 Alert NUMARC IC: SA1 - Loss of all offsite power and loss of all onsite power to critical AC busses for greater than 15 minutes. APPLICABILITY: Operating Conditions I 1 1 4 15 def I EMERGENCY ACTION LEVEL: Complete loss of all AC power to SM-7 and SM-8 GT 15 min. BASES: A loss of the minimum required offsite circuits and failure of the diesel generators to restore power to the emergency busses results in a loss of AC power to all plant safety systems requiring AC power including RHR, ECCS, containment cooling systems, spent fuel heat removal systems, and wetwell cooling systems. This significant reduction in decay heat removal is a substantial reduction in the level of safety of the plant due to a potential for temperature and pressure increases. Credit is not taken in this EAL for the Division 3 Standby Diesel Generator because: 1) it is not required for all situations during Operating Conditions 4 and 5; and 2) although it does supply power to the HPCS pump which is a source of makeup water, it does not supply power to any systems that could be used to remove energy from the reactor and wetwell thereby limiting the long-term decay heat removal effectiveness. When the plant is in a cold shutdown or refueling condition, RPV temperature and pressure are lower than they would be in other operating conditions. These lower pressures and temperatures increase the margin of safety allowing more time before power must be restored to an emergency bus than would be available during Operating Conditions 1, 2 or 3. Fifteen minutes was selected as a conservative lower threshold that retains the anticipatory nature of EALs while excluding transient or momentary power losses. Escalation of this event to a Site Area Emergency would be via the Increased Radiation Release to the Environment (see EAL 5.1 .S. 1 and 5.1 .S.2) or Emergency Director Judgment (see EAL 9.1 .S. 1 and 9.1.S.2). If this same set of conditions were to occur in Operating Conditions 1, 2 or 3, they would be classified a Site Area Emergency (see EAL 6.1 S. 1). Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 82 of 157

REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert SAl WNP-2 Plant Specific EAL Guideline, SAL .1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 83 of 157

6 Electrical Failures S6.1 AC Power Loss 6.1 .A.2 Alert NUMARC IC: SA5 - Power capability to critical AC busses reduced to a single power source for greater than 15 minutes such that any additional single failure would result in station blackout. APPLICABILITY: Operating Conditions 11 12 13 1 I EMERGENCY ACTION LEVEL: Available emergency bus AC power has been reduced to only one of the following sources for GT 15 min.

  • TR-N1 (SM-7 and/or SM-8)
  • TR-S (SM-7 and/or SM-8)
  • TR-B (SM-7 and/or SM-8)
  • DG-1 (SM-7) 0 DG-2 (SM-8)

BASES: This Initiating Condition and its associated EAL provide an escalation from EAL 6.1 .U. 1, "Loss of All Offsite Power to Critical Busses for Greater than 15 Minutes". The condition indicated by this EAL is the degradation of the offsite and onsite power systems such that any additional single failure would result in a station blackout. This EAL includes a loss of both offsite power sources with only one diesel generator powering its respective emergency bus as well as a failure of both diesel generators such that they would not be able to power their respective emergency busses with only one offsite power source available. Credit is not taken in this Initiating Condition for bus SM-4 and the Division 3 Standby Diesel Generator because they only supply power to the HPCS pump and associated loads but not to any decay heat removal systems that would be essential subsequent to a station blackout. Power to busses SM-7 and SM-8 may come from either its respective standby diesel generator or from the Switch Yard through the Startup or Backup Transformers. Regardless of the source of power, failure of the remaining power source would result, at least temporarily, in a station blackout. The determining factor of whether or not to classify then becomes the amount of time that power is not available. Escalation for a Site Area Emergency for a station blackout would be via EAL 6.1.S. 1. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 84 of 157

REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert SA5 WNP-2 Plant Specific EAL Guideline, SA5.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 85 of 157

6 Electrical Failures 6.1 AC Power Loss 6.1.S.1 Site Area Emergency NUMARC IC: SS1 - Loss of all offsite power and loss of all onsite power to critical AC busses for greater than 15 minutes. APPLICABILITY: Operating Conditions 1 12 13 1 1 1 1 EMERGENCY ACTION LEVEL: Complete loss of all AC power to SM-7 and SM-8 GT 15 min. BASES: The condition indicated by this EAL is a station blackout and reflects a condition more serious than that described in Alert 6.1 .A.2 in that both Division 1 and Division 2 Emergency Busses are deenergized and have been without power for 15 minutes or longer. Station blackouts lasting less than 15 minutes or electrical system faults resulting in only one emergency bus powered from only one source are classified according to Alert 6.1 .A.2. Credit is not taken in this EAL for Bus SM-4 and the Division 3 Standby Diesel Generator because it only supplies power to the HPCS pump and associated loads but not to any decay heat removal systems that would be essential subsequent to a station blackout. Fifteen minutes was chosen as a conservative time to maintain the anticipatory nature of EALs while excluding transient or momentary power losses. This event would be upgraded to a General Emergency per. 6.1 .G. 1 if it appears that power cannot be restored to Bus SM-7 or SM-8 within 4 hours or if the Emergency Director determines that a loss or potential loss of a fission product barrier is imminent in accordance with the Fission Product Barrier Degradation table. Imminent in this context means mitigation strategies and actions are not successful in preventing a challenge to Fuel Clad, Reactor Coolant Pressure Boundary or Primary Containment. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 86 of 157

REFERENCE(S): WNP-2 Technical Specifications WNP-2 FSAR, Section 1.5.2, SBO Coping Study NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency SS 1 WNP-2 Plant Specific EAL Guideline, SS1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 87 of 157

6 Electrical Failures 6.1 AC Power Loss 6.1.G. 1 General Emergency NUMARC IC: SG2 - Prolonged loss of all offsite power and prolonged loss of all onsite power to critical AC busses. APPLICABILITY: Operating Conditions 11 12 13 1 1 EMERGENCY ACTION LEVEL: Complete loss of all AC power to SM-7 and SM-8 AND either of the following: In the judgment of the Emergency Director, AC power to either SM-7 or SM-8 is not likely to be restored within 4 hrs. OR RPV level LT -161 in. (For ATWS conditions, RPV level LT -192 inches) BASES: The condition indicated by this Initiating Condition and its associated EAL is a station blackout lasting long enough to degrade or potentially degrade a fission product barrier. Loss of all AC power compromises all plant safety systems requiring AC power including RHR, ECCS, containment cooling systems, spent fuel heat removal systems and Wetwell cooling systems. Prolonged loss of all AC power may lead to loss of integrity of the fuel clad, reactor coolant system or containment. Credit is not taken in this EAL for Bus SM-4 and the Division 3 Standby Diesel Generator because it only supplies power to the HPCS pump and associated loads but not to any decay heat removal systems that would be essential subsequent to a station blackout. Under these conditions, fission product barrier monitoring capability may be degraded. It may be difficult to predict when power can be restored. However, the Emergency Director should determine the need to declare a General Emergency based on two major considerations:

1. Are there any present indications that core cooling is already degraded to the point that loss or potential loss of a fission product barrier is imminent? Imminent in this context means mitigation strategies and actions are not successful in preventing a challenge to Fuel Clad, Reactor Coolant Pressure Boundary or Primary Containment.
2. If there are no present indications of such core cooling degradation, how likely is it that power can be restored in time to assure that a loss of two barriers with a potential loss of the third can be prevented?

The first question is answered by indications of a loss of adequate core cooling, which for the purpose of this EAL is considered to be RPV water level less than -161 in. (or -192 inches for ATWS conditions). The second question should be answered by the Emergency Director by making a realistic assessment of the time required to complete any necessary repairs. This EAL requires the Emergency Director to classify the event as soon as his assessment indicates that necessary repairs will take longer than 4 hours rather than waiting for the 4 hours to expire. During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192 inches (minimum steam cooling RPV water level. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, General Emergency SG1 WNP-2 FSAR, Section 1.5.2, SBO Coping Study WNP-2 Plant Specific EAL Guideline, SG1 .1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 89 of 157

6 Electrical Failures 6.2 DC Power Loss 6.2.U. 1 Unusual Event NUMARC IC: SU7 - Degradation of all critical DC power for greater than 15 minutes. APPLICABILITY: Operating Conditions 14 15 def EMERGENCY ACTION LEVEL: Degradation of both Division 1 and Division 2 critical DC voltage as indicated by bus voltage LT 110 VDC on both 125 V Dist. Panels Si-1 and S1-2 voltmeters (Bd. C) for GT 15 min. BASES: This Initiating Condition and its EAL recognize a loss of DC power compromising the ability to monitor and control the removal of decay heat during cold shutdown, refueling, or defueled. This EAL is intended to be anticipatory in that the operating crew may not have the necessary indication and control of equipment needed to respond to the loss. This is a less severe condition than that described in Site Area Emergency 6.2.S. I because initial temperatures and pressures are lower than they would be for Operating Conditions 1, 2 or 3 and, normally, less decay would be present. Credit is not taken in this EAL for the Division 3 DC bus because it only supplies control power to loads associated with the HPCS pump and not to any decay heat removal systems. The WNP-2 battery sizing calculations for the 125 VDC batteries, S I-I and S 1-2, reveal that a worst case LOCA analysis would permit a 15 minute margin between 106.3 volts and 105.0 volts. However, a conservative value of one hundred ten (110) volts DC is used as a minimum bus voltage. It is based on providing a 15 minute margin of operation before bus voltage drops below 105 volts DC at which time bus loads cannot be guaranteed to function. One hundred ten volts was also selected based on instrument accuracy of+/- 2% full scale or +/- 3 volts and scale increments of 2 volts. The same set of conditions as described in this EAL would be classified Site Area Emergency 6.2.S. 1 if they occurred during Operating Conditions 1, 2 or 3.

REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU7 Engineering Calculation 2.05.01 (Battery Sizing Calc) WNP-2 FSAR Section 8.3.2.1, Batteries CVI 51A-00,8 Exide Manual WNP-2 Plant Specific EAL Guideline, SU7.1

6 Electrical Failures 6.2 DC Power Loss 6.2.S. 1 Site Area Emergency NUMARC IC: SU7 - Degradation of all critical DC power for greater than 15 minutes. APPLICABILITY: Operating Conditions 11 2 13 21 1 EMERGENCY ACTION LEVEL: Degradation of both Division 1 and Division 2 critical DC voltage as indicated by bus voltage LT 110 VDC on both 125 V Dist. Panels SI-I and S1-2 voltmeters (Bd. C) for GT 15 min. BASES: This Initiating Condition and its EAL recognize a loss of DC power compromising the ability to monitor and control the removal of decay heat during power operations, startup and hot shutdown conditions. It is intended to be anticipatory in that the operating crew may not have the necessary indication and control of equipment needed to respond to the loss. This EAL represents a more serious condition that than described in Unusual Event 6.2.U. 1 in that the initial temperatures, pressures and available decay heat may be substantially higher than in Unusual Event 6.2.U. 1 resulting in significantly less time available before failure of systems needed to protect the public. Loss of all DC power compromises the ability to monitor and control plant safety functions. Prolonged loss of all DC power may result in core uncovery and loss of containment integrity when there is significant decay heat and residual heat in the reactor coolant system. Credit is not taken in this EAL for the Division 3 DC bus because it only supplies control power to loads associated with the HPCS pump and not to any decay heat removal systems. The WNP-2 battery sizing calculations for the 125 VDC batteries, S1-1 and S 1-2, reveal that a worst case LOCA analysis would permit a 15 minute margin between 106.3 volts and 105.0 volts. However, a conservative value of one hundred ten (110) volts DC is used as a minimum bus voltage. It is based on providing a 15 minute margin of operation before bus voltage drops below 105 volts DC at which time bus loads cannot be guaranteed to function. One hundred ten volts was also selected based on instrument accuracy of+ 2% full scale or +/- 3 volts and scale increments of 2 volts. REFERENCE(S):

WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency SS3 Engineering Calculation 2.05.01 (Battery Sizing Calc) WNP-2 FSAR Section 8.3.2.1, Batteries CVI 51A-00,8 Exide Manual WNP-2 Plant Specific EAL Guideline, SS3.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 93 of 157

7 EQUIPMENT FAILURES Numerous plant system related equipment failure events which warrant emergency classification, based upon their potential to pose actual or potential threats to plant safety, have been identified in this category. The events of this category have been grouped into the following event types: System Failures: This subcategory includes conditions related to the failure of the plant to be brought to the required plant operating condition required by technical specifications and events which are indicative of a loss of ability to maintain the plant in cold shutdown. Control Room Evacuation: This category addresses losses of Control Room habitability and the ability to establish plant control from remote shutdown panels. Loss of Indication/Communications: Certain events which degrade the plant operators ability to effectively assess plant conditions or communicate with essential personnel within or external to the plant warrant emergency classification. Under this event type are losses of annunciators and/or communication equipment. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 94 of 157

7 Equipment Failures 7.1 System Failures 7.1 .U.1 Unusual Event NUMARC IC: SU2 - Inability to reach required shutdown within technical specification limits. APPLICABILITY: Operating Conditions 1 23 EMERGENCY ACTION LEVEL: Plant is not brought to required operating mode within T.S. LCO action statement time BASES: Limiting Conditions of Operation (LCOs) require the plant to be brought to a required shutdown mode when the Technical Specification required configuration cannot be restored. Depending on the circumstances, this may or may not be an emergency or precursor to a more severe condition. In any case, the initiation of plant shutdown required by the Technical Specifications requires a one hour report under 10 CFR 50.72 (b) Non-emergency events. The plant is within its safety envelope when being shut down within the allowable action statement time in the Technical Specifications. An immediate Notification of Unusual Event is required when the plant is not brought to the required operating mode within the allowable action statement time in the Technical Specifications. Declaration of an Unusual Event is based on the time at which the LCO-specified action statement time period elapses under the site Technical Specifications and is not related to how long a condition may have existed. Other required Technical Specification shutdowns that involve precursors to more serious events are addressed by other categories of Initiating Conditions. When a Limiting Condition is not met, and the associated ACTION requirement is not met within the required time allowed, the plant is not within its safety envelope and not within a T. S. LCO action statement time. Declaration of the Unusual Event should occur when Technical Specification action time elapses. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU2 WNP-2 Plant Specific EAL Guideline, SU2.1 7 Equipment Failures 7.1 System Failures Attachment 4.1 PROCEDURENUMBER REVISION 95 of 157 13.1.1A 17 95AoG15

7.1.U.2 Unusual Event NUMARC IC: HU1 - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions 1 112 13 14 15 1def I EMERGENCY ACTION LEVEL: Uncontrolled flooding in SSB (table 5) that has the potential to affect safety related equipment needed for the current operating mode. BASES: Declaration of this EAL identifies the occurrences of an event of sufficient magnitude to be of concern to the operating crew. This EAL addresses the effect of flooding caused by internal events such as component failures, equipment mis-alignment, or outage activity mishaps. The SSBs contain systems required for safe shutdown that are not designed to be wetted or submerged. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, final draft Rev. 3, Unusual Event HU1.6 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.I.1A 17 96 of 157

7 Equipment Failures 7.1 System Failures 7.1.A.1 Alert '-A NUMARC IC: SA3 - Inability to maintain plant in cold shutdown. APPLICABILITY: Operating Conditions I 1-1 41545 EMERGENCY ACTION LEVEL: Inability to restore and maintain reactor coolant temp LT 200 'F BASES: This EAL addresses loss or degradation of functions required for core cooling during refueling and cold shutdown modes such that the technical specification limit cannot be maintained. Determination of "Inability to maintain" includes making an evaluation that considers both current and future system performance in relation to the current values and trends of relevant parameters. A momentary unplanned excursion above 200'F when adequate heat removal function is available is not intended to constitute an Alert. REFERENCE(S): WNP-2 Technical Specifications NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert SA3 WNP-2 Plant Specific EAL Guideline, SA3.1

7 Equipment Failures 7.1 Natural Events 7.1 .A.2 Alert NUMARC IC: HAI - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions 1 2 3 4 15 def EMERGENCY ACTION LEVEL: Report by plant personnel confirming the occurrence of uncontrolled plant internal flooding in a safe shutdown building, Table 5 AND Affected safe shutdown system parameters indicate degraded performance BASES: Flooding conditions within the plant affecting safe shutdown areas have the potential to directly impact the safe operation of the plant. The uncontrolled flooding event may pose a direct threat to safety-related equipment. As such, the potential exists for substantial degradation of the level of safety of the plant. Flooding is indicated by ECCS room level alarms on P601 and sump hi-hi alarms on P602. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment ICs. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the Radwaste/Control Building
  • Reactor Building
  • Turbine Building
  • Standby Service Water Pump Houses 9 Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HAl WNP-2 Reactor Building 422 Area Flooding, PPM 4.12.4.10 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA1.7

7 Equipment Failures 7.2 Control Room Evacuation 7.2.A. 1 Alert NUMARC IC: HA5 - Control room evacuation has been initiated. APPLICABILITY: Operating Conditions 11 12 13 14 15 1 EMERGENCY ACTION LEVEL: The decision to evacuate the Control Room has been made. BASES: The Alert condition addresses events which involve a substantial degradation of the level of safety of the plant. Frequently, a distinguishing characteristic of a "substantial degradation" is the need for increased monitoring of or assistance in monitoring plant functions. With the Control Room evacuated, additional support, monitoring and direction through the Technical Support Center and/or Operations Support Center is necessary. Therefore, an Alert should be declared when the Control Room must be evacuated. An inability to establish plant control from outside the Control Room will escalate this event to a Site Area Emergency. REFERENCE(S): WNP-2 Control Room Evacuation and Remote Cooldown, PPM 4.12.1.1 NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert HA5 WNP-2 Plant Specific EAL Guideline, HA5.1

7 Equipment Failures 7.2 Control Room Evacuation 7.2.S.1 Site Area Emergency NUMARC IC: HS2 - Control room evacuation has been initiated, but plant control CANNOT be established. APPLICABILITY: Operating Conditions 11 12 1415 EMERGENCY ACTION LEVEL: CR evacuation initiated AND Control of plant equipment needed to maintain adequate core cooling cannot be established at either the Remote Shutdown Panel or Alternate Remote Shutdown panel within 15 min. of the SRO in charge of the CR physically leaving the CR BASES: This Initiating Condition and its associated EAL address a condition where evacuation of the Control Room is necessary but expeditious transfer of safety systems has not occurred. Fission product barrier damage may not yet be indicated. A 15 minute transfer time was chosen for control to be reestablished to ensure that core uncovery with subsequent core damage does not occur and is consistent with NUMARC methodology. Escalation of this event, if appropriate, would be by Fission Product Barrier Degradation, Abnormal Rad Levels/Radiological Effluent, or Emergency Director Judgment Initiating Conditions. REFERENCE(S): NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Site Area Emergency HS2 WNP-2 Control Room Evacuation and Remote Cooldown, PPM 4.12.1.1 WNP-2 Plant Specific EAL Guideline, HS2.1 7 Equipment Failures 7.3 Loss of Indication/Communications Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 101 of 157

7.3.U. 1 Unusual Event NUMARC IC: SU3 - Unplanned loss of most or all safety system annunciators or indication in the control room for greater than 15 minutes. APPLICABILITY: Operating Conditions 1 12 13 1 1 EMERGENCY ACTION LEVEL: Unplanned loss of most or all annunciators on P601, P602, P603, and Bd. C associated with safety-related equipment GT 15 minutes BASES: This Initiating Condition and its associated EAL recognize the difficulty associated with monitoring plant conditions without the use of a major portion of the annunciation equipment. Quantification of "most" is left to the Emergency Director. It is not intended that plant personnel perform a detailed count of the instrumentation lost but rather make a judgment call with approximately 75% being the threshold. It is estimated that if approximately 75% of the annunciators are lost, there is an increased risk that a degraded plant condition could go undetected. Control Room panels with annunciators for safety-related equipment required for off normal or emergency plan response include:

  • P601
  • P602 0 P603 0 Electrical Distribution on Bd C Indications are available at other locations including Control Room back panels, using them to safely operate the plant would require increased surveillance.

Plant design provides redundant safety system indication powered from separate uninterruptible power supplies. While failure of a large portion of annunciators is more likely than a failure of a large portion of indications, the concern is included in this EAL due to difficulty associated with assessment of plant Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 102 of 157

conditions. The loss of specific, or several, safety system indicators should remain a function of that specific system or component operability status. This will be addressed by the specific Technical Specification. The initiation of a Technical Specification- imposed plant shutdown related to the instrument loss will be reported via 10 CFR 50.72. If the shutdown is not in compliance with the Technical Specification Action Statement, the Unusual Event is based on 7.1 .U. 1, "Inability to Reach Required Shutdown Within Technical Specification Limits". Compensatory nonalarming indications include the Process Computers and the Graphic Display System (GDS). It may include other permanently or temporarily installed monitoring systems if they allow the plant operators to compensate for the failed indications. Fifteen minutes was selected as a threshold to exclude transitory or momentary power losses. No Initiating Condition is indicated during cold shutdown and refueling due to the limited number of safety systems required for operation. This event should be escalated to Alert 7.3.A.1 if a transient is in progress or the compensatory indications become unavailable. REFERENCE(S): NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU3 WNP-2 Technical Specifications WNP-2 Plant Specific EAL Guideline, SU3.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 103 of 157

7 Equipment Failures 7.3 Loss of Indication/Communications 7.3.U.2 Unusual Event NUMARC IC: SU6 - Significant loss of onsite or offsite communications capabilities. APPLICABILITY: Operating Conditions I1 2 13 J415 I1ef I EMERGENCY ACTION LEVEL: Unplanned loss of ALL of the following onsite communications capability:

  • Plant Public Address (PA) System

° Plant Telephone System

  • Plant Radio System Operations and Security Channels BASES:

This Initiating Condition and its associated EALs recognize a loss of communications capability that significantly degrades the Plant Operations staffs ability to perform tasks necessary for plant operations or the ability to communicate with offsite authorities. REFERENCE(S): NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU6 WNP-2 Plant Specific EAL Guideline, SU6.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 104 of 157

7 Equipment Failures 7.3 Loss of Indication/Communications 7.3.U.3 Unusual Event NUMARC IC: SU6 - Significant loss of onsite or offsite communications capabilities. APPLICABILITY: Operating Conditions 1 12 13 4 15 1defI EMERGENCY ACTION LEVEL: Unplanned loss of ALL of the following offsite communications capability: State/County Notification (Crash) System Offsite calling capability from the Control Room via direct telephone and fax lines Long distance calling capability on the Plant ("2000") Switch and Kootenai (Plant Support Facility)/Deschutes (Plant Engineering Center) ("8000") Switch BASES: This Initiating Condition and its associated EALs recognize a loss of communications capability that significantly degrades the Plant Operations staffs ability to perform tasks necessary for plant operations or the ability to communicate with offsite authorities. The loss of offsite communications capability is more comprehensive than that addressed by 10 CFR 50.72. Long distance capability may be confirmed by placing a direct long distance call from both the 2000 and 8000 switches. REFERENCE(S): NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event SU6 WNP-2 Plant Specific EAL Guideline, SU6.1

7 Equipment Failures 7.3 Loss of Indication/Communications 7.3.A.1 Alert NUMARC IC: SA4 - Unplanned loss of most or all safety system annunciators or indications in the control room with EITHER: 1) a significant transient in progress; OR

2) Compensatory nonalarming indicators are unavailable.

APPLICABILITY Operating Condit ions 11 12 13 1 EMERGENCY ACTION LEVEL: Unplanned loss of most or all annunciators on P601, P602, P603, and Bd C associated with safety-related equipment GT 15 min. AND either of the following: A significant plant transient is in progress OR Compensatory non alarming indications are not available (plant computer systems and GDS) BASES: This Initiating Condition and its associated EAL recognize the difficulty associated with monitoring plant conditions without the use of a major portion of the annunciation equipment. It represents an increase in severity above that described in Unusual Event 7.3.U. 1 in that either compensatory indications are not available or a significant transient is in progress. Quantification of "most" is left to the Emergency Director. It is not intended that plant personnel perform a detailed count of the annunciation lost but, rather, make a judgment call with approximately 75% being the threshold. It is estimated that if approximately 75% of the annunciators are lost, there is an increased risk that a degraded plant condition could go undetected. Control Room panels with annunciators and indicators for safety-related equipment for off normal or emergency plan response include: P601 P602 P603 Electrical Distribution on Bd C Indications are available at other locations including Control Room back panels. However, using them to safely operate the plant would require increased surveillance. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 106 of 157

Plant design provides redundant safety system indication powered from separate uninterruptible power supplies. While failure of a large portion of annunciators is more likely than a failure of a large portion of indications, the concern is included in this EAL due to difficulty associated with assessment of plant conditions. The loss of specific, or several, safety system indicators should remain a function of that specific system or component operability status. This will be addressed by the specific Technical Specification. The initiation of a Technical Specification-imposed plant shutdown related to the instrument loss will be reported via 10 CFR 50.72. If the shutdown is not in compliance with the Technical Specification action statement, the Unusual Event is based on AU1, "Inability to Reach Required Shutdown Within Technical Specification Limits". Compensatory nonalarming indications include the Process Computer Systems. It may include other permanently or temporarily installed monitoring systems if they allow the plant operators to compensate for the failed indications. Fifteen minutes was selected as a threshold to exclude transient or momentary power losses. A "significant transient" includes response to automatic or manually initiated functions such as scrams, runbacks involving greater than 25% thermal power change, ECCS injection, or thermal power oscillations of 10% or greater. No Initiating Condition is indicated during cold shutdown or refueling due to the limited number of safety systems required for operation. This event should be escalated to Site Area Emergency 7.3.S. 1 if the operating crew cannot monitor a transient in progress. REFERENCE(S): NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert SA4 WNP-2 Technical Specifications WNP-2 Plant Specific EAL Guideline, SA4.1

7 Equipment Failures 7.3 Loss of Indication/Communications 7.3.S.1 Site Area Emergency NUMARC IC: SS6 - Inability to monitor a significant transient in progress. APPLICABILITY: Operating Conditions 1i1 2 31 T7 EMERGENCY ACTION LEVEL: Loss of most or all annunciators on P601, P602, P603 and Bd. C associated with safety-related equipment AND Compensatory non-alarming indications are unavailable (process computer system and GDS) AND Significant transient in progress AND Loss of indications needed to monitor ANY of the following plant critical safety parameters:

  • Reactor power
  • RPV level
  • RPV pressure
  • Drywell pressure
  • Drywell temperature
  • Wetwell pressure
  • Wetwell/Drywell H2/02 Concentrations
  • Wetwell level
  • Wetwell temperature Radioactive Gaseous Effluents Attachment 4.1 PROCEDURE NUMBER REVISION A PAGE 13.1.1A 7 108 of 157

BASES: This Initiating Condition and its associated EAL recognize the inability of the Control Room staff to monitor plant response to a transient. A Site Area Emergency is considered to exist if the Control Room staff cannot monitor the critical safety functions needed for protection of the public. Critical safety functions include those plant parameters and functions that allow the plant operators to verify they have a coolable core geometry, that core cooling is maintained, and that containment is intact. The WNP-2 Safety Analysis Report states that the safety functions include:

1. The accommodation of abnormal operational transients and postulated design basis accidents;
2. The maintenance of containment integrity;
3. The assurance of Emergency Core Cooling; and
4. The continuance of reactor coolant pressure boundary integrity.

Compensatory nonalarming indications include the Process Computer Systems. It may include other permanently or temporarily installed monitoring systems if they allow the plant operators to compensate for the failed indications. A "significant transient" includes response to automatic or manually initiated functions such as scrams, runbacks involving greater than 25% thermal power change, ECCs injection, or thermal power oscillations of 10% or greater. REFERENCE(S): NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Alert SS6 WNP-2 Technical Specifications WNP-2 Plant Specific EAL Guideline, SS6.1

8 Hazards Hazards are those nonplant system-related events which can directly or indirectly impact plant operation or reactor plant and personnel safety. The events of this category have been grouped into the following types: Security Threats: This category includes unauthorized entry attempts into the Protected Area as well as bomb threats and sabotage attempts. Also addressed are actual security compromises threateningJoss of physical control of the plant. Fire or Explosion: Fires can pose significant hazards to personnel and reactor safety. Appropriate for classification are fires within the site Protected Area or which may affect operability of vital equipment. Man-made Events: Man-made events are those nonnaturally occurring events which can cause damage to plant facilities such as aircraft crashes, missile impacts, toxic or flammable gas leaks or explosions from whatever source. Natural Events: Events such as hurricanes, earthquakes or tornadoes which have potential to cause damage to plant structures or equipment significant enough to threaten personnel or plant safety.

8 Hazards 8.1 Security Threats 8.1 .U. 1 Unusual Event NUMARC IC: HU4 - Confirmed security event which indicates a potential degradation in the level of safety of the plant. APPLICABILITY: Operating Conditions 1 2 13 4 5 def EMERGENCY ACTION LEVEL: Bomb device discovered within Plant Protected Area but outside a Safe Shutdown Building, Table 5 OR Confirmed report of an attempted entry, sabotage or security threat that cannot be properly compensated for within 10 minutes BASES: Events which are believed by the Emergency Director to indicate a potential degradation of the level of safety of the plant should be declared an Unusual Event. Security events which do not represent at least a potential degradation in this level of safety of the plant are reported under 10 CFR 73.71 or, in some cases, 10 CFR 50.72. The 10 minute criteria to compensate is derived from regulatory guidance on implementation of 10 CFR 73.71, Reporting of Security Events. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

REFERENCE(S):

WNP-2 Safeguards Contingency Plan NUMARC/NESP-007, Methodology for Development of Emergency Actions Levels, Rev. 2, Unusual Event HU4 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HU4.1

8 Hazards 8.1 Security Threats 8.1 .A. 1 Alert NUMARC IC: HA4 - Security event in a Plant Protected Area. APPLICABILITY: Operating Conditions 1 2 13 4 15 Idef EMERGENCY ACTION LEVEL: Confirmed report of an intrusion by a hostile force into the Plant Protected Area BASES: This class of security events represents an escalated threat to plant safety above that contained in the Unusual event. For the purpose of this Initiating Condition, a civil disturbance which penetrates the Protected Area Boundary as well as an individual or group of individuals with known or suspected malicious intent is considered a hostile force. Intrusion into a Safe Shutdown Building by a hostile force as defined in Site Area Emergency NS1 will escalate this event to Site Area Emergency. REFERENCE(S): WNP-2 Safeguards Contingency Plan NUMARC/NESP-007, Methodology for Development of Emergency Actions Levels, Rev. 2, Unusual Event HA4 WNP-2 Plant Specific EAL Guideline, HA4.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 1113 of 157

8 Hazards 8.1 Security Threats 8.1.S.1 Site Area Emergency NUMARC IC: HS1 - Security event in a Plant Vital Area. APPLICABILITY: Operating Conditions 11 12 13 14 15 1defI EMERGENCY ACTION LEVEL: Bomb device discovered or detonated within a Safe Shutdown Building, Table 5 OR Confirmed report of intrusion by a hostile force into a Safe Shutdown Building, Table 5 BASES: This class of security event represents an escalated threat to plant safety above that contained in Alert 8.1 .A. 1 in that a hostile force has progressed from the Protected Area to a Safe Shutdown Building. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations: 0 Vital portions of the RadWaste/Control Building

  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

For the purposes of this EAL, a civil disturbance which penetrates the Protected Area Boundary as well as an individual or group of individuals with known or suspected malicious intent can be considered a hostile force.

REFERENCE(S): WNP-2 Safeguards Contingency Plan NUMARC/NESP-007, Methodology for Development of Emergency Actions Levels, Rev. 2, Unusual Event HS 1 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HSI .1, HS1.2

8 Hazards 8.1 Security Threats 8.1.G.1 General Emergency NUMARC IC: HG1 - Security event resulting in loss of ability to reach and maintain cold shutdown. APPLICABILITY: Operating Conditions I1 12 1 3 -14 15 Idef I EMERGENCY ACTION LEVEL: Loss of physical control of the CR due to security event OR Loss of physical control of the remote shutdown capability due to security event BASES: This Initiating Condition encompasses conditions under which a hostile force has taken physical control of areas required to reach and maintain cold shutdown. For the purpose of this EAL, a civil disturbance which penetrates the Protected Area Boundary as well as an individual or group of individuals with known or suspected malicious intent is considered a hostile force. REFERENCE(S): WNP-2 Safeguards Contingency Plan NUMARC/NESP-007, Methodology for Development of Emergency Actions Levels, Rev. 2, Unusual Event HG1 WNP-2 Plant Specific EAL Guideline, HGL.1, HG1.2

8 Hazards 8.2 Fire/Explosion Caused by Equipment Failure 8.2.U. 1 Unusual Event NUMARC IC: HU2 - Fire within the Protected Area Boundary not extinguished within 15 minutes of detection or an explosion within Protected Area Boundary. APPLICABILITY: Operating Conditions 11 2 13 4 15 def EMERGENCY ACTION LEVEL: Fire within or adjacent to any Safe Shutdown Building, Table 5, which is not extinguished within 15 minutes of either CR notification by plant personnel or receipt of an alarm OR Report by plant personnel of an unplanned explosion within the Protected Area Boundary resulting in visible damage to permanent structures or equipment BASES: This Initiating Condition and its associated EAL address fires that are of sufficient magnitude that they may be potentially significant precursors to damage to safety systems. This excludes items such as fires within administrative buildings or other structures not contiguous with a safe shutdown building, and other fires of no safety consequence or threat to a safe shutdown building such as slipping drive belts or overheated bearings, or other equipment not listed in FSAR Table 3.2-1, Seismic Category 1. A fire alarm can be confirmed by multiple/redundant indications such as additional alarms on FCP-1 or FCP-2, fire pumps starting, fire suppression system discharge, fire water header pressure fluctuations or by notification by plant personnel. If an alarm must be verified by dispatching an individual to the scene, the 15 minute clock starts at the time of the alarm. If an inspection of the area is completed within 15 minutes with no evidence of a fire (spurious alarm), no declaration need be made. NEI 99-01 revision 4 defines fire as combustion characterized by heat and light. Sources of heat and smoke, such as slipping drive belts or overheated electrical components do not constitute fires. Observation of flame is preferred but not required if large quantities of heat and smoke are observed. No attempt is made to assess the magnitude of the damage. The occurrence of the explosion with reports of damage (deformation/scorching) is sufficient for declaration.

Any security aspects of this event should be considered under Event Category 8.1, "Security Threats". If structural or equipment damage occurs within areas housing safe shutdown equipment and functions, the event may be escalated to Alert, 8.2.A. 1. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building 0 Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I. The only equipment in the Turbine Building listed in FSAR Table 3.2-1, Seismic Category I is:

  • DEH Pressure Switches
  • RPS switches on turbine throttle valves
  • Main Steam Line Radiation Monitors 0 Turbine Building Ventilation Radiation Monitors
  • Main Steam Piping up to MS-V-146 and the first stop valves REFERENCE(S):

Title 10 of the Code of Federal Regulations, Part 50, Domestic Licensing of Production and Utilization Facilities, Appendix R, Fire Protection Program for Nuclear Power Facilities NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HU2 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HU2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 118 of 157

8 Hazards 8.2 Fire/Explosion Caused by Equipment Failure 8.2.A.1 Alert NUMARC IC: HA2 - Fire or explosion affecting the operability of plant safety systems required to establish or maintain safe shutdown. APPLICABILITY: Operating Conditions 11 2 13 4 15 Tdef EMERGENCY ACTION LEVEL: Confirmed fire or explosion in a safe shutdown building, Table 5 AND either of the following: Affected safe shutdown system parameters indicate degraded performance OR Report by plant personnel of visible damage to the affected safe shutdown building or equipment contained within the affected safe shutdown building BASES: As used here, an explosion is a rapid, violent, unconfined combustion or catastrophic failure of pressurized equipment, that potentially imparts significant energy to near-by structures and materials. The inclusion of a "report of visible damage" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in this EAL to assess the actual magnitude of the damage. The occurrence of the explosion with reports of evidence of damage (e.g., deformation, scorching) is sufficient for declaration. It is important to note that this EAL addresses a fire and not the degradation in performance of affected systems. The reference to damage of systems is used to identify the magnitude of the fire and to discriminate against minor fires, such as fires or explosions not near equipment listed in FSAR Table 3.2-1, Seismic Category I. The reference to Safe Shutdown Buildings is included to discriminate against fires in areas having a low probability of affecting safe operation. The significance here is not that a safety system was degraded but the fact that the fire was large enough to cause damage to these systems. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 119 of 157

This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I. Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I. The only equipment in the Turbine Building listed in FSAR Table 3.2-1, Seismic Category I is:

  • DEH Pressure Switches
  • RPS switches on turbine throttle valves
  • Main Steam Line Radiation Monitors
  • Turbine Building Ventilation Radiation Monitors
  • Main Steam Piping up to MS-V-146 and the first stop valves REFERENCE(S):

Title 10 of the Code of Federal Regulations, Part 50, Domestic Licensing of Production and Utilization Facilities, Appendix R, Fire Protection Program for Nuclear Power Facilities NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA2 PPM 4.12.1.1, Control Room Evacuation and Remote Cooldown FSAR Appendix F, Fire Safety Evaluation WNP-2 Plant Specific EAL Guideline, HA2.1

8 Hazards 8.3 Man-Made Events 8.3.U.1 Unusual Event NUMARC IC: HUI - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions 1 12 13 14 15 idefI EMERGENCY ACTION LEVEL: Vehicle crash into or projectile which impacts a Safe Shutdown Building, Table 5 BASES: This EAL addresses such items as plane, helicopter, train, car, truck, or barge crash, or impact of other projectiles that may potentially damage plant structures containing functions and systems required for safe shutdown of the plant. The impact is of such force that damage to structures or equipment inside a Safe Shutdown Building may have occurred. If the crash is confirmed to affect equipment in a Safe Shutdown Building, the event may be escalated to Alert. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations: 0 Vital portions of the RadWaste/Control Building

  • Reactor Building
  • Vital portions of the Turbine Building I

° Standby Service Water Pump Houses 0 Diesel Generator Building

  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI WNP-2 Plant Specific EAL Guideline, HU1.4 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 121 of 157

8 Hazards 8.3 Man-Made Events 8.3.U.2 Unusual Event NUMARC IC: HUI - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions 1 12 3 - 1 EMERGENCY ACTION LEVEL: Turbine failure resulting in casing penetration or damage to turbine or generator seals BASES: Turbine failure with casing penetration or seal failure increases the potential for leakage of combustible fluids (oils and gas). REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI WNP-2 Plant Specific EAL Guideline, HU1.6

8 Hazards 8.3 Man-Made Events 8.3.U.3 Unusual Event NUMARC IC: HU3 - Release of toxic or flammable gases affecting the Protected Area Boundary deemed detrimental to safe operation of the plant. APPLICABILITY: Operating Conditions 1 2 13 14 15 1def EMERGENCY ACTION LEVEL: Report or detection of toxic or flammable gases that could enter or have entered within the Protected Area Boundary in amounts that could affect the health of plant personnel or safe plant operation OR Report by local, county or state officials for evacuation or shelter of site personnel based on offsite event BASES: This Initiating Condition and its associated EALs are based on releases in concentrations within the Protected Area Boundary that may affect the health of plant personnel or the safe operation of the plant. This includes releases that originate onsite as well as releases that originate offsite but threaten onsite areas. A toxic gas is considered to be any gas that is dangerous to life or limb by reason of inhalation or skin contact. A combustible gas, if maintained at a concentration lower than the Lower Explosive Limit (LEL), will not explode due to ignition. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HU3 WNP-2 Plant Specific EAL Guideline, HU3.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 123 of 157

8 Hazards 8.3 Man-Made Events 8.3.A.1 Alert NUMARC IC: HAI - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions 1112 13 14 15 1def I EMERGENCY ACTION LEVEL: Vehicle crash or projectile impact which impedes access to or damages equipment in a Safe Shutdown Building, Table 5 BASES: This EAL addresses such items as plane, helicopter, train, car, truck, or barge crash, or impact of other projectiles that may affect plant structures containing functions and systems required for safe shutdown of the plant. If the crash is confirmed to affect equipment in a Safe Shutdown Building, then the event is an Alert. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment EALs. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations: 0 Vital portions of the RadWaste/Control Building

  • Reactor Building 0 Vital portions of the Turbine Building I

0 Standby Service Water Pump Houses a Diesel Generator Building

  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I. Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 124 of 157

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA1 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA1.5 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 125 of 157

8 Hazards 8.3 Man-Made Events 8.3.A.2 Alert NUMARC IC: HAl - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions 11 12 13 1 1 EMERGENCY ACTION LEVEL: Missiles generated from a turbine failure have resulted in visible structural damage to or penetration of a safe shutdown building, Table 5 BASES: Turbine causing penetration, caused by failure of turbine rotating components, can result in missiles (blading, pieces of diaphragm, etc.) being hurled through the casing penetrations with such force, they can penetrate the turbine and come to rest a significant distance away. These turbine-generated missiles pose a threat to safety-related equipment if they cause visible structural damage to, or if they penetrate, Safe Shutdown Buildings. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment EALs. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HAl FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA1.6

8 Hazards 8.3 Man-Made Events 8.3.A.3 Alert NUMARC IC: HA3 - Release of toxic or flammable gases within a facility structure which jeopardizes operation of systems required to maintain safe operations or to establish or maintain cold shutdown. APPLICABILITY: Operating Conditions 1 2 13 -4 5 def EMERGENCY ACTION LEVEL: Report or detection of toxic or flammable gases within a safe shutdown building, Table 5, in concentrations that will be life threatening to plant personnel or impede access to equipment needed for safe plant operation BASES: This EAL is based on gases that have entered a plant structure impeding access to equipment necessary for the safe operation of the plant. This EAL applies to Safe Shutdown Buildings and areas contiguous to plant vital areas or other significant buildings or areas. The intent of this EAL is not to include buildings (i.e., warehouses) or other areas that are not contiguous or immediately adjacent to plant vital areas or Safe Shutdown Buildings. It is appropriate that increased monitoring be done to ascertain whether consequential damage has occurred. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA3 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA3.1, HA3.2

8 Hazards 8.4 Natural Events 8.4.U. 1 Unusual Event NUMARC IC: HU1 - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions 12 13 14 15 1def I EMERGENCY ACTION LEVEL: MINIMUM SEISMIC EARTHQUAKE alarm (H13-P851-S1-2.5) AND CR receives report from plant personnel who have felt an earthquake BASES: The method of detection associated with an earthquake of this intensity is based on the condition for a "felt earthquake" as defined in the EPRI-sponsored "Guidelines for, Nuclear Plant Response to an Earthquake". These methods include the activation of seismic monitoring instrumentation as evidenced by a valid alarm on P851-S 1-2.5, "MINIMUM SEISMIC EARTHQUAKE EXCEEDED" along with confirmation from plant personnel who have physically felt the ground motion and recognize the event as an earthquake. An earthquake of this magnitude may be sufficient to cause some minor damage to ... plant structures or equipment within the Protected Area. Damage is considered to be minor since it does not affect physical or structural integrity. The event is not expected to affect the capabilities of plant safety functions. Due to the unpredictable nature of earthquakes, this may be a precursor to a more serious event and, therefore, represents a potential degradation in the level of safety of the plant. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI EPRI Guidelines for Nuclear Plant Response to an Earthquake

8 Hazards 8.4 Natural Events 8.4.U.2 Unusual Event NUMARC IC: HIU1 - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions 1 12 13 14 15 1defI EMERGENCY ACTION LEVEL: Weather Service projected winds GT 80 mph OR CR measured winds GT 66 mph (5 minute average at 33 ft) OR Report by plant personnel confirming the occurrence of a tornado striking within the Protected Area Boundary BASES: This event is a natural and potentially destructive phenomena that may accompany certain events such as a tornado or hurricane. These sustained high winds may also be produced by unstable weather conditions. However this event occurs, it may be a precursor to a more serious event and, therefore, represents a potential degradation in the level of safety of the plant. A tornado touching down within the Protected Area is an observed event with the potential to cause damage to structures containing systems or functions necessary for the safe shutdown of the plant. As such, the occurrence of a tornado strike represents a potential degradation in the level of safety of the plant. If structural damage is confirmed, this event would be escalated to Alert 8.4.A.2. If it is determined that the occurrence of the tornado strike has either affected or caused the loss of shutdown cooling functions, then the consequences of the event are assessed under event category 7.1, "System Failures". The event may then be escalated via this category if appropriate. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI WNP-2 Tornado/High Winds, PPM 4.12.4.8 WNP-2 Plant Specific EAL Guideline, HU1 .1

8 Hazards 8.4 Natural Events 8.4.U.3 Unusual Event NUMARC IC: HU1 - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions I 1 2 13 14 15 def l EMERGENCY ACTION LEVEL: Range fires near the plant which threaten to reduce the level of safety BASES: WNP-2 is located on a dry land steppe. Range fires routinely occur in this type of environment. This event has the potential to affect or cause the loss of safe shutdown systems and functions and, therefore, may be a precursor to a more serious event. REFERENCE(S): "NUMARCNESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI WNP-2 Plant Specific EAL Guideline, HU1.3

8 Hazards 8.4 Natural Events 8.4.U.4 Unusual Event NUMARC IC: HUI - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions I1 12 13 14 15 Idef I EMERGENCY ACTION LEVEL: Visible ash fallout from volcanic activity BASES: In May of 1980, Mount St. Helens volcano erupted. Prevailing winds spread up to 1/4" of volcanic ash on the WNP-2 site, with much heavier concentrations of ash several miles north of the site. Ash can clog diesel-generator air intakes and can be highly abrasive to rotating machinery. This event represents a potential degradation in the level of safety of the plant. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI WNP-2 Design Basis Ash Fallout, PPM 4.12.4.5 WNP-2 Plant Specific EAL Guideline, HU1.3

8 Hazards 8.4 Natural Events 8.4.U.5 Unusual Event NUMARC IC: HUI - Natural and destructive phenomena affecting the Protected Area Boundary. APPLICABILITY: Operating Conditions 1 2 13 14 5 defI EMERGENCY ACTION LEVEL: River level increase which threatens to flood the river pumphouse BASES: The Columbia Generating Station is located on an elevated plateau, well removed from risk of flooding by the Columbia River. The river pumphouse, located lower and closer to the river, may be prone to flooding. Should the river pumphouse be lost, the Standby Service Water Ultimate Heat Sink spray ponds have a 30 day supply of water. However, loss of the river pumphouse is deemed a potential degradation in the level of safety of the plant. The first Control Room indication of river pumphouse flooding would be TMU-LI-7 off-scale high. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HUI WNP-2 Flood, PPM 4.12.4.2 WNP-2 Plant Specific EAL Guideline, HU1.7 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 134 of 157

8 Hazards 8.4 Natural Events 8.4.A. I Alert NUMARC IC: HAI - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions 11 13 4 5 def EMERGENCY ACTION LEVEL: OPERATING BASIS EARTHQUAKE alarm (H1 3-P85 1-S 1-5.1) AND CR receives report from plant personnel who have felt an earthquake BASES: An earthquake that exceeds the OBE level is beyond the design basis limits for the plant as specified in the Safety Analysis Report, Section 3.7, Seismic Design. A seismic event of this magnitude can cause damage to safety-related systems and functions. Detection of this event includes activation of seismic monitoring instrumentation as evidenced by a valid alarm on P851-S 1-5.1, "OPERATING BASIS EARTHQUAKE EXCEEDED" along with confirmation from plant personnel who have physically felt the associated ground motion. An evaluation along with a thorough inspection of plant areas and systems will be used to determine the extent of plant damage and will provide the necessary information to determine if escalation to a higher emergency classification is required. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment lCs. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building

° Reactor Building 0 Vital portions of the Turbine Building 0 Standby Service Water Pump Houses 0 Diesel Generator Building

  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I. REFERENCE(S): Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.lA 7 1 135 of 157

NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA1 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA1.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 136 of 157

8 Hazards 8.4 Natural Events 8.4.A.2 Alert NUMARC IC: HAI - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions 11 14 5 def EMERGENCY ACTION LEVEL: Weather Service projected winds GT 100 mph OR CR measured winds GT 76 mph (5 minute average at 33 fit) OR Report by plant personnel confirming the occurrence of a tornado striking a plant safe shutdown building, Table 5 BASES: This event is a natural and potentially destructive phenomena that may accompany certain events such as a tornado or hurricane. These sustained high winds may also be produced by unstable weather conditions. However this event occurs, it may be a precursor to a more serious event and, therefore, represents a potential for substantial degradation in the level of safety of the plant. Sustained high winds at this level are beyond the design basis limits for the plant as described in SAR Section 3.3, Wind Loading. Wind loads of this magnitude have the potential to damage safety-related systems and functions. As such, the potential exists for substantial degradation of the level of the safety of the plant. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment ICs. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I. REFERENCE(S):

NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA1 PPM 4.12.4.8, WNP-2 Tornado/High Winds FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA1.2

8 Hazards 8.4 Natural Events 8.4.A.3 Alert NUMARC IC: HAl - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions I1 12 13 14 15 1def I EMERGENCY ACTION LEVEL: Ash fallout from volcanic activity is severe enough to warrant plant shutdown BASES: In May of 1980, Mount St. Helens volcano erupted. Prevailing winds spread up to 1/4" of volcanic ash on the WNP-2 site, with much heavier concentrations of ash several miles north of the site. Ash can clog diesel-generator air intakes and can be highly abrasive to rotating machinery. Should the Ash fallout be severe enough to warrant plant shutdown, the event additionally represents a potential for substantial degradation in the level of safety of the plant. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment ICs. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HAl WNP-2 Design Basis Ash Fallout, PPM 4.12.4.5 WNP-2 Plant Specific EAL Guideline, HA1.4

8 Hazards 8.4 Natural Events 8.4.A.4 Alert NUMARC IC: HAI - Natural and destructive phenomena affecting Safe Shutdown Buildings. APPLICABILITY: Operating Conditions 1 2 13 14 15 de EMERGENCY ACTION LEVEL: Report by plant personnel of an event causing visible structural damage to a safe shutdown building, Table 5 BASES: Visible structural damage is any observed physically degraded condition that indicates a significant impairment of the structural integrity of the building or area. An example of such a condition would be where a building sustained enough damage that it appears as if the roof could collapse at any time. The damage is based upon a report only. A detailed investigation or engineering evaluation is not required in order to classify the event. This EAL is intended to address events that may have resulted in Safe Shutdown Buildings being subjected to forces beyond design limits and, thus, damage may be assumed to have occurred to safe shutdown systems. The initial "report" should not be interpreted as mandating a lengthy damage assessment prior to classification. No attempt is made in these EALs to assess the actual magnitude of the damage. Escalation to a higher emergency class, if appropriate, will be based on the specific system malfunctions, fission product barrier degradation, abnormal radiological releases, or Emergency Director judgment 1Cs. For the purposes of this EAL, Safe Shutdown Buildings are considered to be the following locations:

  • Vital portions of the RadWaste/Control Building
  • Reactor Building
  • Vital portions of the Turbine Building
  • Standby Service Water Pump Houses
  • Diesel Generator Building
  • Diesel Generator Fuel Oil Storage Area This list was developed from equipment locations identified in FSAR Table 3.2-1, Seismic Category I.

Equipment in Safe Shutdown Buildings is identified in FSAR Table 3.2-1, Seismic Category I.

REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA1 FSAR Table 3.2-1 WNP-2 Plant Specific EAL Guideline, HA1.3 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 141 of 157

9.0 OTHER The EALs defined in categories 1.0 through 8.0 specify the predetermined symptoms or events which are indicative of emergency or potential emergency conditions, and which warrant classification. While these EALs have been developed to address the full spectrum of possible emergency conditions which may warrant classification and subsequent implementation of the Emergency Plan, a provision for classification of emergencies based on operator/management experience and judgment is still necessary. The EALs of this category provide the Shift Manager or Emergency Director (ED) the latitude to classify emergency conditions consistent with the established classification criteria, based upon their judgment.

9 Other 9.1.U.1 Unusual Event NUMARC IC: HU5 - Other conditions existing which, in the judgment of the Emergency Director, warrant declaration of an Unusual Event. APPLICABILITY: Operating Conditions I1 12 13:14 15 1def I EMERGENCY ACTION LEVEL: In the judgment of the Emergency Director, events are in progress or have occurred which indicate a potential degradation of the level of safety of the plant BASES: Events which are believed by the Emergency Director to indicate a potential degradation of the level of safety of the plant should be declared an Unusual Event. For those cases where the degradation in the level of the safety of the plant is tied to equipment or system malfunctions, the decision that the component is degraded should be based upon its functionality and not its operability. A system, subsystem, train, component or device, though degraded in equipment condition or configuration, is functional if it is capable of maintaining respective system parameters within acceptable design limits. Releases of radioactive material requiring offsite response or monitoring are not expected to occur at the Unusual Event level unless further degradation of safety systems occur. However, if one does occur, it will be classified under Category 5 "Radioactivity Release". REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HU5 WNP-2 Plant Specific EAL Guideline, HU1.5

9 Other 9.1.U.2 Unusual Event NUMARC IC: Los*s or potential loss of Primary Containment APPLICABILITY: Operating Conditions l1 12 13 1 1 1 EMERGENCY ACTION LEVEL: A event, in the judgment of the Emergency Director, that could lead to or has led to a loss or potential loss of primary containment as indicated by Fission Product Barrier Degradation Table, Table 6 BASES: This EAL addresses any other factors that are to be used by the Emergency Director in determining whether the containment barrier is lost or potentially lost. In addition, the inability to monitor the barrier should also be incorporated in this EAL as a factor in Emergency Director judgment that the barrier may be considered lost or potentially lost. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, PC6.1

9 Other 9.1 .A. 1 Alert NUMARC IC: HA6 - Other conditions existing which, in the judgment of the Emergency Director, warrant declaration of an Alert. APPLICABILITY: Operating Conditi-ons 1112 13 t4 15 1def I EMERGENCY ACTION LEVEL: In the judgment of the Emergency Director, events are in progress or have occurred which indicate actual or potential substantial degradation of the level of safety of the plant BASES: This Emergency Action Level is intended to address unanticipated conditions not addressed explicitly elsewhere but that warrant declaration of an emergency because conditions exist which are believed by the Emergency Director to fall under the Alert emergency class. This includes a determination by the Emergency Director that additional assistance similar to that provided by the TSC and OSC staffs, including a transfer of the Emergency Director responsibilities to the TSC, is necessary for the event to be effectively mitigated. Transfer of Emergency Director duties for classification, offsite notifications and PAR decisions, is used as an initiator since an event significant enough to warrant transfer of command and control is a substantial reduction in the level of safety of the plant. Activation of the TSC outside of the Emergency Plan in support of the Control Room staff is permissible. Releases that are expected to be limited to a small fraction of the EPA Protective Action Guideline exposure levels are addressed under Category 5 "Radioactivity Release". REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HA6 WNP-2 Plant Specific EAL Guideline, HA6.1

9 Other 9.1.A.2 Alert NUMARC IC: Loss or potential loss of fuel clad or RCS APPLICABILITY: Operating Conditions 1 2 13 1 1 r ] EMERGENCY ACTION LEVEL: AU event, in the judgment of the Emergency Director, that could lead or has led to a loss or potential loss of either fuel clad or RCS barrier as indicated by Fission Product Barrier Degradation Table, Table 6 BASES: This EAL addresses any other factors that are to be used by the Emergency Director in determining whether the fuel clad or RCS barriers are lost or potentially lost. In addition, the inability to monitor the barriers should also be considered in this EAL as a factor in Emergency Director judgment that the barriers may be considered lost or potentially lost. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline, FC5.1, RCS6.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 146 of 157

9 Other 9.1.S.1 Site Area Emergency NUMARC IC: HS3 - Other conditions existing which, in the judgment of the Emergency Director, warrant declaration of a Site Area Emergency. APPLICABILITY: Operating Conditions I1 12 13:14 15 1def I EMERGENCY ACTION LEVEL: In the judgment of the Emergency Director, events are in progress or have occurred which involve actual or likely major failures of plant functions needed for protection of the public BASES: This Emergency Action Level is intended to address unanticipated conditions not addressed explicitly elsewhere but that warrant declaration of an emergency because conditions exist which are believed by the Emergency Director to fall under the emergency class description for a Site Area Emergency. Radioactive releases are not expected to result in exposure levels which exceed EPA Protective Action Guideline exposure levels except within the site boundary. Radioactive releases to the general public are addressed under Category 5 "Radioactivity Release". REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HS3 WNP-2 Plant Specific EAL Guideline, HS3.1

9 Other 9.1.S.2 Site Area Emergency NUMARC IC: Loss or potential loss of any two fission product barriers APPLICABILITY: Operating Conditions 11 12 13 1 1 1 EMERGENCY ACTION LEVEL: Any event, in the judgment of the Emergency Director, that could lead or has led to a loss or potential loss of any two fission product barriers as indicated by Fission Product Barrier Degradation Table 6. BASES: This EAL addresses unanticipated conditions affecting fission product barriers which are not addressed explicitly elsewhere. Declaration of an emergency is warranted because conditions exist which are believed by the Emergency Director to fall under the emergency class description for Site Area Emergency. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 148 of 157

9 Other 9.1.G.1 General Emergency NUMARC IC: HG2 - Other conditions existing which, in the judgment of the Emergency Director, warrant declaration of a General Emergency.

0.0.1 APPLICABILITY

Operating Conditions 11 12 13 14 15 1defi EMERGENCY ACTION LEVEL: In the judgment of the Emergency Director, other conditions exist which indicate either of the following: Actual or imminent substantial core degradation or melting with the potential for loss of containment integrity OR Potential for uncontrolled radionuclide releases which can reasonably be expected to exceed EPA PAG plume exposure levels outside the site boundary BASES: This Emergency Action Level is intended to address unanticipated conditions not addressed explicitly elsewhere but that warrant declaration of an emergency because conditions exist which are believed by the Emergency Director to fall under the General Emergency class. Imminent in this context means mitigation strategies and actions are not successful in preventing a challenge to Fuel Clad, Reactor Coolant Pressure Boundary or Primary Containment. Radioactive releases may exceed EPA Protective Action Guideline exposure levels offsite for more than the immediate site area. Radioactive releases to the general public are addressed under Category 5 "Radioactivity Release". REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Unusual Event HG2 WNP-2 Plant Specific EAL Guideline, HG2.1 Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 1 149 of 157

9 Other 9.1.G.2 General Emergency NUMARC IC: A loss of any two fission product barriers and loss or potential loss of the third APPLICABILITY: Operating Conditions I1 12 13 1 1 17 EMERGENCY ACTION LEVEL: Any event, in the judgment of the Emergency Director, that could lead or has led to a loss of any two fission product barriers and loss or potential loss of the third as indicated by Fission Product Barrier Degradation Table, Table 6 BASES: This EAL addresses unanticipated conditions affecting fission product barriers which are not addressed explicitly elsewhere. Declaration of an emergency is warranted because conditions exist which are believed by the Emergency Director to fall under the emergency class description for the General Emergency class. REFERENCE(S): NUMARC NESP-007, Methodology for Development of Emergency Action Levels, Rev. 2, Fission Product Barrier Basis Information for Table 3 WNP-2 Fission Product Barrier Evaluation WNP-2 Plant Specific EAL Guideline Attachment 4.1 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 150 of 157

            ,,                                                                                                                                                                     (L TABLE 6, FISSION PRODU('                f BARRIER DEGRADATION TABI.E RAqER TABLE BASF.S Fuel Clad Loss               Fucl Clad Potential Loss          RCS Loss                     RCS Potential Loss                     PC Loss                  PC Potential Loss Coolant activity GT 300            RPV level LT -161 inches    Containment Radiation          Total RCS leakage GT 30          Rapid unexplained decrease       Containment Radiation p.Ci/gm dose equivalent           (for ATWS conditions,       Monitor CMS-RIS-27E            gpm inside PC or                 of PC pressure following an      Monitor CMS-RIS-27E iodine                            RPV level LT -192 inches)   and CMS-RIS-27F reading        EDR-FRS-623, Pen 2 upscale       initial increase                 and CMS-RIS-27F GT 70 R/hr                      high                                                              reading GT 14,000 R/hr Containment Radiation                                          RPV level LT - 161 inches      Unisolable primary system        Drywell pressure response        PC H2 and 02 Monitor CMS-RIS-27E and                                       (for ATWS conditions,           discharging outside PC           not consistent with LOCA         concentrations GT 6%

CMS-RIS-27F reading GT RPV level LT -192 inches) resulting in any area conditions H 2 and 5% 02 3,600 R/hr temperature or radiation level above Maximum Safe Operating Values (PPM 5.3. 1, "Secondary Containment Control")

 -        0 Entry into Severe Accident                                    Drywell pressure GT 1.68                                         Failure of containment           Entry into Severe Guidelines                                                    psig with indications of                                         isolation valves (LCS            Accident Guidelines RCS leakage inside                                              Table 1.6.3.1-1) in any one drywell                                                          line to close following auto     Loss of pressure or manual initiation              suppression function AND downstream pathway outside primary containment 2:

exists' OR Unisolable primary system Cannot maintain plant --.A. discharging outside PC parameters within resulting in any area HCTL, SRVTPLL temperature or radiation level above Maximum Safe

   '-...                                                                                                                                     Operating Values (PPM 5.3.1, "Secondary Containment Control")

Intentional venting per Wetwell pressure PPM 5.2.1, "Primary exceeds PSP Containment Control" I PC pressure GT PCPL Any event, in the judgment of the Emergency Director, that Any event, in the judgment of the Emergency Director, that Any event, in the judgment of the Emergency Director, could lead or has led to a loss or potential loss of the fuel could lead or has led to a loss or potential loss of the RCS that could lead to or has led to a loss or potential loss of clad barrier barrier primary containment barrier

TABLE 6, FISSION PRODUCT BARRIER DEGRADATION TABLE BASES (Contd.) Fuel Clad Loss Indicators Coolant activity GT 300 ,uCi/gm dose equivalent iodine Fuel Clad barrier damage is indicated by a coolant activity of 300 [tCi/gm dose equivalent 1-131. This amount of activity is well above that expected for iodine spikes and corresponds to approximately 2-5% fuel clad failure in accordance with assessment performed by the NUMARC EAL task force. This amount of clad failure indicates significant clad heating and, thus, the Fuel Clad barrier is considered lost. ContainmentRadiation Monitor CMS-RIS-27E and CMS-RJS-27F readingGT 3,600 R/hr A 3,600 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a release of reactor coolant, with elevated activity indicative of fuel damage, into the drywell. Therefore, this condition represents loss of both the fuel clad and RCS barriers. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory associated with coolant concentration associated with 5% clad failures into the drywell atmosphere. WNP-2 has elected to provide an example dealing with the top end of the 2-5% range discussed in NESP-007. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. Entry into Severe Accident Guidelines Entry into Severe Accident Guidelines is indicative of both a loss of fuel clad and RCS barriers because:

1) RPV water level cannot be restored and maintained above -161 inches, or
2) For ATWS conditions, RPV water level cannot be maintained above -192", or
3) If RPV water level cannot be determined, RPV flooding for ATWS or non-ATWS conditions cannot be established or maintained.

Entry into Severe Accident Guidelines is indicative of a potential loss of primary containment because actions to flood the containment may jeopardize the pressure suppression capability of the containment or result in the need to vent the RPV or primary containment. Attachment 4.2 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 152 of 157

TABLE 6, FISSION PRODUCT BARRIER DEGRADATION TABLE BASES (Contd.) Fuel Clad Potential Loss Indicators RPV level LT -161 inches (for ATWS conditions, RPV level LT -192 inches) Indicating fuel clad barrier potential Loss at -161" (Top of Active Fuel) or -192 inches for ATWS conditions, ensures that an emergency is declared before fuel perforation occurs. An unintentional level decrease to below -161" is also indicative of a large RCS break, or a smaller break with loss of high pressure makeup. During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192 inches (minimum steam cooling RPV water level. RCS Loss Indicators Containment Radiation Monitor CMS-RJS-27E and CMS-RJS-27F reading GT 70 R/hr A 70 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate a loss of the Reactor Coolant System barrier. This value assumes a 0.1% clad damage and the instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. The value of 0.1% clad damage was assumed to be the greatest amount of fuel failure under which power operation could occur. RPV level LT -161 inches (for A TWS conditions,RPV level LT -192 inches) An unintentional level decrease to below -161" or -192 inches for ATWS conditions is also indicative of a large RCS break, or a smaller break with loss of high pressure makeup. During ATWS conditions, level may be intentionally lowered to reduce reactor power. This level decrease is not indicative of an RCS break as long as level is maintained above -192 inches (minimum steam cooling RPV water level. Drywell pressure GT 1.68 psig with indicationsof RCS leakage inside drywell The 1.68 psig drywell pressure for the Reactor Coolant System barrier loss is based on the drywell pressure scram and isolation setpoint and indicates a Loss of Coolant Accident (LOCA). A potential loss of the Reactor Coolant System barrier would not result in an increasing drywell pressure and, therefore, no indicator is provided. The qualifier of "with indications of RCS leak inside drywell" is included as an indicator of RCS boundary degradation and eliminates a drywell pressure increase due to a loss of drywell ventilation. TABLE 6, FISSION PRODUCT BARRIER DEGRADATION TABLE BASES (Contd.)

RCS Potential Loss Indicators Total RCS leakage GT 30 gpm inside PC or EDR-FRS-623, Pen 2 upscale high Total leakage is considered to be the total of both identified and unidentified leakage as measured on EDR-FRS-623 pen 1 (unidentified - Floor Drain Sump Fill Rate) and pen 2 (identified - Equipment Drain Sump Fill Rate). The maximum measurable identified leak rate (pen 2) in the Control Room at WNP-2 is 30 gpm,-therefore 30 gpm is used instead of the 50 gpm limit recommended by NUMARC. Unisolableprimary system dischargingoutside PC resulting in any area temperatureor radiationlevel above Maximum Safe Operating Values (PPM5.3.1, "Secondary Containment Control') The presence of elevated area temperatures and/or radiation levels in the secondary containment may be indicative of an unisolable primary system leakage outside the primary containment. These conditions represent a loss of the containment barrier and a potential loss of the RCS barrier. PC Loss Indicators Rapid unexplained decreaseof PC pressurefollowing an initialincrease Rapid unexplained loss of pressure (i.e., not attributable to drywell spray or condensation effects) following initial pressure increase indicates a loss of containment integrity. In interpreting this EAL, an initial increase is any PC pressure increase above 1.68 psig. A rapid decrease should be considered any decrease which occurs faster than the initial increase. Drywell pressure response not consistent with LOCA conditions Containment or drywell pressure responses not consistent with LOCA conditions indicate a loss of the Primary Containment barrier. This may be noticed as a decrease in drywell pressure when no operation action (e.g., starting drywell cooling fans) has been taken. It would also include a failure of the drywell pressure to increase as expected during a LOCA.

TABLE 6, FISSION PRODUCT BARRIER DEGRADATION TABLE BASES (Contd.) Failureof containment isolation valves (LCS Table 1.6.1.3-1) in any one line to closefollowing auto or manual initiation AND downstream pathway outside primary containment exists OR Unisolableprimary system dischargingoutside PC resulting in any area temperatureor radiationlevel above Maximum Safe Operating Values (PPM5.3. 1, "Secondary Containment Control") The failure to isolate condition is intended to cover containment isolation failures allowing a direct flow path to the environment such as a failure of MSIVs to close with open valves downstream to the turbine or condenser. Downstream path outside primary containment does not mean leakage incident to normal system integrity. Only those penetrations required to isolate per Technical Specifications should be considered. The presence of elevated area temperatures and/or radiation levels in the secondary containment may be indicative of an unisolable primary system leakage outside the primary containment. These conditions represent a loss of the containment barrier and a potential loss of the RCS barrier. Intentionalventing per PPM5.2.1, "PrimaryContainment Control" Venting, if necessary to prevent failure of primary containment, is included as a loss of primary containment. This is specified in PPM 5.2.1, "Primary Containment Control" when containment hydrogen and oxygen concentrations are in excess of or cannot be determined to be below combustible limits or when wetwell pressure approaches PCPL. However, routine venting per PPM 2.3.1, as long as radioactivity release rates are maintained, is not considered a loss of primary containment. PC Potential Loss Indicators Containment Radiation Monitor CMS-RIS-27E and CMS-RIS-27F reading GT 14, 000 R/hr An 14,000 R/hr reading on CMS-RIS-27E and CMS-RIS-27F is used to indicate potential failure of the primary containment barrier. It is a value that indicates significant fuel damage well in excess of that associated with the loss of both Fuel Clad and RCS barriers. A major release of radioactivity requiring offsite protective actions is not possible unless a major failure of fuel cladding allows radioactive material to be released from the core into the reactor coolant.

TABLE 6, FISSION PRODUCT BARRIER DEGRADATION TABLE BASES (Contd.) Regardless of whether containment is challenged, this amount of activity in containment, if released, could have such severe consequences that it is prudent to treat this as a potential loss of containment, such that a General Emergency declaration is warranted. This level of activity is indicative of approximately 20% clad failure. This value assumes an instantaneous release and dispersal of the reactor coolant noble gas and iodine inventory into the drywell atmosphere. PC H 2 and 02 concentrationsGT 6% H 2 and 5% 02 Hydrogen and Oxygen concentrations at or above PPM 5.2.1, "Primary Containment Control", Table 19, Combustible Limits, in the drywell or wetwell represent a potential for a deflagration with a subsequent containment failure. Entry into Severe Accident Guidelines Entry into Severe Accident Guidelines is indicative of a potential loss of primary containment because actions to flood the containment may jeopardize the pressure suppression capability of the containment or result in the need to vent the RPV or primary containment. Loss ofpressuresuppressionfunction Physical degradation of the containment structure as indicated by an equalization between suppression chamber and drywell pressures constitutes a loss of pressure suppression capability and should be considered a potential loss of containment. Cannot maintainplantparameters within HCTL, or SR VTPLL The Heat Capacity Temperature Limit (HCTL) is the highest wetwell temperature at which initiation of RPV depressurization will not result in exceeding the Primary Containment Pressure Limit (PCPL) before the rate of energy transfer to the containment is within the capacity of the containment vent. The HCTL is used to preclude failure of the containment or equipment necessary for safe shutdown by assuring that RPV blowdown does not cause containment pressure to exceed the PCPL. The potential loss occurs when RPV pressure and wetwell temperature cannot be maintained below HCTL. The SRV Tail Pipe Level Limit (SRVTPLL) is the highest wetwell water level at which opening of an SRV will not result in exceeding the code allowable stresses in the tailpipe, tailpipe supports, quenchers or quencher supports. This level is a function of RPV pressure and the Limit is utilized to preclude SRV system failure and containment failure. The consequences of operating SRVs when wetwell water level exceeds the SRVTPLL may include direct pressurization of the containment from a break in the SRV tail pipe. The resulting primary containment pressurization could cause containment failure. Attachment 4.2 PROCEDURE NUMBER REVISION PAGE 13.1.1A 7 156 of 157

TABLE 6. FISSION PRODUCT BARRIER DEGRADATION TABLE BASES (Contd.) Wetwell pressure exceeds PSP Entry into the unsafe region of the Pressure Suppression Pressure curve (PPM 5.2.1, "Primary Containment Control", Figure F, PSP) is included as a potential primary containment barrier loss. A rapid depressurization of the RPV (e.g., occurrence of a large break LOCA or initiation of ADS) at wetwell pressures in excess of the PSP may cause either: Wetwell pressure responses indicative of a failure in the drywell-to-wetw-ell boundary, or Wetwell pressure increases to or beyond the Primary Containment Pressure Limit (PPM 5.2.1, "Primary Containment Control", Figure B, PCPL). PCpressure GTPCPL and increasing Containment pressures that exceeds 34.7 psig, the maximum expected pressure following a LOCA, have the potential to result in a loss of the containment barrier. Preparations to vent containment are required by PPM 5.2.1, "Primary Containment Control" when Drywell pressure exceeds PCPL and before the Wetwell pressure reaches the Primary Containment Pressure Limit (PCPL). Therefore, this condition is considered a potential loss of containment.

ENERGY USE CURRENT REVISION NORTHWEST COLUMBIA GENERATING STATION PLANT PROCEDURES MANUAL PROCEDURE NUMBER APPROVED BY DATE

         "*13.2.1                                       DWC - Revision 15              -      02/22/01 VOLUME NAME EMERGENCY PLAN IMPLEMENTING PROCEDURES SECTION PROTECTIVE MEASURES TITLE EMERGENCY EXPOSURE LEVELS/PROTECTIVE ACTION GUIDES TABLE OF CONTENTS 1.0     PURPOSE        ..................................................                                     2

2.0 REFERENCES

            ...............................................                                2 3.0     PRECAUTIONS AND LIMITATIONS ................................                                          2 4.0     PROCEDURE ................................................                                            3 4.1      Emergency Worker PAGs ....................................                                   3 4.2      Public Protective Action Guides ................................                             4 4.3      Administration of Potassium Iodide (KI) ...........................                          4 5.0     ATTACHM ENTS ..............................................                                           5 5.1      Federal Personnel Dose Limits (10CFR20) .........................                            6 5.2      EPA 400 Protective Action Guides For Emergency Workers ...............                       7 5.3      Protective Action Guides (PAG) For The Plume Exposure Pathway ...........                    8 5.4      Guidance for Administering Potassium Iodide (KI) ......................                      9 5.5      Emergency Exposure Request .................................                                14 PROCEDURE NUMBER                           REVISION                          PAGE 13.2.1                                             15                  1 of 14

1.0 PURPOSE This procedure outlines the authority and process for exceeding annual administrative exposure holdpoints and implementing EPA-400 limits for emergency worker Protective Action Guides (PAGs). Additionally, it provides guidance for administration of potassium iodide (KI) and authorization of Emergency Exposures above EPA-400 limits during emergency situations. {R-1599}

2.0 REFERENCES

2.1 Letter No. G02-93-125, Supply System to NRC, Dated May 27, 1993 {2.1} 2.2 FSAR, Chapter 13.3, Emergency Plan, Section 5 2.3 10CFR50.47(b)(11) {R-1599} 2.4 10CFR20, Standards for Protection Against Radiation 2.5 State of Washington - Department of Health, "Response Procedures for Radiation Emergencies", June 1993 2.6 United States Environmental Protection Agency, "Manual of Protective Action Guides and Protective Actions for Nuclear Incidents", EPA 400, May 1992 2.7 GEN -RPP-05, Respiratory Program Description 2.8 GEN-RPP-07, Personnel Exposure Limits and Monitoring Requirements 2.9 GEN-RPP-10, Use of Respiratory Protection Equipment 2.10 PPM 13.2.2, Determining Protective Action Recommendations 2.11 PPM 13.13.3, Intermediate Phase MUDAC Operations 3.0 PRECAUTIONS AND LIMITATIONS 3.1 Declaration of an Alert or higher emergency classification automatically waives Energy Northwest administrative exposure holdpoints. 3.2 Only pressure-demand self-contained breathing apparatus should be used for entries into atmospheres immediately-dangerous-to-life-or-health (IDLH), or into areas where the level of hazard has not been assessed because of the existence of unusual conditions, or because of unanticipated releases of radioactive material. Airborne radioactivity surveys should be performed as soon as possible in order to evaluate the use of other respiratory protection equipment in accordance with GEN RPP-05 and GEN-RPP-10. 3.3 If respiratory protection equipment is not prescribed, administer potassium iodide (KI) as outlined in Attachment 5.4. {2.1} PROCEDURE NUMBER REVISION PAGE 13.2.1 15 12 of 14

3.4 The Emergency Director has the authority and responsibility for approving emergency worker exposures above the EPA PAG of 5 rem. He may delegate this authority and responsibility. 4.0 PROCEDURE 4.1 Emergency Worker PAGs Responsibilities of the Radiation Protection Manager (for workers within the Protected Area), and Radiological Emergency Manager (for Energy Northwest emergency workers and field team members at any location outside of the Protected Area): NOTE: When implementing emergency authorized exposure guides, prompt, sound judgment and flexibility of action are crucial to the success of any type of emergency action. 4.1.1 Evaluate alternatives prior to granting authorization to exceed the EPA PAG emergency worker guidelines. Refer to Attachment 5.2.

a. Consideration of approving additional exposure beyond 5 rem should include the following:

The presence of conditions that prevent the rotation of workers or other commonly used dose reduction methods. The exposure of workers that is incurred for the protection of large populations may be justified for situations in which the collective dose avoided by the emergency operation is significantly larger than incurred by the workers involved. 4.1.2 When authorizing exposures in excess of emergency worker limits, refer to Attachment 5.2, Protective Action Guides For Emergency Workers. NOTE: The exposure values described below are intended as guides and not absolute limits. These guidelines are contained in the referenced EPA 400 Manual. 25 rem Total Effective Dose Equivalent (TEDE) for life-saving or protection of large populations

  • 10 rem TEDE for situations to protect valuable property 4.1.3 Obtain concurrence from the Emergency Director or designee prior to implementing emergency exposure guides above EPA PAG limits, and:
a. Caution personnel to maximize efforts to remain below emergency worker limits.

PROCEDURE NUMBER REVISION PAGE 13.2.1 15 3 of 14

4.1.4 Document the request and justification for the Emergency Exposure on Attachment 5.5, Emergency Exposure Request.

a. Following completion of the Emergency Exposure Request, submit the request to the Emergency Director or designee for signature.

4.2 Public Protective Action Guides Responsibilities of the Emergency Director and Radiation Protection Manager or Radiological Emergency Manager, and Protective Action Decisi6n Group in MUDAC: 4.2.1 Refer to Attachment 5.3, Protective Action Guides for the Plume Exposure Pathway, for guidance in developing public Protective Action Recommendations (PARs) for the Plume Emergency Planning Zone. 4.2.2 Refer to PPMs 13.13.3 and 13.2.2 for Protective Action Recommendation guidance. 4.3 Administration of Potassium Iodide (KI) 4.3.1 Shift Manager Duties (as Emergency Director)

a. Refer to Attachment 5.4, Guidance for Administering Potassium Iodide 0K1).
b. When action conditions are reached, recommend self administration of KI to shift workers within the protected area. Consider emergency workers in the Control Room, Central Alarm Station, Operations Support Center, Technical Support Center and any other Protected Area location deemed necessary.

4.3.2 Radiation Protection Manager Duties

a. Refer to Attachment 5.4, Guidance for Administering Potassium Iodide (KI).
b. When action conditions are reached, advise the TSC Manager that KI be recommended for affected emergency workers within the protected area. Consider emergency workers in the Control Room, Central Alarm Station, Operations Support Center, Technical Support Center and any other Protected Area location deemed necessary.

4.3.3 TSC Manager Duties Direct the appropriate centers to recommend self administration of KI by emergency workers. PROCEDURE NUMBER REVISION PAGE 13.2.1 15 4 of 14

4.3.4 Radiological Emergency Manager Duties

a. Refer to Attachment 5.4, Guidance for Administering Potassium Iodide (KI).
b. When action conditions are reached, advise the EOF Manager that KI be recommended for affected emergency workers outside of the protected area. Consider all emergency workers within the Plume Exposure Emergency Planning Zone (EPZ).

4.3.5 EOF Manager Duties

a. Recommend affected Energy Northwest workers outside of the Protected Area to self administer KI.
b. Notify offsite authorities (State and County) that the State criteria for recommending KI has been met.

5.0 ATTACHMENTS 5.1 Federal Personnel Dose Limits (10CFR20) 5.2 EPA 400 Protective Action Guides For Emergency Workers 5.3 Protective Action Guides (PAG) For The Plume Exposure Pathway 5.4 Guidance for Administering Potassium Iodide (KI) 5.5 Emergency Exposure Request PROCEDURE NUMBER REVISION PAGE 13.2.1 15 15 of 14

FEDERAL PERSONNEL DOSE LIMITS (10CFR20) Dose Limits for Adults, Embryo/Fetus, Minors, Members of the Public, and PSEs. The licensee shall control the occupational dose to individual adults (20.1201), dose to an embryo/fetus during the entire pregnancy for declared pregnant women (20.1208), doses to minors (20.1207), individual members of the public (20.1301), and exposures necessary due to an exceptional situation constituting a planned special exposures (20.1206). The following dose limits apply: 0 The total effective dose equivalent (TEDE) for adult workers shall be limited to 5 rem (5,000 mrem) per year.

  • The total organ dose equivalent (TODE) for adult workers shall be limited to 50 rem (50,000 mrem) per year.
  • The lens dose equivalent (LDE) for adult workers shall be limited to 15 rem (15,000 mrem) per year.
  • The shallow dose equivalent (SDE) to the skin or to any extremity for adult workers shall be limited to 50 rem (50,000 mrem) per year.
  • Hot particle exposure limits are the same as the shallow dose equivalent (SDE) limit to the skin (50 rem/yr), but will not be added to skin dose(s) from sources other than hot particles, nor are hot particles exposures from different particles summed unless the different particles result in doses to the same area (within 1 cm) of the skin.

The dose to the embryo/fetus during the entire pregnancy, due to occupational exposure of a declared pregnant woman, shall not exceed 0.5 rem (500 mrem) TEDE. If the embryo/fetus has accumulated 0.5 rem or greater during the time between conception and declaration, the embryo/fetus shall be limited to 0.05 rem (50 mrem) for the remainder of the pregnancy. The annual occupational dose limits for minors are 10 percent of the annual dose limits specified for adult workers. Individual members of the general public shall be limited to 0.1 rem per year (100 mrem) TEDE from licensed operations. Attachment 5.1 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 6 of 14

EPA 400 PROTECTIVE ACTION GUIDES FOR EMERGENCY WORKERS DOSE LIMIT (TEDE)+ ACTIVITY PROTECTIVE ACTIONS 5 rem ALL 10 rem PROTECTING VALUABLE Lower dose not practicable PROPERTY 25 rem LIFE-SAVING OR Lower dose not practicable PROTECTION OF LARGE POPULATIONS

    > 25 rem               LIFE-SAVING OR                        Only on a voluntary basis to persons fully PROTECTION OF                         aware of the risks involved.

LARGE POPULATIONS NOTE: Refer to Attachment 5.4 for information concerning the administration of Potassium Iodide (KI). + Sum of external effective dose equivalent and committed effective dose equivalent to nonpregnant adults from exposure and intake during an emergency situation. Workers performing services during emergencies should limit dose to the lens of the eye to three times the listed value and doses to any other organ (including skin and body extremities) to ten times the listed value. These limits apply to all doses from an incident, except those received in an unrestricted area as members of the public during the intermediate phase of the incident. + + CEDE is the risk weighted sum of committed dose equivalent (CDE). CDE is the total dose from internally deposited radionuclide over a subsequent 50 year period. Attachment 5.2 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 7 of 14

PROTECTIVE ACTION GUIDES (PAG) FOR THE PLUME EXPOSURE PATHWAY Total Effective Thyroid Population Dose Equivalent (rem) CDE (rem) General Public 1 5 The PAG limits the Total Effective Dose Equivalent (TEDE) which is the sum of the deep dose equivalents (DDE) resulting from external exposure to plume or ground deposition and the committed effective dose equivalent (CEDE) projected over 50 years incurred from all significant inhalation pathways during the early phase. Committed dose equivalents (CDE) to the thyroid and to the skin may be 5 and 50 times larger, respectively. Attachment 5.3 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 8 of 14

GUIDANCE FOR ADMINISTERING POTASSIUM IODIDE (KI A. Purpose This attachment provides guidelines for recommending administration of potassium iodide (KI) to all emergency workers both on and offsite as a thyroid-blocking agent to provide protection against airborne radioiodine. B. Location of KI Supplies

1. Control Room
2. Technical Support Center
3. Operations Support Center
4. In-plant Emergency Equipment Cabinets
5. Emergency Operations Facility
6. Field Team Kits
7. Protected Area Access Point (PAAP)

C. Discussion Each THYRO-BLOCK tablet contains 130 mg of potassium iodide (KI). Certain forms of iodine help the thyroid gland work. The thyroid can "store" or hold only a certain amount of iodine. In a radiation emergency, radioactive iodine may be released in the air where it may be breathed or swallowed. It may enter the thyroid gland and damage it by overexposure. When potassium iodide is administered, it saturates the thyroid gland, thereby reducing the chance that harmful radioactive iodine will enter the thyroid gland. Possible side. effects include skin rashes, swelling of the salivary glands, and "iodism", (metallic tastes, burning mouth and throat, sore teeth and gums, symptoms of a head cold, and sometimes upset stomach and diarrhea). A few people have an allergic reaction with more serious symptoms. These could be fever and joint pains, or'swelling of parts of the face and body and at times, severe shortness of breath that requires immediate medical attention. Taking iodine may rarely cause overactivity of the thyroid gland, underactivity of the thyroid gland, or enlargement of the thyroid gland (goiter). The only people who should not take potassium iodide are people who know they are allergic to iodine. One may take potassium iodide even if you are taking medicine for a thyroid problem (for example, a thyroid hormone or anti-thyroid drug). Pregnant and nursing women can also take this drug. Attachment 5.4 Page 1 of 5 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 9 of 14

GUIDANCE FOR ADMINISTERING POTASSIUM IODIDE (KI) (Contd.) D. Precautions

1. Potassium iodide should not be used by people allergic to iodine. In case of overdose or allergic reaction, refer the individual to medical personnel.
2. Doses recommended by these guidelines should be followed by all applicable personnel to avoid overdoses or insufficient protection.
3. Only the TSC Manager and EOF Manager (or the Shift Manager acting as Emergency Director) can authorize the use of THYRO-BLOCK. They SHALL establish the extent and duration of the THYRO-BLOCK usage, based on radiological conditions and the advice of the Radiation Protection Manager or Radiological Emergency Manager, as appropriate.

E. Determination of KI Use NOTE: If airborne Iodine concentrations have not been analyzed, consider plant conditions including the potential for unmonitored/unfiltered releases from the reactor coolant pressure boundary to occupied, or potentially occupied spaces.

1. The EOF Manager, in consultation with the Radiological Emergency Manager, should notify the State and County authorities that the State criteria for administering KI based on the following criteria has been met:
         "* Projected or actual 250 mrem/hr to the Thyroid, OR
         "* Air sample results > 1.4 x      10-7/ixCi/cc 1-131
2. The TSC Manager, or the Shift Manager acting as the Emergency Director, in consultation with the Radiation Protection Manager, should recommend that emergency workers in any affected Protected Area location take KI:

0 If the projected thyroid CDE is 25 rem or more

3. As directed by the Radiation Protection Manager, personnel within the Protected Area shall use appropriate respiratory protection, and/or KI for thyroid protection.

Attachment 5.4 Page 2 of 5 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 10 of 14

GUIDANCE FOR ADMINISTERING POTASSIUM IODIDE (KI) (Contd.)

4. The EOF Manager, in consultation with the Radiological Emergency Manager, should recommend that Energy Northwest emergency workers at affected locations outside the Protected Area (Security personnel, environmental field teams, etc.) take KI:
  • If the projected thyroid CDE is 25 rem or more
  • 25 rem CDE thyroid is 1000 DAC-hours and is equivalent to an intake of approximately 25 !Ci Iodine-131
5. Determine the radiological conditions in occupied areas using the following methods, as applicable:
         "* Dose rate surveys
         "* Air samples
         "* Continuous Air Monitor (CAM) readings
         "* Area Radiation Monitor readings
         "* Plant effluent process monitor readings
         "* Offsite dose projection (EDPS) data
6. Determine if nonessential personnel could be evacuated from affected areas to prevent potential, large thyroid doses.
7. Based on actual (or potential) radiological conditions, determine the projected thyroid dose to personnel in occupied, affected areas.

NOTE: The FDA's Bureau of Radiological Health and Drugs Bulletin Volume XVI, Number 7, recommends issuance of KI to individuals projected to receive a thyroid dose of 25 rem CDE or more.

8. If the projected dose to affected personnel has exceeded, or is projected to exceed 25 rem CDE thyroid, recommend to the TSC Manager or EOF Manager that KI be administered (to affected personnel only).

NOTE: To be most effective, potassium iodide must be taken immediately prior to, or within a few hours after exposure to high concentrations of radioiodine. Attachment 5.4 Page 3 of 5 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 11lofl14

GUIDANCE FOR ADMINISTERING POTASSIUM IODIDE (KI) (Contd.)

9. If and when the TSC Manager or EOF Manager (or Shift Manager as Emergency Director) decide to administer KI to affected personnel, refer to Section F of this Attachment.
10. The EOF Manager should notify offsite authorities (State, County) when the State criteria for recommending KI has been met.

NOTE: The use of potassium iodide is strictly voluntary. F. KI Issuance Instructions CAUTION: Prior to issuing Potassium Iodide, personnel should be cautioned to NOT participate if they know that they are allergic to iodine.

1. For areas within the Protected Area, the RPM will coordinate the issuance of KI to affected individuals.
2. For areas outside the Protected Area, the REM will coordinate the issuance of KI to affected individuals.
3. Issue KI to affected individuals as follows:
         "* Question personnel to determine if they know if they are allergic to iodine, and if so, DO NOT issue KI to those individuals.
         "* Determine if individuals will voluntarily participate (by taking KI) as directed.
         "* For participating individuals, issue one bottle of potassium iodide (KI) tablets to each individual whose thyroid dose is projected to exceed 25 rem CDE.
         "* Provide a THYRO-BLOCK information pamphlet to all individuals issued KI and ensure personnel are aware of the following information:

The recommended KI dosage is one tablet daily, for a period not to exceed 10 days

              -      Do not exceed the recommended dosage Attachment 5.4 Page 4 of 5 PROCEDURE NUMBER                  REVISION                          PAGE 13.2.1                            15                           12 of 14

GUIDANCE FOR ADMINISTERING POTASSIUM IODIDE (KI) (Contd.) Begin taking KI when directed by the TSC Manager or EOF Manager (or Shift Manager acting as Emergency Director) To be most effective, KI should be taken shortly before, or immediately after, exposure to radioiodine, however, the initial administration will still have substantial benefit if it is taken three or four hours after exposure

            -      If side effects are experienced, stop taking KI, notify your supervisor and obtain medical attention Using the Personnel Accountability Log or other appropriate log, record the following information:
            -      The name of the individuals contacted
            -      Whether the individual participated in KI administration
            -      The date and time the individual began using KI
4. Upon completion of KI issuance to affected personnel, inform the TSC Manager and the EOF Manager of any individuals that decline to use KI.
5. Return all completed Personnel Accountability Logs or other logs used to issue KI to the RPM and REM.
6. When directed, personnel should discontinue taking KI and return the unused portion to the Plant for proper disposal.
7. The Personnel Accountability Logs or other logs used to issue KI should be completed by indicating the date individuals discontinued KI use.

Attachment 5.4 Page 5 of 5 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 13 of 14

EMERGENCY EXPOSURE REQUEST TASK/JUSTIFICATION FOR INCREASED EXPOSURE: Exposure Limit for This Individual: INDIVIDUAL INFORMATION: Name: Date: SSN: Exposure (YTD): Lifetime: I have received instructions in the measures to be taken, the radiological conditions, and have been advised of the associated risks involved. Individual to receive increased exposure: (Signature required if expected to exceed GT TEDE 25 REM) COGNIZANT EMERGENCY MANAGER (RPM or REM) All evaluations are complete, documented and attached, if necessary: Radiation Protection Manager, or Radiological Emergency Manager: Date: APPROVAL: Emergency Director or Designee: Date: Attachment 5.5 PROCEDURE NUMBER REVISION PAGE 13.2.1 15 14 of 14

DATE: 02/22/01 EDITORIAL 13.14.4

3.10 PPM 13.14.9, Emergency Program Maintenance 3.11 PPM 13.10.6, Plant/NRC Liaison Duties I 3.12 EPI-15, ERDS Quarterly Test 3.13 Emergency Response Log, 968-23895 3.14 Classification Notification Forms, 968-24075 3.15 Event Notification Worksheet, NRC Form 361, 968-25665 3.16 Repair Team Briefing/Debriefing Form, 968-25560 3.17 Emergency Director Turnover Sheet, 968-25810 3.18 10 Mile EPZ Dose Projection and Data Map Form, 968-25831 3.19 Skin/Clothing Contamination Report, 968-24080 4.0 PROCEDURE 4.1 Supervisor, Health Physics Operations Responsibilities 4.1.1 Ensure cabinets or vehicles containing emergency first aid, fire brigade equipment, or radiological protection equipment are checked at the locations, and per instructions outlined in Attachments 5.1-1, 5.1-2, 5.1-3, 5.1-4, 5.1-5, and 5.1-7. 4.1.2 Ensure the following are checked per the instructions outlined in Attachment 5.2, EOF/ENOC Emergency Equipment: Field Monitoring Kits: Location:

  • Kootenai Building and MPF Decon Storage Area:

Location: 0 ENOC Room 1-208A, MPF PROCEDURE NUMBER REVISION PAGE 13.14.4 34 4 of 71

INSTRUCTIONS FIELD SAMPLING KIT (Cont.) Passport Activities: FIELD SAMPLE KIT IFS FIELD SAMPLE KIT 2FS FIELD SAMPLE KIT 3FS FIELD SAMPLE KIT 4FS Locations:

     "*    Kit IFS - Field Team Cabinet Number 1, Kootenai Building Health Physics Center
     "*    Kit 2FS - Field Team Cabinet Number 2, Kootenai Building Health Physics Center
     "*    Kit 3FS - Field Team Cabinet Number 3, Kootenai Building Health Physics Center
     "*    Kit 4FS - ENOC, Cabinet Number 4, MPF, 1st Floor, Room 201 Quarterly (and after use or if seal not intact):
     "*    Inventory contents and ensure required quantities are correct.
     "*    Check physical condition of contents and replace, as necessary.

Attachment 5.2-1 Page 2 of 2 PROCEDURE NUMBER REVISION PAGE 13.14.4 34 27 of 71

INSTRUCTIONS PROTECTIVE CLOTHING KIT (Cont.) Passport Activities: PC KIT 1PC PC KIT 2PC PC KIT 3PC PC KIT 4PC Locations:

      "*    Kit 1PC - Field Team Cabinet Number 1, Kootenai Building Health Physics Center
      "*    Kit 2PC - Field Team Cabinet Number 2, Kootenai Building Health Physics Center
  • Kit 3PC - Field Team Cabinet Number 3, Kootenai Building Health Physics Center
  • Kit 4PC - ENOC, Cabinet Number 4, MPF, 1st Floor, Outside Room 201 Quarterly (and after use or if seal not intact):
      "*    Inventory contents and ensure required quantities are correct.
      "*    Check physical condition of contents and replace, as necessary.

Attachment 5.2-2 Page 2 of 2 PROCEDURE NUMBER REVISION PAGE 13.14.4 34 29 of 71

INSTRUCTIONS AIR SAMPLING KIT (Cont.) Passport Activities: AIR SAMPLE KIT 1AS AIR SAMPLE KIT 2AS AIR SAMPLE KIT 3AS AIR SAMPLE KIT 4AS Locations:

     "*     Kit 1AS - Field Team Cabinet Number 1, Kootenai Building Health Physics Center
     "*     Kit 2AS - Field Team Cabinet Number 2, Kootenai Building Health Physics Center
     "*     Kit 3AS - Field Team Cabinet Number 3, Kootenai Building Health Physics Center
     "*     Kit 4AS - ENOC, Cabinet Number 4, MPF, 1st Floor, Room 201 Quarterly (and after use or if seal not intact):
     "*     Inventory contents and ensure required quantities are correct.
     "*     Check physical condition of contents and replace, as necessary.
     "*     Verify air sampler calibration date will not be exceeded prior to the next quarterly check.

Replace with a fresh calibrated air sampler as needed.

     "*     Start-up air sampler.
     "*     Perform operational check of stopwatch.
     "*     Ensure expiration date of Silver Zeolite Cartridges will not be exceeded prior to the next quarterly check; however:
            -      If contained in manufacturer's sealed bags, cartridges are good for ten years;
            -      If contained in other than manufacturer's sealed bags, cartridges are good for one year.
            -      Replace as required.
     "*     Verify charcoal packets are sealed and if not sealed, replace.

Attachment 5.2-3 Page 2 of 2 PROCEDURE NUMBER RE3SION PACE 13.14.4 34 31 of 71

INSTRUCTIONS INSTRUMENTATION KIT (Cont.) Passport Activities: QTRLY INST KIT IlK QTRLY INST KIT 21K QTRLY INST KIT 31K QTRLY INST KIT 41K CHANGEOUT RADIOS Locations: "* Kit IlK - Field Team Cabinet Number 1, Kootenai Building Health Physics Center "* Kit 21K - Field Team Cabinet Number 2, Kootenai Building Health Physics Center "* Kit 31K - Field Team Cabinet Number 3, Kootenai Building Health Physics Center

  • Kit 41K - ENOC, Cabinet Number 4, MPF, 1st Floor, Outside Room 201 Quarterly (and if used or if seal not intact):

"* Inventory contents and ensure required quantities are correct. "* Check physical condition of contents and replace, as necessary. "* Ensure portable instrument calibration dates will not be exceeded prior to the next quarterly check. Replace with fresh calibrated instruments as needed. "* Perform operational checks:

  • Portable instruments (battery check)
  • Calculator
  • Battery lantern
  • Flashlight

"* Ensure expiration dates will not be exceeded prior to the next quarterly check:

  • Credit cards
  • Iodine tablets Annually:
  • Replace radios (obtain replacement radios and batteries from radio/battery charging unit in PSF Room 118A cabinet next to decon showers and deliver replaced radio/batteries to Telecommunications for operational check).

Attachment 5.2-4 Page 2 of 2 PROCEDURE NUMBER REVISION PAGE 13.14.4 34 33 of 71

INSTRUCTIONS DECON CABINET (Cont.) Passport Activity: DECON CABINET Location:

  • DC - Emergency Cabinet Number 14, Kootenai Building Health Physics Decon Shower Area Quarterly (and after use or if seal not intact):
     "*    Inventory contents and ensure required quantities are correct.
     "*    Check physical condition of contents and replace, as necessary.
     "*    Ensure calibration/expiration dates will not be exceeded prior to next quarterly check, and replace as needed:
           -      Portable instrument
           -      Chemicals
     "*    Perform operational check on portable instruments (battery check).

Attachment 5.2-5 Page 2 of 2 PROCEDURE NUMBER REVISION PAGE 13.14.4 34 35 of 71

INSTRUCTIONS EXTRA PROTECTIVE CLOTHING (Cont.) Passport Activities: EXTRA PC KIT 1XP QTRLY CHK PC KIT 2PC Location:

     "*     Kit 1XP - Emergency Cabinet Number 6, Kootenai Building Health Physics Center
     "*     Kit 2XP - Emergency Cabinet Number 6, Kootenai Building Health Physics Center Quarterly (and after use or if seal not intact):
     "*     Inventory contents and ensure required quantities are correct.
     "*     Check physical condition of contents and replace, as necessary.

Attachment 5.2-6 Page 2 of 2 PROCEDURE NUMBER REVISION PAGE 13.14.4 34 37 of 71

DATE: 02/22/01 EDITORIAL 13.14.9

1.0 PURPOSE This procedure identifies the activities necessary to maintain a current emergency preparedness program in accordance with commitments made in the Columbia Generating Station Emergency Plan. {R1710}

2.0 REFERENCES

2.1 10CFR50.47(b), Emergency Plans {R-1605} 2.2 10CFR50.54(q), Condition of Licenses {R-1700} 2.3 10CFCR50.54(t), Conditions of Licenses, (audits) (R-1710, R-1712} 2.4 10CFR50 Appendix E, IV and V {R-5728, R-5730, R-5896, R-5928 R-5930} 2.5 NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants {R-2878, R-4114} 2.6 FSAR, Chapter 13.3, WNP-2 Emergency Plan 2.7 OQAPD, Appendix III {R-1368} 2.8 SWP-REC-01, Records Management 2.9 PPM 1.3.43, Licensing Basis Impact Determinations 2.10 SWP-LIC-03, Licensing Document Change Process 2.11 PPM 13.14.4, Emergency Equipment 3.0 DISCUSSION The Emergency Preparedness (EP) Program for Columbia Generating Station has many facets which require ongoing review and assessment to ensure they are being maintained. Many of these are attended to by groups outside of the Emergency Preparedness Department. For example, field survey instruments are checked and calibrated by the Radiation Protection Department, field team vehicles are maintained by the Facilities Group, pagers and sirens are maintained by the Telecommunications Group, Emergency Operations Facility (EOF), Richland Office Complex (ROC) HVAC and, emergency diesel generators by the Facilities Services Group, etc. If organizations that assist in the process of maintaining the EP Program are not diligent in performing their portion of the effort, the Program could be adversely affected. For this reason, the Emergency Preparedness Department will maintain an oversight role to ensure that all program maintenance requirements are being performed. PROCEDURE NUMBER REVISION PAGE 13.14.9 18 2 of 10

4.0 PROCEDURE 4.1 Corporate Emergency Preparedness, Safety and Health Officer 4.1.1 Coordinate, as appropriate, with Energy Northwest managers to implement the requirements of Attachment 5.1, Topics Requiring Periodic Review Or Action.

4. L2 Maintain, prepare, and archive records generated as a result of Emergency Preparedness program implementation in accordance with the Emergency Preparedness Records Management Plan and SWP-REC-01.

4.1.3 Notify the Vice President, Operations Support/PIO of any condition which would preclude or interfere with the ability of Energy Northwest to implement the requirements of the WNP-2 Emergency Plan. 4.2 Applicable Energy Northwest Managers 4.2.1 Coordinate, as appropriate, with the Corporate Emergency Preparedness, Safety and Health Officer to implement the requirements of Attachment 5.1, Topics Requiring Periodic Review Or Action. 4.2.2 Notify the Corporate Emergency Preparedness, Safety and Health Officer of any condition which would preclude or interfere with the ability of Energy Northwest to respond to emergency conditions. 5.0 ATTACHMENTS 5.1 Topics Requiring Periodic Review Or Action PROCEDURE NUMBER REVISION PAGE 13.14.9 18 3 ofl10

TOPICS REOUIRING PERIODIC REVIEW OR ACTION TOPIC RESPONSIBILITY FREQUENCY SCOPE

1. WNP-2 Emergency Corporate Emergency Annually A. Utilize guidance from Plan Review (PTL Preparedness, Safety and SWP-LIC-03, to coordinate R156728) Health Officer {R-1605} review, revision, approval, and issuance of the plan to incorporate changes resulting from new regulations, critiques of drills/exercises, audit findings, and comments from personnel or agencies inside and outside Energy Northwest.

B. Ensure that the Washington State Emergency Management, the Benton and Franklin County Departments of Emergency Management, and the Department of Energy-Richland Operations are contacted early in the review/revision process and that their comments are solicited and considered for input into the process. Document this portion of the review. C. Ensure a Licensing Basis Impact review is completed in accordance with PPM 1.3.43. D. Ensure the supporting documentation is submitted for POC review consistent with the proposed change. E. Ensure the Emergency Plan is sent to the NRC per 10CFR50.4(b)(5) within 30 days of making the changes. {R-1700, R-5930} Attachment 5.1}}