M080723, M080723A-Affirmation Session: I. SECY-08-0097 Progress Energy Carolinas Inc. (Shearon Harris Units 2 & 3) Motion by North Carolina Waste Awareness & Reduction Network (Nc Warn) to Immediately Suspend the Hearing Notice & Req for Expedited C

From kanterella
Jump to navigation Jump to search
M080723A-Affirmation Session: I. SECY-08-0097 Progress Energy Carolinas Inc. (Shearon Harris Units 2 & 3) Motion by North Carolina Waste Awareness & Reduction Network (Nc Warn) to Immediately Suspend the Hearing Notice & Req for Expedited C
ML082060052
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/23/2008
From:
NRC/OCM
To:
References
M080723A, SECY-08-0097
Download: ML082060052 (4)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

AFFIRMATION SESSION

PUBLIC MEETING

Nuclear Regulatory Commission Commission Hearing Room

11555 Rockv ille Pike Rockville, Maryland July 23, 2008 The Commission met in open session, pursuant to notice, at 1:25 p.m.,

Dale E. Klein, Chairman, presiding.

COMMISSIONERS PRESENT:

DALE E. KLEIN, Chairman of the Commission GREGORY B. JACZKO, Member of the Commission

PETER B. LYONS, Member of the Commission

KRISTINE L. SVINICKI, Member of the Commission

STAFF AND PRESENTERS SEATED AT THE COMMISSION TABLE:

KAREN CYR, General Counsel ANDREW BATES, Acting Secretary of the Commission

2

DISCLAIMER

This is an unofficial transcript of a meeting of the United States Nuclear Regulatory Commission on July 23, 2008 in the Commission

=s office at One White Flint North, Rockville, Maryland. The meeting was open to public attendance and observation. This transcript has not been reviewed, corrected or edited, and it may contain inaccuracies. The transcript is intended solely for general information purposes. As provided by 10 CFR 9.103, it is not part of the formal or informal record of decision of the matters discussed.

Expressions of opinion in this transcript do not necessarily reflect final determination or beliefs.

No pleading or other paper may be filed with the Commission in any proceeding as the result of, or addressed to, any statement or argument contained herein, except as the Commission may authorize.

3 [1:25 p.m.] P R O C E E D I N G S CHAIRMAN KLEIN: Would you like to do the Affirmation? MR. BATES: Mr. Chairman, Commissioners, we have one item for Affirmation today. It's SECY-08-0097 In the Matter of Progress Energy Carolinas Inc., the Shearon Harris Nuclear Power Plant, Units 2 and 3. The Commission is being asked to respond to a request by the North Carolina Waste Awareness and Reduction Network to suspend the period to request a hearing in the Shearon Harris COL proceeding until after the completion of the certified design rulemaking for the AP1000, Revision 16. The Commission has voted to approve a Memorandum and Order, which we circulated to you, which denies the motion. May I have your votes please? CHAIRMAN KLEIN: Aye.

COMMISSIONER JACZKO: Aye. COMMISSIONER LYONS: Aye. COMMISSIONER SVINICKI: Aye. MR. BATES: That's the only matter I have today for you.

CHAIRMAN KLEIN: Any comments? Meeting's adjourned.

4 CERTIFICATE

This is to certify that the attached description of a meeting of the U.S. Nuclear Regulatory Commission entitled:

TITLE OF MEETING: Affirmation Session (PUBLIC MEETING)

PLACE OF MEETING: Rockville, Maryland DATE OF MEETING: July 23, 2008

was held as herein appears, is a true and accurate record of the meeting, and that this is the original transcript thereof taken stenographically by me, thereafter reduced to typewriting by me or under the direction of the court reporting company.

Transcriber: DARLENE K. WRIGHT Reporter: (TAPE RECORDING)