M070122, SRM-M070122A-Affirmation: I. SECY-06-0240 Entergy Nuclear Vermont Yankee, LLC & Entergy Nuclear Operations, Inc. LBP-06-20: Entergy Nuclear Generation Co. (Pilgrim) LBP-06-23; Ii. SECY-07-0003 Exelon Generation Co., LLC (Early Site Permit C

From kanterella
Jump to navigation Jump to search
SRM-M070122A-Affirmation: I. SECY-06-0240 Entergy Nuclear Vermont Yankee, LLC & Entergy Nuclear Operations, Inc. LBP-06-20: Entergy Nuclear Generation Co. (Pilgrim) LBP-06-23; Ii. SECY-07-0003 Exelon Generation Co., LLC (Early Site Permit C
ML070230087
Person / Time
Site: Pilgrim, Vermont Yankee, Victoria  Entergy icon.png
Issue date: 01/22/2007
From: Vietti-Cook A L
NRC/SECY
To: Cordes J F
NRC/OCAA
References
LBP-06-20, LBP-06-23, M070122A, SECY-06-0240, SECY-07-0003 SRM-M070122A
Download: ML070230087 (2)


Text

1Section 201 of the Energy Reorganization Act, 42 U.S.C. Section 5841, provides thataction of the Commission shall be determined by a "majority vote of the members present." Chairman Klein and Commissioners Merrifield, Jaczko and Lyons were present in the Conference Room. Commissioner McGaffigan participated in the meeting via speakerphone. IN RESPONSE, PLEASEREFER TO: M070122AJanuary 22, 2007MEMORANDUM FOR:John F. Cordes, DirectorOffice of Commission Appellate AdjudicationFROM:Annette L. Vietti-Cook, Secretary /RA/

SUBJECT:

STAFF REQUIREMENTS - AFFIRMATION SESSION, 1:25 P.M.,MONDAY, JANUARY 22, 2007, COMMISSIONERS' CONFERENCE ROOM, ONE WHITE FLINT NORTH, ROCKVILLE, MARYLAND (OPEN TO PUBLIC ATTENDANCE) 1 I.SECY-06-0240 - Entergy Nuclear Vermont Yankee, LLC, & Entergy Nuclear Operations,Inc. (Vermont Yankee Nuclear Power Station), LBP-06-20 (Sept. 22, 2006): EntergyNuclear Generation Company & Entergy Nuclear Operations, Inc (Pilgrim NuclearPower Station), LBP-06-23 (Oct. 16, 2006)

The Commission approved a Memorandum and Order responding to two appeals byMassachusetts Attorney General concerning fire hazards in high-density spent fuel pools.

These appeals were filed with respect to the separate decisions of two Atomic Safety and Licensing Boards (LBP-06-20 and LBP-06-23) in two license renewal proceedings. The Memorandum and Order affirms the Licensing Boards' decisions in LBP-06-20 and LBP-06-23.(Subsequently, on January 22, 2007, the Secretary signed the Memorandum and Order.)

II.SECY-07-0003 - Exelon Generation Company, LLC (Early Site Permit for Clinton ESP)The Commission approved an Order requesting comments on the Atomic Safety and LicensingBoard's Decision authorizing issuance of the early site permit for the Clinton site. (LBP-06-28)

The Order sets a schedule to provide briefs for the Commission's consideration. (Subsequently, on January 22, 2007, the Secretary signed the Memorandum and Order.)

cc:Chairman Klein Commissioner McGaffigan Commissioner Merrifield Commissioner Jaczko Commissioner Lyons

EDO OGC CFO OCAA OCA OIG OPA Office Directors, Regions, ACRS, ACNW, ASLBP (via E-Mail)

PDR