LR-N19-0048, 2018 Annual Report of SRV Challenges
| ML19102A069 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 04/12/2019 |
| From: | Casulli E Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N19-0048 | |
| Download: ML19102A069 (2) | |
Text
APR 1 2 2019 LR-N19-0048 PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Hope Creek Generating Station Renewed Facility Operating License No. NPF-57 NRC Docket No. 50-354 2018 Annual Report of SRV Challenges 0 PSEG NuclearLLC TS 6.9.1.5.b This report is being submitted in accordance with Hope Creek Technical Specification 6.9.1.5.b, which requires the documentation of all challenges to main steam line safety/ relief valves (SRVs) be provided on an annual basis.
For 2018, the SRVs were not challenged by any over pressurization events or transients that would have required the valves to respond automatically.
There are no regulatory commitments contained in this letter.
Should you have any questions or require any additional information regarding this submittal, please contact Ms. Kirsten Stokes, at (856) 339-2834.
Sincerely, Edward T. Casulli Plant Manager, Hope Creek Generating Station
Page 2 LR-N19-0048 cc:
Administrator, Region I, NRC NRC Project Manager, Hope Creek NRC Senior Resident Inspector, Hope Creek Manager, NJBNE Corporate Commitment Tracking Coordinator Hope Creek Commitment Tracking Coordinator TS 6.9.1.5.b