PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, New Jersey 08038-0236 JUL 2 3 2014 LR-N14-0110 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Hope Creek Generating Station Renewed Facility Operating License No. NPF-57 NRC Docket No. 50-354 2013 Summary of Revised Regulatory Commitments t>SlCi Nuclear LLC NEI 99-04 In accordance with the Nuclear Energy Institute (NEI) process (NEI 99-04) for managing Nuclear Regulatory Commission (NRC) commitments and associated NRC notifications, PSEG Nuclear LLC (PSEG) submits this correspondence to discuss commitments that were changed and not reported by other means.
There were no revised commitments requiring NRC notification in 2013.
There are no regulatory commitments contained in this letter.
Should you have any questions or require additional information, please contact Philip J. Duca at (856) 339-1640.
Sincerely
.0
Paul J. Davison Site Vice President Hope Creek Generating Station
Document Control Desk LR-N14-0110 Page 2 of 2 cc:
Mr. W. Dean, Administrator-Region I U. S. Nuclear Regulatory Commission 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 Mr. J. Lamb, Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 8B1A Washington, DC 20555-0001 USNRC Senior Resident Inspector - Hope Creek (X24)
USNRC Senior Resident Inspector - Salem (X24)
Mr. P. Mulligan, Manager New Jersey Department of Environmental Protection P.O. Box 420 MC 33-01 33 Arctic Parkway Trenton, NJ 08625 Hope Creek Commitment Coordinator (H02)
Corporate Commitment Coordinator (N21)