LR-N08-0212, Response to Request for Additional Information Concerning Control System Vulnerability
| ML082690604 | |
| Person / Time | |
|---|---|
| Site: | Salem, Hope Creek |
| Issue date: | 09/16/2008 |
| From: | Neely C Public Service Enterprise Group |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| LR-N08-0212 | |
| Download: ML082690604 (3) | |
Text
PSEG Nuclear LLC P.O. Box 236,, Hancocks Bridge, NJ 08038-0236 0 PSEG Nuclear L.L. C.
LR-N08-0212 September 16, 2008 United States Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 SALEM GENERATING STATION - UNIT 1 and UNIT 2 FACILITY OPERATING LICENSE NOS. DPR 70 and DPR-75 NRC DOCKET NOS. 50-272 and 50-311 HOPE CREEK GENERATING STATION FACILITY OPERATING LICENSE NO. NPF-57 NRC DOCKET NO. 50-354
Subject:
RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION CONCERNING CONTROL SYSTEM VULNERABILITY
References:
(1) Letter from Richard B. Ennis to W. Levis, "Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2 -
Request For Additional Information regarding Control System Vulnerability", dated July 18, 2008 (2) Letter from W. Levis to NRC: "Control System Vulnerability 60-Day Response", dated August 20, 2007 (Correspondence No. LR-N07-0201)
(3) Letter from J. E Dyer to Facility Addressees, "Control System Vulnerability", dated June 22, 2007 In Reference 2, PSEG Nuclear LLC (PSEG) submitted a 60 - day response to the Reference 3 request for information concerning Control System Vulnerability. The NRC has provided PSEG with a Request for Additional Information (RAI) regarding the information provided in Reference 2 via Reference 1.
Attachments 1 and 2 to this submittal provide the PSEG 60-day response to the RAI in Reference 1 for Salem and Hope Creek generating Stations. The attachments do contain personal privacy, proprietary, or safeguards information, for which protection is requested under the provisions for 10 CFR § 2.390.
Document Control Desk LR-N08-0212 2
This letter contains the following new commitments as listed in Attachment 3:
- 1. The information required to fill in the RAI Enclosure 2 Table for Salem will be transferred into the Table, as requested by RAI 3B, and available for NRC inspection by 12/18/2008. (CM.SC.2008-71)
- 2. The information required to fill in the RAI Enclosure 2 Table for Hope Creek will be transferred into the Table, as requested by RAI 3B, and available for NRC inspection by 12/18/2008. (CM.HC.2008-72)
If you have any questions or require additional information, please do not hesitate to contact Mr. Jeffrie Keenan at (856) 339-5429.
Sincerely,
'Christine T. Neely Director, Regulatory Affairs Attachments (3) 1 - Salem Units 1, 2 and 3 Day Response to RAI 2 - Hope Creek 60-Day Response to RAI 3 - List Of Commitments
Document Control Desk 3
LR-N08-0212 C
Mr. S. Collins, Administrator - Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. R. Ennis, Project Manager - Hope Creek/Salem Unit 1 and Unit 2 U. S. Nuclear Regulatory Commission Mail Stop 08B1 Washington, DC 20555-0001 USNRC Resident Inspector Office - Salem and Hope Creek (X24)
Mr. Patrick Mulligan, Manager IV Bureau of Nuclear Engineering PO Box 415 Trenton, New Jersey 08625-0415 U.S. Nuclear Regulatory Commission ATTN: Thomas Alexion, Sr. Project Manager NRR/DPR/PGCB, MS O-12H2 Washington, DC.20555-0001 U.S. Nuclear Regulatory Commission ATTN: Thomas Koshy, Team Leader RES/DFERR/ERA/IE, MS T-10D20 Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission ATTN: Angela Baxter NRR/ADRO/DORL/LP, MS - 8 BlA Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission ATTN: Peter Tam NRR/ADRO/DORL/LP, MS-8 H4A Washington,.DC 20555-0001 U.S. Nuclear Regulatory Commission ATTN: Nitin Patel NRR/ADES/DE/EEEB, MS O-9E3 Washington, DC 20555-0001