Letter Sequence Request |
---|
|
|
MONTHYEARLIC-09-0004, License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements2009-01-30030 January 2009 License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements Project stage: Request ML0905407952009-02-23023 February 2009 Acceptance Review Email, License Amendment Request, Modify Technical Specifications to Add Operability and Testing Requirements for Steam .Generator Blowdown Isolation on a Reactor Trip Project stage: Acceptance Review ML0916805892009-06-17017 June 2009 Request for Additional Information, License Amendment Request, Modify Technical Specifications to Add Operability and Testing Requirements for Steam Generator Blowdown Isolation on a Reactor Trip Project stage: RAI ML0916805862009-06-17017 June 2009 Email, Request for Additional Information, License Amendment Request, Modify Technical Specifications to Add Operability and Testing Requirements for Steam Generator Blowdown Isolation on a Reactor Trip Project stage: RAI LIC-09-0043, Response to Request for Additional Information Concerning License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements2009-06-30030 June 2009 Response to Request for Additional Information Concerning License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements Project stage: Response to RAI LIC-09-0068, Response to Revision to License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements.2009-08-28028 August 2009 Response to Revision to License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements. Project stage: Request ML0925405912009-10-0909 October 2009 License Amendment, Issuance of Amendment No. 263 Modify Technical Specifications to Add Operability and Testing Requirements for Steam Generator Blowdown Isolation on a Reactor Trip Project stage: Approval ML0935611192010-01-22022 January 2010 Correction to Amendment No. 263 Request to Add Steam Generator Blowdown Isolation Requirements to Technical Specifications Project stage: Other 2009-06-17
[Table View] |
|
---|
Category:Letter type:LIC
MONTHYEARLIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update LIC-18-0030, Request for Partial Site Release Phase 22018-11-12012 November 2018 Request for Partial Site Release Phase 2 LIC-18-0028, Letter of Intent to Submit Request for Additional Partial Site Release2018-10-18018 October 2018 Letter of Intent to Submit Request for Additional Partial Site Release LIC-18-0027, Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2018-10-0303 October 2018 Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update LIC-18-0003, License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool2018-09-28028 September 2018 License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool LIC-18-0025, Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 20192018-07-19019 July 2018 Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 2019 LIC-18-0023, Fort Calhoun Station, Unit 1 Request for Partial Site Release2018-06-29029 June 2018 Fort Calhoun Station, Unit 1 Request for Partial Site Release LIC-18-0021, Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan)2018-06-0606 June 2018 Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan) LIC-18-0017, Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy2018-04-26026 April 2018 Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy 2023-08-24
[Table view] |
Text
IIIUH OmahaPublic Power District Fort Calhoun Station P.O. Box 550, Fort Calhoun, NE 68023 August 28, 2009 LIC-09-0068 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
References:
- 1. Docket No. 50-285
- 2. Letter from OPPD (R. P. Clemens) to NRC (Document Control Desk), "Fort Calhoun Station (FCS) Unit No. 1 License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements," dated January 30, 2009 (LIC-09-0004) (ML090340536)
- 3. Email from NRC (L. E. Wilkins) to OPPD (B. R. Hansher), "RAIs (Request for Additional Information) for LAR 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements," dated April 9, 2009 (ML091680589)
- 4. Letter from OPPD (R. P. Clemens) to NRC (Document Control Desk),
"Response to Request for Additional Information Concerning License Amendment Request (LAR) 09-01, Steam Generator Blowdown Isolation Operability and Testing Requirements," dated June 30, 2009 (LIC-09-0043)
(ML091830041)
SUBJECT:
Revision to License Amendment Request (LAR) 09-01, "Steam Generator Blowdown Isolation Operability and Testing Requirements" In Reference 2, the Omaha Public Power District (OPPD) requested a change to Fort Calhoun Station (FCS), Unit No. 1, Renewed Operating License No. DPR-40, to add operability and surveillance testing requirements to the FCS Technical Specifications (TS) for the steam generator (SG) blowdown isolation on a reactor trip. The NRC staff reviewed the proposed change and in Reference 3, transmitted a request for additional information (RAI).
OPPD responded in Reference 4 by providing a discussion as to why TS 2.15(1) through 2.15(4) do not apply and explained that the proposed footnotes provide specific guidance for component inoperability. As stated on page 6 of Reference 4, the operability of the initiationportion of the blowdown isolation function is addressed by TS 2.15, Table 2-2. The proposed revision adds TS for the actuation portion of the blowdown isolation function; TS 2.15(1) through 2.15(4) apply to initiating channels. In a teleconference on August 13, 2009, the NRC expressed a concern about the proposed wording of the footnotes.
Employment with Equal Opportunity 4171
U. S. Nuclear Regulatory Commission LIC-09-0068 Page 2 Specifically, proposed footnote (h) which provides information on the logic subsystem is designated as associated with TS 2.15, Table 2-4, Item 4B, Reactor Trip, which is the automatic portion of the actuation circuit, but was not designated as associated with TS 2.15, Table 2-4, Item 4A, which is the manual portion of the actuation circuit. Additionally, since TS 2.15, Table 2-4, footnotes (i) and (j) do not state that TS 2.15(1) through 2.15(4) do not apply, in some situations it could be concluded that both the TS 2.15 guidance and the footnotes would apply and contain different actions for the same condition. Therefore, for clarification, footnote (h) is revised to apply to the manual actuation train in addition to the automatic actuation train, and footnotes (i) and (j) are revised to specifically state that TS 2.15(1) through 2.15(4) do not apply.
OPPD has reviewed and approved the changes requested by the NRC and they are incorporated in the attached markup and clean pages. The attached pages supersede the corresponding pages provided with Reference 2. As the changes are considered a minor clarification, the conclusion of the evaluation provided by Reference 2 that the changes present no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), remains valid.
No regulatory commitments are made in this letter. If you should have any questions regarding this submittal or require additional information, please contact Mr. Bill R. Hansher at (402) 533-6894.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 28, 2009.
J rey A. Reinhart e Vice President JAR/BRH/dll Attachments: 1. Technical Specification Page Markups
- 2. Retyped ("Clean") Technical Specifications c: E. E. Collins, NRC Regional Administrator, Region IV A. B. Wang, NRC Project Manager J. C. Kirkland, NRC Senior Resident Inspector Director of Consumer Health Services, Department of Regulation and Licensure, Nebraska Health and Human Services, State of Nebraska
LIC-09-0068 Page 1 Technical Specification Page Markups
TECHNICAL SPECIFICATIONS TABLE 2-4 Instrument Operating Conditions for Isolation Functions Test, Minimum Minimum Permissible Maintenance Functional Operable Degree of Bypass and Inoperable No.. Unit Channels Redundancy Condition Bypass 1 Containment Isolation A Manual 1 None None N/A B Containment High Pressure Logic Subsystem A 2 (a)(e)(g) 1 During Leak (f)
Logic Subsystem B 2 1 Test C Pressurizer Low/Low Pressure Logic Subsystem A 2 (a)(e)(g) 1 Reactor Coolant (f)
Logic Subsystem B 2 (a)(e)(g) 1 Pressure Less Than 1700 psia(b) 2 Steam Generator Isolation A Manual 1 None None N/A B Steam Generator Isolation 1 None None N/A (i) Steam Generator Low Pressure Logic Subsystem A 2/Steam 1/Steam Steam Generator (f)
Gen(a)(e)(g) Gen Pressure Less Than 600 psia(c)
Logic Subsystem B 2/Steam 1/Steam Gen(a)(e)(g) Gen (ii) Containment High Pressure Logic Subsystem A 2 (a)(e)(g) 1 During Leak (f)
Logic Subsystem B 2 (a)(e)(g) 1 Test 3 Ventilation Isolation A Manual 1 None None N/A B Containment High Radiation Logic Subsystem A 1(d)(g) None If Containment (f)
Logic Subsystem B 1(d)(9) None Relief and Purge Valves are Closed
,14 ,, Steam-GeneratortBlowdown Isolation Manual - 111") None : Operating Modes' N/A
- 3. 4. &
B Reactor Trilii Trains A and, B None Operating Modes (j) 3, 4, & 5 OR '.
at least one v-i for each steamf-Aan-r-irý R 2.15 - Page 12 Amendment No. 88,93,108,152,153,17-3,184,194,249,
TECHNICAL SPECIFICATIONS TABLE 2-4 (Continued) a Circuits on ESF Logic Subsystems A and B each have 4 channels.
b Auto removal of bypass prior to exceeding 1700 psia.
c Auto removal of bypass prior to exceeding 600 psia.
d A and B trains are both actuated by either the Containment or Auxiliary Building Exhaust Stack initiating channels. The number of installed channels for Containment Radiation High Signal is two for purposes of Specification 2.15(1).
e If minimum operable channel conditions are reached, one inoperable channel must be placed in the tripped condition within eight hours from the time of discovery of loss of operability. Specification 2.15(2) is
- applicable.
f If one channel becomes inoperable, that channel must be placed in the tripped or bypassed condition within eight hours from the time of discovery of loss of operability. Specification 2.15(1) is applicable.
g Specification 2.15(3) is applicable. If ESF Logic Subsystems A and B are inoperable, enter Specification 2.0.1.
trins(loic sucstesswhich ar rqire to beoerabet rvd aulo uoai Gbodw isoliation valve h for,ur.__Spe eac
.if stea geerto
++i~p*2.15() + is,*
.2closed+
(3) andOR(4.pq be
++ in MOD o 2 ihi be S ous .. ndi sntap MD i icaleh nx O6trains beomeinpeabe power opeir aytion mycntiu prvie atlatoeS both lo slto 2.15 - Page 13 Amendment No. 88,108,152,173,194, 249
LIC-09-0068 Page 1 Retyped ("Clean") Technical Specifications
TECHNICAL SPECIFICATIONS TABLE 2-4 Instrument Operating Conditions for Isolation Functions Test, Minimum Minimum Permissible Maintenance Functional Operable Degree of Bypass and Inoperable No. Unit Channels Redundancy Condition Bypass 1 Containment Isolation A Manual 1 None None N/A B Containment High Pressure Logic Subsystem A 2 (a)(e)(g) 1 During Leak (f)
Logic Subsystem B 2(a)(e)(g) 1 Test C Pressurizer Low/Low Pressure Logic Subsystem A 2 (a)(e)(g) 1 Reactor Coolant (f)
Logic Subsystem B 2 (a)(e)(g) 1 Pressure Less Than 1700 psia(b) 2 Steam Generator Isolation A Manual 1 None None N/A B Steam Generator Isolation I None None N/A (i) Steam Generator Low Pressure Logic Subsystem A 2/Steam 1/Steam Steam Generator (f)
Gen(a)(e)(§) Gen Pressure Less Than 600 psia(c)
Logic Subsystem B 2/Steam 1/Steam Gen(a)(e)(g) Gen (ii) Containment High Pressure Logic Subsystem A 2 (a)(e)(g) 1 During Leak (f)
Logic Subsystem B 2 (a)(e)(g) 1 Test 3 Ventilation Isolation A Manual 1 None None N/A B Containment High Radiation Logic Subsystem A 1(d)(g) None If Containment (f)
Logic Subsystem B 1 (d)(g) None Relief and Purge Valves are Closed 4 Steam Generator Blowdown Isolation A Manual 1 (h) None Operating Modes N/A 3,4, &5 B Reactor Trip Trains A and B None Operating Modes (J) 3,4, & 5 OR if at least one valve for each steam generator is closed 2.15- Page 12 Amendment No. 88,93,108,152,153,173,184,194,249, 2,5
TECHNICAL SPECIFICATIONS TABLE 2-4 (Continued) a Circuits on ESF Logic Subsystems A and B each have 4 channels.
b Auto removal of bypass prior to exceeding 1700 psia.
c Auto removal of bypass prior to exceeding 600 psia.
d A and B trains are both actuated by either the Containment or Auxiliary Building Exhaust Stack initiating channels. The number of installed channels for Containment Radiation High Signal is two for purposes of Specification 2.15(1).
e If minimum operable channel conditions are reached, one inoperable channel must be placed in the tripped condition within eight hours from the time of discovery of loss of operability. Specification 2.15(2) is applicable.
f If one channel becomes inoperable, that channel must be placed in the tripped or bypassed condition within eight hours from the time of discovery of loss of operability. Specification 2.15(1) is applicable.
g Specification 2.15(3) is applicable. If ESF Logic Subsystems A and B are inoperable, enter Specification 2.0.1.
h "Minimum Operable Channels" for steam generator blowdown isolation refers to the minimum number of trains (logic subsystems) which are required to be operable to provide manual or automatic SG blowdown isolation.
If both trains become inoperable, power operation may continue provided at least one SG blowdown isolation valve for each steam generator is closed OR be in MODE 2 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 3 in the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
Specifications 2.15(1), (2), (3) and (4) are not applicable; TS LCO 2.0.1 is not applicable.
If one train becomes inoperable, that train may be placed in the bypassed condition. Ifthe train is not returned to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from time of discovery of loss of operability, operation may continue as long as one SG blowdown isolation valve to each steam generator is closed. If the train is not returned to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> from time of discovery, with blowdown not isolated to both SGs, be in MODE 2 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and in MODE 3 in the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. Specifications 2.15(1), (2), (3) and (4) are not applicable; TS LCO 2.0.1 is not applicable.
2.15 - Page 13 Amendment No. 88,n108, 152,173,194, 2 9