MONTHYEARLIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update LIC-18-0030, Request for Partial Site Release Phase 22018-11-12012 November 2018 Request for Partial Site Release Phase 2 LIC-18-0028, Letter of Intent to Submit Request for Additional Partial Site Release2018-10-18018 October 2018 Letter of Intent to Submit Request for Additional Partial Site Release LIC-18-0027, Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update2018-10-0303 October 2018 Submittal of Foreign Ownership, Control or Influence Five-Year Renewal Filing and NRC Facility Clearance Update LIC-18-0003, License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool2018-09-28028 September 2018 License Amendment Request (LAR) 18-01; Revised Fort Calhoun Station Permanently Defueled Technical Specifications to Align to Those Requirements for Permanent Removal of Spent Fuel from Spent Fuel Pool LIC-18-0025, Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 20192018-07-19019 July 2018 Guarantee of Payment of Deferred Premiums for the Period of July 1, 2018 to June 30, 2019 LIC-18-0023, Fort Calhoun Station, Unit 1 Request for Partial Site Release2018-06-29029 June 2018 Fort Calhoun Station, Unit 1 Request for Partial Site Release LIC-18-0021, Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan)2018-06-0606 June 2018 Transmittal of Revision 3 to the Physical Security Plan (PSP) and Revision 4 to the FCS Protective Strategy (Safeguards Contingency Plan) LIC-18-0017, Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy2018-04-26026 April 2018 Submittal of Revision 2 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) and Revision 3 of the FCS Protective Strategy 2023-08-24
[Table view] |
Text
Opp" Omaha Public PowerDistrict 444 South 16th Street Mall Omaha NE 68102-2247 May 9, 2002 LIC-02-0060 U. S. Nuclear Regulatory Commission ATTN.: Document Control Desk Washington, DC 20555-0001
Reference:
- 1) Docket No. 50-285
- 2) Letter from OPPD (R. T. Ridenoure) to NRC (Document Control Desk) dated March 27, 2002, Fort Calhoun Station Unit No. 1 License Amendment Request, "Revision of the High Power Trip Setpoint" (LIC-02-003 1)
SUBJECT:
Fort Calhoun Station Unit No. 1 License Amendment Request, "Revision of the High Power Trip Setpoint" On March 27, 2002, pursuant to 10 CFR 50.90, Omaha Public Power District (OPPD) submitted a License Amendment Request for Fort Calhoun Station Unit 1 (FCS) (Reference 2). This proposed amendment changes the Reactor Protective System High Power Level trip to 109.0%
from the current 107.0% value in Technical Specification (TS) 1.3.1. OPPD now requests that this License Amendment Request be approved on an exigent basis.
Attachment 1 of Reference 2 provides the No Significant Hazards Evaluation and the technical bases for this requested change to the TS. Attachments 2 and 3 of Reference 2 contain a marked up and clean version reflecting the requested TS and Basis changes. Attachment 1 of this submittal contains an explanation of the exigency and why OPPD could not have avoided the present condition, pursuant to 10 CFR 50.9 1(a)(6)(vi).
In order to help alleviate difficulties experienced with hot leg flow streaming anomalies, OPPD requests approval of the proposed amendment on an exigent basis by May 31, 2002, to be available for >95% power operation following the Spring 2002 Refueling Outage. The Spring 2002 Refueling Outage is planned to end and power operation begin on May 31, 2002. Once approved, the amendment shall be implemented by June 5, 2002.
I declare under penalty of perjury that the foregoing is true and correct. (Executed on May 9, 2002)
Employment with Equal Opportunity 4171
U. S. Nuclear Regulatory Commission LIC-02-0060 Page 2 If you have any questions or require additional information, please contact Dr. R. L. Jaworski of my staff at 402-533-6833.
Sincerely, 1./ Explanation of the Exigency and Why the Situation Could Not Have Been Avoided c: E. W. Merschoff, NRC Regional Administrator, Region IV A. B. Wang, NRC Project Manager W. C. Walker, NRC Senior Resident Inspector Division Administrator, Public Health Assurance, State of Nebraska Winston & Strawn LIC-02-0060 Page 1 Attachment 1 Explanation of the Exigency and Why the Situation Could Not Have Been Avoided On March 27, 2002, Omaha Public Power District (OPPD) requested an amendment to change the high power trip setpoint (Reference 2). OPPD informed the NRC that the revised setpoint for the high power trip needed to be approved prior to exceeding 95%
rated power to avoid a potential plant trip due to a hot leg flow streaming event.- OPPD asked the NRC that the amendment be approved by May 31, 2002 to provide OPPD sufficient time to implement the change. Fort Calhoun Station Unit 1 (FCS) began its Spring Refueling Outage on May 3, 2002. The Spring Refueling Outage is scheduled to be completed and power operation scheduled to resume on May 31, 2002. FCS is currently scheduled to exceed 95% power on June 5, 2002. On May 2, 2002, the NRC notified OPPD that the NRC had missed the April 16, 2002 deadline for publication of the no significant hazards consideration notice in the April 30, 2002 Federal Register.
Publication in the Federal Register was needed by April 30, 2002 to allow the NRC to issue the amendment by May 31, 2002. The NRC informed OPPD that the Federal Register Notice went for publication on April 25, 2002 and would be issued on May 14, 2002. Therefore, the comment period would not end until June 13, 2002 and the amendment could not be issued until June 14, 2002. After reviewing the options available for issuing the amendment by May 31, 2002, OPPD has concluded that the amendment should be processed on an exigent basis.
The exigency is needed to enable the plant to achieve 100% power because the amendment cannot be issued by June 5, 2002 as a result of the public comment period.
Therefore, OPPD requests approval of this License Amendment Request on an exigent basis.