L-88-466, Responds to NRC Ltr Re Violations Noted in Insp Repts 50-250/88-25 & 50-251/88-25.Corrective Actions:All Three Fuel Pool Cooling Pump Maint Procedures Will Be Permanently Revised to Provide Adequate Instructions & Drawings

From kanterella
(Redirected from L-88-466)
Jump to navigation Jump to search
Responds to NRC Ltr Re Violations Noted in Insp Repts 50-250/88-25 & 50-251/88-25.Corrective Actions:All Three Fuel Pool Cooling Pump Maint Procedures Will Be Permanently Revised to Provide Adequate Instructions & Drawings
ML17345A473
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/26/1988
From: Conway W
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
L-88-466, NUDOCS 8811010437
Download: ML17345A473 (7)


Text

C CEXZRATED DISTRlBUTION DEMO'NSTRATIOR SY~g]p[

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RZDS)

ACCESSION NBR:8811010437 DOC.DATE: 88/10/26 NOTARIZED:

NO Doci(ET FACIL:50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 05000250 50-251 Turkey Point Plant, Unit 4, Florida Power and Light C

05000251 UTH.NAME AUTHOR AFFILIATION ONWAYgW.F.

Florida Power a Light Co.

RECIP.NAME RECIPIENT AFFILIATION, Document Control Branch (Document Control Desk)

SUBJECT:

Responds to NRC ltr re violations noted in Insp Repts 50-250/88-25

& 50-251/88-25.Corrective actions:

DISTRIBUTION CODE:

ZEOlD COPIES RECEIVED:LTR O'NCL 3 SIZE:

TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES:

RECIPIENT ID CODE/NAME PD2-2 PD INTERNAL: AEOD NRR MORISSEAUgD NRR/DLPQ/QAB 10 NRR/DREP/EPB 10 NRR/DRIS DIR 9A NUDOCS-ABSTRACT OGC/HDS2 RES/DSR DEPY ERNAL: LPDR NSIC COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 1

1 RECIPIENT ID CODE/NAME EDISON,G DEDRO NRR/DLPQ/PEB ll NRR/DOEA DIR 11 NRR/DREP/RPB 10 NRR/PMAS/ILRB12 0

BERMAN,J G

02 RGN2 FILE 01 NRC PDR RESL MARTIN,D COPIES LTTR ENCL 1

1 1

1 1

1 1

1 2

2 1

1 1

1 1

1 1

1 1

1 1

1 S

D S

0 TOTAL NUMBER OF COPIES REQUIRED:

LTTR 23'NCL 23

P. O. BOX 14000, JUNO BkACH, PI 33408.0420 OCTOBER 2 6 1988 L-88-466 U. S. Nuclear Regulatory Commission Attn:

Document Control Desk Washington, D.

C.

20555 Gentlemen:

Re:

Turkey Point Units 3 and 4

Docket Nos.

50-250 and 50-251 Reply to Notice of Violation Ins ection Re ort 88-25 Florida Power

& Light Company has reviewed the subject inspection report and a response is attached.

Very truly yours,

~v~+

Senior Vice President Nuclear WFC/SDF/gp Attachment cc:

Malcolm L. Ernst, Acting Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Plant 881iOi0437 88i026 PDR ADOCK 05000250 8

PNU

~p>r'JI an FPL Group company

ATTACHMENT RE:

TURKEY POINT UNITS 3 AND 4 DOCKET NOS ~ 50-250 AND 50-251 IE INSPECTION REPORT 250-88-25

& 251-88-25 FINDING 10 CFR 50, Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, Criterion V, as implemented by the approved Florida Power and Light Company Topical Quality Assurance Report (FPLTQAR) 1.76A, Revision 10, (June 24, 1988),

and in Topical Quality Requirement (TQR) 5.0, Revision 7, (June 24, 1988), requires that activities affecting quality assurance shall be prescribed by documented instructions, and shall be accomplished in accordance with these instructions, procedures or drawings.

Contrary to the above, Maintenance Procedure (MP) 3507.2,, entitled "Spent Fuel Pit Pump Disassembly, Repair and Assembly (Ingersoll-Rand)",

revision dated November 4, 1986, did not provide adequate instructions or drawings for the assembly and installation of the 4A SFP cooling pump, as evidenced by the improper mounting of the constant level oiler.

The improper mounting of the oiler resulted in inadequate lubrication of the pump bearings and the subsequent failure of the pump.

RESPONSE

1)

Florida Power and Light accepts the violation.

2)

The reason for the violation was the omission of specific instructions related to the proper mounting of the constant level oiler from Maintenance Procedure (MP) 3507.2.

3)

The following actions have been or will be taken to address the violation:

a.

Procedure 3507.2 was, revised on September 9,

1988 to incorporate specific instructions related to the proper mounting of the constant level oilers by an On-The-Spot-Change to the procedure.

An On-The-Spot-Change was also implemented for the other Spent Fuel Pool Cooling pump which utilizes a constant level oiler.

This was completed on October 21, 1988.

b ~

Maintenance Mechanics have been trained in the identification of oiler types, how to set the required oil level, and how to replenish the oiler supply bottle.

This was completed on September 27, 1988.

0 C ~

Oil filled safety related pumps, accessible during power operations, were inspected to verify the type of oiler installed, the configuration of the oiler to the bearing housing, actual oil level in bearing frame, oil leakage and oil level mark-on the bearing housing.

This inspection was completed on September 3,

1988.

Some discrepant conditions were

identified which do not affect pump operability.

Correction of these discrepancies is ongoing and will be completed by December 14, 1988.

The remaining oil filled safety related pumps will be inspected during the current unit 4 refueling outage and the current unit 3 outage.

d.

Responsibility for replenishment of oilers was specifically assigned to the mechanical maintenance department on September 27, 1988.

This will provide assurance of consistent proper oil level maintenance.

4)

The corrective actions which have been or will be taken to avoid recurrence include:

a.

All three fuel pool cooling pump maintenance procedures will be permanently revised to provide adequate instructions and drawings for oiler installation and maintenance where applicable.

Other safety related pump procedures will be reviewed to assure the. adequacy of the instructions and drawings for oiler installation and maintenance.

Necessary revisions will be completed by December 31, 1988.

-b.

Preventative Maintenance work instructions for pumps with constant level oilers will include data sheets which specifically address oiler maintenance.

This was incorporated on September 7,

1988.

C ~

Initial and continuing training for maintenance mechanics will include a description of this event.

5)

Permanent maintenance procedure revisions will be completed by December 31, 1988.

The deficiencies identified during the inspection of all safety related pumps will be corrected by December 14, 1988.

The training program for maintenance mechanics will incorporate the lessons learned in this event into the 1989 lesson plans.

The remaining oil filled safety related pumps will be inspected during the current unit 4 refueling outage and the current unit 3 maintenance outage.

I I