| Site: | Saint Lucie |
| Issue date: | 12/23/1981 |
| From: | Robert E. Uhrig FLORIDA POWER & LIGHT CO. |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, 50-389-81-007, 50-389-81-7, L-81-538, NUDOCS 8112310198 | |
| Download: ML20039C999 (1) | |
Text
_
P.o. BOX 529100 MI AMI, F L 33152 b
~}
5 3 rLoaio^ eowea a LiGar cour^~v n
December 23,3981 L-81-538 Mr. James P. O'Reilly Regional Administrator, Region II g
e U. S. Nuclear Regulatory Commission g
101 Mariett'a Street, Suite 3100 A) y p'
g Atlanta, Georgia 30303
Dear Mr. O'Reilly:
bc b
g 7%.
Re: RII:JP0
'y
?; -
50-389 Potential 10 CFR 50.55(e) Report 50-389/81-007-Q 'ib 1 s
/
Broken Studs on Relay Mechanical Interlock Arm - Interim Report On November 24, 1981 Florida Power & Light Company notified the NRC's Region II office in Atlanta (Hugh Dance) of a potential 10 CFR 50.55 (e) involving broken studs on relay mechanical interlock arms. The concern involved the fact that with the mechanical arm guide studs broken, the number 42 relay remained locked in its "as is" position.
In this situation neither the 42 open coil nor the 42 close coil could be operated. The relays in question are part of the 480V motor control center line starters to motor operated valves.
At the present time, our evaluation of this concern is still ongoing.
We expect to complete'our evaluation and submit a final response, no later than February 15,. '92.
Very truly yours, obert E. Uhrig Vice President Advanced Systems & Technology REU/DME/ah cc: Director of Inspection and Enforcement l