Letter Furnishing Definition of Certain Technical Specification Terminology to Avoid Ambiguity or Violations at a Later Date
ML18227B781
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 06/01/1976
From: Robert E. Uhrig
Florida Power & Light Co
To: Stello V
Office of Nuclear Reactor Regulation
References
L-76-197
Download: ML18227B781 (6)


Text

f NRC FoBM 195 Ia. )6l U.S. NUCLCAB IIEGULATOB';,IMISION fo~sa ""as(

NRC DISTRIBuTION FoB PART 50 DOCKEl MATERIAL FILE NUMOEB MR V STELID 7

~

S>>

~ i,i~ (

~i FRO+FIDRIIA POWER 8o LIGHT CO MIAMI) FLA R E UHRIG......

DATC OF DOCVMFNT

~-I-l4 DATC RECEIVED

)LETTER

/ORIGINAL DCOPV QNOTOBIZED Pl UNCLASSIFIED PROP INPUT FORM NUMIIEBOF COPICS RECEIVED DESCRIPTION LTR'URN DEFINITION OF CERTAIN TECHNICAL SPECXFXCATIONS, TERMINOLOGY TO AVOID AMBIGUITY OR VIOLATXONS.........

ENCLOSV BE DO NOT REMOVE ACZNOWI,EDGED.

QOi@\\'I Q g4 SAriiY ASSIGNED AD:

2HAIICH CHIW:

PROiTECT t"IANAGEH; LIC. ASST.:

FOR ACTION/INFO RIIJIATION ASSIGNED AD.'RANCH CHIEF:

PHOJECT MANAGER:

LXC. ASST.:

EG Fir NHC PDH X8;E OELD GOSSXCK 5, STAFF MIPC CASH HANAUEH

~iiESS IM'ANAHMFXP Y

P COLLINS HOUSTON PVK'HSON MLiiTZ IIEI TE?DIES SKOVHOLT LPDH ~hl5i ~h.

VTC NSIC ASLB ACHS IOLDXNO SENT NBiC FORM IiJII ('2.78)

INTERNALD SYSTLV8 ~<<Y HEINOUS.N SCHHOEDER ENGXNEERTNG PAWLICKI HIM.cToH 8AFETY ROSS NOVAK HOSZTOCZY CHECK AT a: I SALTZMAN HUT13EBG EXTI:.RNALDISTRIBUTION 16'1'L LAI3 HHG. V-XE LA 'PDI<

CONSULTANTS IST R I BUTION PIJINT SYSTr'21S TEDESCO 13KMiROYA IPPOLITO OPERATING r?HAG"R S STELLO OPERATING TECH HXSENHUT SFIAO HAEH SCHIKNCER GRIMES SXTEi S~ii Y g LiiVLHO ANALYSIS DI':vsoN a ter EH PI<OOKIIAVEN NATL LAB ULHEl(SON 01?NL E?FIXHO TrrH Ig@QT RAr,re~

SITE TIX!H GAIRILL STEpr HULtIAN SITE ANALYSIS VOLL?iIIiH KJNCH J. coLLINs KREGEH CONTROL NUiABER

1

~

~

~

~

~

~

t

'l

~ ~

4 II 4

~

~

~

KOI48~L '."(>NOG

g0gu)tee ~<

ggtlIIyg 6'PISA%

FLORIDA POWER & LIGHT COMPANY L-76-197

<<.June 1,

1976

.'ffice of Nuclear Reactor Regulation Attn:

Mr. Victor Stello, Jr., Director Division of Operating Licenses U.

S. Nuclear Regulatory Commission Washington, D.

C.

20555

Dear Mr. Stello:

Re:

Turkey Point Plant Units 3 and 4

Docket Nos.

50-250 and 50-251 Definition of Certain Technical S ecifications Terminolo i<<>>

Certain sections of the Turkey Point Plant Units 3 and 4

Technical Specifications are being interpreted differently by the various personnel involved with implementing the technical specifications.

This letter documents the in-terpretation which the NRC Staff has given to these sections to avoid ambiguity or violations at a later date.

1.

Section 6.5.1.6:

"The Plant Nuclear Safety Committee shall be responsible for:...

h.

Review of the Plant Security Plan and implementing procedures and submitting recommended changes to the Chairman of the Company Nuclear Review Board."

The Turkey Point Security Plan indicates the responsibility for updating the plan, lies with the Vice President of Power Resources.

Therefore, Subsection 6.5.1.6.h is interpreted to read, "Review of the Plant Security Plan and implementing procedures and shall submit recommended changes to the Vice President of Power Resources for approval, and the Chairman of the Company Nuclear Review Board for information."

2.

Section 6.5.1.6:

"The Plant Nuclear Safety Committee shall be responsible for:... "i.

Review of the Emergency Plan and implementing procedures and submitting recommended changes to the Chairman of the Company Nuclear Review Board."

The Turkey Point Emergency Plan indicates that the responsibility for updating the Emergency Plan and implementing procedures, lies with the Vice President of Power Resources.

Therefore, Subsection 6.5.1.6.i is 58'ELPING BUILD FLORIDA

0 (s

,~

P "c

C

To:

Victor Stello, Jr.

Re:

Turkey Point Plant Units 3 and 4

Definition of.Certain Technical S ecifications Terminolo June 1,

1976 Page interpreted to read, "Review of the Emergency Plan and implementing procedures and shall submit recommended changes to the Vice President of Power Resources for

approval, and to the Chairman of the Company Nuclear Review Board for information."

Very truly yours, Robert E. Uhrig Vice President REU/GDW/hlc cc: