OCT 1 8 2004 FPL L-2004-236 10 CFA 50.36 William D. Travers Regional Administrator U. S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth Street, S. W., Suite 23T85 Atlanta, GA 30303 Re:

Turkey Point Unit 3 Docket No. 50-250 Steam Generator Tube Plugging 15-Day Special Report In accordance with Turkey Point Technical Specification 4.4.5.5.a, the subject Special Report is submitted pursuant to Technical Specification 6.9.2 for Turkey Point Unit 3, as a result of the End of Cycle 20 inservice inspection of steam generator tubes.

The Turkey Point Unit 3 steam generators were inspected from October 6, 2004, through October 14, 2004. No tubes required plugging in steam generators 3A, 3B or 3C as a result of these examinations.

Should there be any questions, please contact Walter Parker at 305-246-6632.

Very truly yours, Terry e

Vice President Turkey Point Nuclear Plant OIH cc: