MONTHYEARL-2016-112, Emergency Plan Implementing Procedure, Revision 6 to CY-SL-108-0004, Guidelines for Collecting Post-Accident Samples2016-05-0606 May 2016 Emergency Plan Implementing Procedure, Revision 6 to CY-SL-108-0004, Guidelines for Collecting Post-Accident Samples L-2016-099, Emergency Plan Implementing Procedures, Including Revision 50 to EPIP-04 and Revision 34 to EPIP-122016-04-21021 April 2016 Emergency Plan Implementing Procedures, Including Revision 50 to EPIP-04 and Revision 34 to EPIP-12 L-2016-054, Submittal of Revised Emergency Plan Implementing Procedures2016-03-0909 March 2016 Submittal of Revised Emergency Plan Implementing Procedures L-2016-042, Emergency Plan Implementing Procedures, Including Revision 27 to EPIP-03, Revision 40 to EPIP-08, and Revision 7 to EPIP-112016-02-29029 February 2016 Emergency Plan Implementing Procedures, Including Revision 27 to EPIP-03, Revision 40 to EPIP-08, and Revision 7 to EPIP-11 L-2016-007, Emergency Plan Implementing Procedures, Including Revision 26 to EPIP-03, Revision 48 to EPIP-04, Revision 34 to EPIP-05, and Revision 44 to EPIP-062016-01-0808 January 2016 Emergency Plan Implementing Procedures, Including Revision 26 to EPIP-03, Revision 48 to EPIP-04, Revision 34 to EPIP-05, and Revision 44 to EPIP-06 L-2015-011, Radiological Emergency Plan - Revision 632015-01-0909 January 2015 Radiological Emergency Plan - Revision 63 L-2004-090, Emergency Plan Implementing Procedures EPIP-00, Rev 2B EPIP-03, Rev 10A and HP-90, Rev 43A2004-04-13013 April 2004 Emergency Plan Implementing Procedures EPIP-00, Rev 2B EPIP-03, Rev 10A and HP-90, Rev 43A L-2004-011, Emergency Plan Implementing Procedure2004-01-30030 January 2004 Emergency Plan Implementing Procedure L-2004-002, Emergency Plan Implementing Procedure2004-01-12012 January 2004 Emergency Plan Implementing Procedure L-2003-292, Revised Emergency Plan Implementing Procedures2003-12-0202 December 2003 Revised Emergency Plan Implementing Procedures L-2003-266, Emergency Plan Implementing Procedure HP-202, Rev 30A, Environmental Monitoring During Emergencies.2003-10-15015 October 2003 Emergency Plan Implementing Procedure HP-202, Rev 30A, Environmental Monitoring During Emergencies. L-2003-242, Revision 10 to EPIP-05, Activation and Operation of the Operational Support Center, and Revision 7 to EPIP-06, Activation and Operation of the Emergency Operations Facility2003-10-0606 October 2003 Revision 10 to EPIP-05, Activation and Operation of the Operational Support Center, and Revision 7 to EPIP-06, Activation and Operation of the Emergency Operations Facility ML0327903352003-09-0202 September 2003 Emergency Plan Implementing Procedure No. EPIP-08, Rev 6, Off-Site Notifications and Protective Action Recommendations L-2003-219, Revision 7B to EPIP-13, Maintaining Emergency Preparedness - Emergency Exercises, Drills, Tests, and Evaluations2003-08-20020 August 2003 Revision 7B to EPIP-13, Maintaining Emergency Preparedness - Emergency Exercises, Drills, Tests, and Evaluations L-2003-202, Emergency Plan Implementing Procedure, EPIP-05, Revision 92003-08-11011 August 2003 Emergency Plan Implementing Procedure, EPIP-05, Revision 9 L-2003-185, Emergency Plan Implementing Procedures2003-07-18018 July 2003 Emergency Plan Implementing Procedures L-2003-175, Emergency Plan Implementing Procedure2003-07-0909 July 2003 Emergency Plan Implementing Procedure L-2003-107, Emergency Plan Implementing Procedure2003-04-23023 April 2003 Emergency Plan Implementing Procedure L-2003-072, Emergency Plan Implementing Procedures, Table of Contents - HP 203.42003-03-13013 March 2003 Emergency Plan Implementing Procedures, Table of Contents - HP 203.4 L-2003-059, Emergency Plan Implementing Procedure2003-03-0707 March 2003 Emergency Plan Implementing Procedure L-2003-046, Emergency Plan Implementing Procedure2003-02-24024 February 2003 Emergency Plan Implementing Procedure L-2003-026, Emergency Plan Implementing Procedure2003-02-0707 February 2003 Emergency Plan Implementing Procedure L-2002-215, Emergency Plan Implementing Procedure2002-10-29029 October 2002 Emergency Plan Implementing Procedure L-2002-161, Revised Emergency Plan Implementing Procedures, EPIP-09, Revision 7 - EPIP-12, Revision 112002-08-26026 August 2002 Revised Emergency Plan Implementing Procedures, EPIP-09, Revision 7 - EPIP-12, Revision 11 ML0224702502002-08-26026 August 2002 Revised Emergency Plan Implementing Procedures, EPIP-01, Revision 5, Table of Contents - EPIP-01, Revision 10, Attachment 13 L-2002-145, Emergency Plan Implementing Procedure, Rev. 7 to EPIP-13 and Rev. 41 to HP-902002-08-0808 August 2002 Emergency Plan Implementing Procedure, Rev. 7 to EPIP-13 and Rev. 41 to HP-90 L-2002-134, Revision 4 to EPIP-01, Classification Emergencies.2002-07-11011 July 2002 Revision 4 to EPIP-01, Classification Emergencies. L-2002-100, Emergency Plan Implementing Procedures2002-05-14014 May 2002 Emergency Plan Implementing Procedures L-2002-083, Emergency Plan Implementing Procedure2002-05-0202 May 2002 Emergency Plan Implementing Procedure L-2002-047, Revision 6A to EPIP-09, Off-Site Dose Calculations.2002-03-13013 March 2002 Revision 6A to EPIP-09, Off-Site Dose Calculations. L-2002-028, Revision 8 to EPIP-09, Off-Site Dose Calculations.2002-02-18018 February 2002 Revision 8 to EPIP-09, Off-Site Dose Calculations. L-2001-082, Revised Emergency Plan Implementing Procedures2001-04-0909 April 2001 Revised Emergency Plan Implementing Procedures L-99-276, Revised Epips, Including Rev 5 to EPIP-12, Maintaining Emergency Preparedness - Radiological Emergency Plan Training & Rev 15 to HP-200, Health Physics Emergency Organization. with 12/20/1999 Letter1999-12-20020 December 1999 Revised Epips, Including Rev 5 to EPIP-12, Maintaining Emergency Preparedness - Radiological Emergency Plan Training & Rev 15 to HP-200, Health Physics Emergency Organization. with 12/20/1999 Letter 2016-05-06
[Table view] Category:Letter type:L
MONTHYEARL-2024-176, Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2024-10-30030 October 2024 Annual 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums L-2024-169, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes2024-10-15015 October 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site- Specific Annexes L-2024-085, Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results2024-10-15015 October 2024 Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results L-2024-165, Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made2024-10-14014 October 2024 Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) L-2024-155, Subsequent License Renewal Application, Third Annual Update2024-09-27027 September 2024 Subsequent License Renewal Application, Third Annual Update L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-138, License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles2024-09-11011 September 2024 License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles L-2024-148, Submittal of Offsite Dose Calculation Manual (Odcm), Revision 552024-09-0909 September 2024 Submittal of Offsite Dose Calculation Manual (Odcm), Revision 55 L-2024-133, Snubber Program Plan Submittal2024-08-14014 August 2024 Snubber Program Plan Submittal L-2024-140, Cycle 28 Core Operating Limits Report2024-08-14014 August 2024 Cycle 28 Core Operating Limits Report L-2024-132, 2024 Population Update Analysis2024-08-13013 August 2024 2024 Population Update Analysis L-2024-129, Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval2024-08-0707 August 2024 Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval L-2024-121, Subsequent License Renewal Commitment 30 Revision2024-07-30030 July 2024 Subsequent License Renewal Commitment 30 Revision L-2024-123, Submittal of In-Service Inspection Program Owners Activity Report (OAR-1)2024-07-29029 July 2024 Submittal of In-Service Inspection Program Owners Activity Report (OAR-1) L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-110, Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake2024-07-10010 July 2024 Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake L-2024-109, Schedule for Subsequent License Renewal Environmental Review2024-07-0303 July 2024 Schedule for Subsequent License Renewal Environmental Review L-2024-104, Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 102024-06-26026 June 2024 Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 L-2024-097, Technical Specification Special Report2024-06-20020 June 2024 Technical Specification Special Report L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update L-2024-090, Revised Steam Generator Tube Inspection Reports2024-06-0404 June 2024 Revised Steam Generator Tube Inspection Reports L-2024-075, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-05-13013 May 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation L-2024-053, License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis2024-04-30030 April 2024 License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis L-2024-071, Cycle 27 Core Operating Limits Report2024-04-29029 April 2024 Cycle 27 Core Operating Limits Report L-2024-070, Cycle 32 Core Operating Limits Report2024-04-29029 April 2024 Cycle 32 Core Operating Limits Report L-2024-064, Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report2024-04-17017 April 2024 Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report L-2024-056, Annual Radiological Environmental Operating Report for Calendar Year 20232024-04-17017 April 2024 Annual Radiological Environmental Operating Report for Calendar Year 2023 L-2024-054, 2023 Annual Environmental Operating Report2024-04-0909 April 2024 2023 Annual Environmental Operating Report L-2024-047, Proposed Use of a Subsequent ASME Code Edition and Addenda2024-03-28028 March 2024 Proposed Use of a Subsequent ASME Code Edition and Addenda L-2024-045, Report of 10 CFR 72.48 Plant Changes2024-03-27027 March 2024 Report of 10 CFR 72.48 Plant Changes L-2024-011, And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 And Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications L-2024-023, Unusual or Important Environmental Event - Turtle Mortality2024-03-0606 March 2024 Unusual or Important Environmental Event - Turtle Mortality L-2024-015, 2023 Annual Radioactive Effluent Release Report2024-02-29029 February 2024 2023 Annual Radioactive Effluent Release Report L-2024-029, 2023 Annual Operating Report2024-02-28028 February 2024 2023 Annual Operating Report L-2024-026, Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules2024-02-27027 February 2024 Revised Reactor Vessel Materials Surveillance Capsule Withdrawal Schedules L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2024-004, Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years2024-01-18018 January 2024 Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 to 20 Years L-2024-002, Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump2024-01-0808 January 2024 Withdrawal of Proposed Alternative to American Society of Mechanical Engineers (ASME) Operation and Maintenance (OM) Code for the Auxiliary Feedwater (AFW) 2C Pump L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-179, Unusual or Important Environmental Event - Turtle Mortality2023-12-14014 December 2023 Unusual or Important Environmental Event - Turtle Mortality L-2023-168, License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 52023-12-12012 December 2023 License Amendment Request Supplement to Revision 2 for the Technical Specifications Conversion to NUREG-1432 Revision 5 L-2023-175, Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-169, Correction to the 2022 Annual Radioactive Effluent Release Report2023-11-28028 November 2023 Correction to the 2022 Annual Radioactive Effluent Release Report L-2023-162, Response to 50.69 2nd Round of Rals2023-11-21021 November 2023 Response to 50.69 2nd Round of Rals L-2023-158, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-131, Subsequent License Renewal Application - Second Annual Update2023-09-28028 September 2023 Subsequent License Renewal Application - Second Annual Update 2024-09-09
[Table view] |
Text
Florida Power & Light Company, 6501 South Ocean Drive, Jensen Beach, FL 34957 October 29, 2002 FPL L-2002-215 10 CFR 50 Appendix E U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re: St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Emerqency Plan Implementing Procedure In accordance with 10 CFR 50 Appendix E, enclosed is a copy of a revised procedure that implements the St. Lucie Plant Radiological Emergency Plan.
Number Title Revision Implementation Date COP-06.11 Establishing Remote Laboratory OB October 18, 2002 For Analyses Of Accident Samples COP-06.11 was revised to remove references and steps that refer to manual boron titration since re performed with auto titration only.
onald E.an Vice President St. Lucie Plant DEJ/tlt Enclosure 0
an FPL Group company
Procedure No.
ST. LUCIE PLANT COP-06.11 CHEMISTRY OPERATING Current Revision No.
PROCEDURE OB FPL SAFETY RELATED Effective Date 10118/02
Title:
ESTABLISHING REMOTE LABORATORY FOR ANALYSES OF ACCIDENT 8A-R_!$E i Responsible Department: CHEMISTRY REVISION
SUMMARY
- oO 'f I REVISION 0B - Removed references and steps that refer to marD are all performed with auto titration only. (Dale Majewski, 10/16/02)
REVISION OA - Replaced references to C-46 with COP-01.07. Replaced reference to C-46 with COP-01.07 on page 10 of 12. FRG reviewed this minor correction on 01/11/00. The PGM's name was added to cover page. The cover page and page 10 were reissued.
(David Valentine, 12/03/99)
REVISION 0- Previouslyissued as C-111. This procedure provides instruction for the Operational Support Center (OSC) Chemistry Supervisor to establish remote laboratories at the location(s) specified by the Technical Support Center (TSC) Chemistry Supervisor.
(Russ Cox, 05/27/99)
Revision FRG Review Date Approved By Approval Date S OPS 0 05127/99 R. G. West 05/27/99 DATE Plant General Manager DOCT PROCEDURE Revision FRG Review Date Approved By Approval Date DOCN coP-06 11 OB 01/11/00 R.G. West 01/11/00 SYS Plant General Manager COM COMPLETED Eric Katzman 12/03199 ITM OB Designated Approver G.A. Bird 10/16/02 Designated Approver (Minor Correction)
11 REVISION NO: PROCEDURE TITLE: PAGE OB ESTABLISHING REMOTE LABORATORY 2 PROCEDURE NO.: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT TABLE OF CONTENTS SECTION PAGE 1.0 P UR P O S E ....................................................................................................... 3 2.0 R EFEREN C ES ................................................................................................ 3 3.0 PREREQUISITES ..................................................................................... 4 4.0 PRECAUTIONS / LIMITATIONS ............................................................... 4 5.0 RECORDS REQUIRED ............................................................................. 4 6.0 INSTRUCTIONS ....................................................................................... 5 6.1 The OSC Chemistry Supervisor shall establish the operation of Remote Laboratories ....................................................................... 5 6.2 Set Up Boron Analysis Stand(s) ..................................................... 7 6.3 Set Up Gamma Pulse Height Analyzer(pha) System ....................... 8 6.4 Set Up Tritium Analysis System ...................................................... 9 6.5 Set Up Alpha Analysis System ..................................................... 10 6.6 Set Up Sample Prescreening Process in Remote Lab ................... 11 FIGURE FIGURE 1 MAXIMUM ALLOWABLE RADIATION READING ON SAMPLE FOR AVOIDING EXCESSIVE ANALYSIS DEAD TIME ................. 12
1 REVISION NO.: PROCEDURE TITLE. PAGE.
GB ESTABLISHING REMOTE LABORATORY PROCEDURE NO: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 1.0 PURPOSE 1.1 This procedure provides instruction for the Operational Support Center (OSC)
Chemistry Supervisor to establish remote laboratories at the location(s) specified by the Technical Support Center (TSC) Chemistry Supervisor.
1.2 To identify the minimum analyses equipment required for initial Accident Conditions.
2.0 REFERENCES
NOTE One or more of the following symbols may be used in this procedure:
§ Indicates a Regulatory commitment made by Technical Specifications, Condition of License, Audit, LER, Bulletin, Operating Experience, License Renewal, etc. and shall NOT be revised without Facility Review Group review and Plant General Manager approval.
[ Indicates a management directive, vendor recommendation, plant practice or other non-regulatory 'commitment that should NOT be revised without consultation with the plant staff.
T Indicates a step that requires a sign off on an attachment.
2.1 Plant Procedures
ý6
- EPIP-05, Activation and Operation of the Operational Support Center ADM-1 7.09, Invoking 10 CFR 50.54 (X)
COP-06.06, Guidelines for Collecting Post Accident Samples a,
- COP-07.15, Determination of Boron Using the Mettler Titrator
- COP-65.01, Ortec Multichannel Analyzers 0i
- COP-01.04, Determination of Gross Beta Gamma and Tritium with LS6500 Liquid Scintillation Counter 0 COP-01.07, Determination of Gross Alpha Radioactivity
REVISION NO.: PROCEDURE TITLE. PAGE.
OB ESTABLISHING REMOTE LABORATORY PROCEDURE NO: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 3.0 PREREQUISITES 3.1 Power from 110 volt AC outlets available.
4.0 PRECAUTIONS / LIMITATIONS 4.1 Standard Health Physics precautions shall be observed while handling all Accident samples.
4.2 ADM-1 7.09, Invoking 10 CFR 50.54(X), addresses the suspension of some Technical Specifications Surveillances when the Reactor Coolant System (RCS) is declared Out of Service. ADM-17.09 should be reviewed if the RCS is declared out of service as a result of accident conditions.
4.3 P-10 Gas is FLAMMABLE and under high pressure in the bottle.
5.0 RECORDS REQUIRED 5.1 As per routine requirements of the applicable procedures regulating the systems and sampling, etc., as per Chemistry LIMs data base computer, records for Accident Sample Inventory and Tracking as per Results Templates P1_PASINV for Unit 1, and P2_PASINV for Unit 2, or shall be maintained in the plant files in accordance with QI-17-PSL-1, Quality Assurance Records.
REVISION NO.' PROCEDURE TITLE: PAGE:
OB ESTABLISHING REMOTE LABORATORY PROCEDURE NO FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.0 INSTRUCTIONS Date/Time Initials 6.1 The OSC Chemistry Supervisor shall establish the operation of Remote Laboratories as follows:
- 1. The OSC Chemistry Supervisor shall contact the TSC Chemistry Supervisor to assess the location of the Remote Lab(s) based on the affected Reactor Unit and safe location to locate the lab(s).
Check the appropriate choices:
Accident affected Reactor is _ Unit 1 OR - Unit 2 Boron analysis Remote Lab is:
Unit 1 Hot Lab Unit 2 Hot Lab Unit 1 Cold Lab Other Location: /
L____
pha analysis Remote Lab is:
Unit 1 Hot Lab Unit 2 Hot Lab Unit I Cold Lab Other Location: / ____________
- 2. As soon as possible, the OSC Chemistry Supervisor shall assess and/or direct that the following minimum analyses equipment is set up in the designated Remote Lab(s), and ENTER the location of the test stand(s).
One Boron Analysis Stand per Step 6.2 is OPERABLE at location: IL One pha multi-channel analyzer per Step 6.3 is OPERABLE at location:
REVISION NO: PROCEDURE TITLE: PAGE*
0B ESTABLISHING REMOTE LABORATORY 6 PROCEDURE NO.: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.1 The OSC Chemistry Supervisor shall establish the Date/Time Initials operation of the Remote Laboratories as follows:
(continued)
- 3. As accident time and manpower conditions permit, the OSC Chemistry Supervisor shall assess and/or direct that the following equipment I processes are set up in the designated Remote Lab(s).
One Tritium Analysis System per Step 6.4 is OPERABLE at location: I One Alpha Analysis System per Step 6.5 is
________/
OPERABLE at location:
A second pha Detector and 92X spectrum master in the Remote Lab per Step 6.3 if the Chemistry Counting Room cannot be used as a Remote Lab. I ____________
One Sample Prescreening Process per Step 6.6 Implement Accident Sample Inventory and Results Documentation Process for records required per Step 5.1 I ____________
END OF SECTION 6.1
REVISION NO.: PROCEDURE TITLE PAGE.
OB ESTABLISHING REMOTE LABORATORY 7 PROCEDURE NO: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.2 Set Up Boron Analysis Stand(s) Date/Time Initials
- 1. ENSURE that a copy of COP-07.15, Determination of Boron Using the Mettler Titrator, is available for X the Remote Lab location. I ____________
- 2. ENSURE test stand equipment, standard and reagents are available in the Remote Lab per the applicable procedure above. I________ ____________
- 3. ENSURE a QC Boron Calibration Check is performed on the instrument test stand prior to use. I END OF SECTION 6.2
REVISION NO.* PROCEDURE TITLE: PAGE:
OB ESTABLISHING REMOTE LABORATORY 8 PROCEDURE NO: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.3 Set Up Gamma Pulse Height Analyzer(pha) System Date/Time Initials
- 1. ENSURE that a pha system is available in the Remote Lab(s) consisting of:
PC Computer "HOBBES", one 92X Spectrum Master, and Detector #1 and/or Detector #2.
OR PC Computer "CALVIN", one 92X Spectrum Master, and Detector #3. ________/ ____________
- 2. ENSURE that a copy of COP-65.01, Ortec Multichannel Analyzers, is available in the Remote Lab for the pha system(s). _______I ___________
- 3. If the pha system(s) were moved from the Unit 1 Chemistry Counting Room or the Power to them was interrupted, Then VERIFY that the High Voltage Power Supply to the Detector(s) has been restored to the values displayed on the front panel of each Detector's 92X interface box. I_______ ___________
- 4. ENSURE that a Quality Control Check Source is available and that an Activity Check is performed on the Detector(s) that are present, prior to use. ________I ___________
END OF SECTION 6.3
REVISION NO.: PROCEDURE TITLE: PAGE:
OB ESTABLISHING REMOTE LABORATORY 9 PROCEDURE NO: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.4 Set Up Tritium Analysis System Date/Time Initials
- 1. ENSURE that a Beckman LS 6500 Scintillator is available in a Remote Lab.
I ______
- 2. ENSURE that a copy of COP-01.04, Determination of Gross Beta Gamma and Tritium with LS6500 Liquid Scintillation Counter is available in the Remote Lab.
- 3. ENSURE that Quality Control Check Source(s) are available and that an Activity Check is performed on the User Program(s) for Tritium and/or 1 ml. Gross prior to use.
END OF SECTION 6.4
REVISION NO.: PROCEDURE TITLE: PAGE.
OB ESTABLISHING REMOTE LABORATORY 1 PROCEDURE NO: FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.5 Set Up Alpha Analysis System Date/Time Initials
- 1. ENSURE that one Alpha Counter and counting I_____
assembly is available in a Remote Lab.
- 2. ENSURE that a copy of COP-01.07, Determination of Gross Alpha Radioactivity, is available in the I_
Remote Lab.
CAUTION P-10 gas is FLAMMABLE.
- 3. ENSURE that a P-10 gas bottle is available to supply the instrument at the Remote Lab location. ________I________ ____________
- 4. If a P-10 bottle and temporary tubing have to be set up in a Remote Lab (other than the Chemistry Unit I Counting Room), Then the bottle connections and instrument tubing connections should be checked for gas leaks. ________I ____________
- 5. ENSURE that a Quality Control Check Source is available and that an Activity Check is performed prior to use. I ____________
END OF SECTION 6.5
REVISION NO.: PROCEDURE TITLE: PAGE OB ESTABLISHING REMOTE LABORATORY 1 PROCEDURE NO. FOR ANALYSES OF ACCIDENT SAMPLES COP-06.11 ST. LUCIE PLANT 6.6 Set Up Sample Prescreening Process in Remote Lab Date/Time Initials
- 1. OBTAIN a Health Physics General Area Survey Meter for the Remote Lab. If available, Then the survey meter should have OPEN and CLOSED window capability.
- 2. VERIFY that the Survey Meter is calibrated per the affixed calibration sticker.
- 3. CHECK the Survey Meter's Battery Check is
/ ____L__
satisfactory.
- 4. The Survey Meter should be used to measure contact readings on accident samples prior to counting. I _____
- 5. For long-term accident recovery, Figure 1 should be filled out to provide guidance for the maximum sample radiation reading(s) that can be tolerated for counting without sample pretreatment (dilution).
END OF SECTION 6.6
. I REVISION NO' PROCEDURE TITLE: PAGE OB ESTABLISHING REMOTE LABORATORY 12 of 12 PROCEDURE NO.: FOR ANALYSES OF ACCIDENT SAMPLES 1 COP-06.11 ST. LUCIE PLANT FIGURE 1 MAXIMUM ALLOWABLE RADIATION READING ON SAMPLE FOR AVOIDING EXCESSIVE ANALYSIS DEAD TiME (Page 1 of 1)
For GAMMA Analysis Without Pre-Dilution HP Survey Meter Specify Sample TYPE Analysis Maximum Allowable Engineering and Container System Contact Reading Units Gas in -30 cc glass sphere pha on Shelf #1 Gas in 1250 cc man pha on Face beaker Liquid in 16 ml vial pha on Shelf #1 geometry Liquid in 4000 ml mad pha on Face beaker Iodine in TEDA II cartridge pha on Shelf #1 (flip counted)
Particulate Filter in pha on Shelf #0 (zero)
Whirlpak on Shelf # 0 (zero) on Detector I (or 2)
Particulate Filter in pha on Shelf #1 Whirlpak on Shelf #1 on Detector 3 Evaporated Liquid in pha on appropriate planchet shelf For Alpha and Tritium Analysis Without Pre-Dilution HP Survey Meter Maximum Allowable Contact Reading: Specify Sample TYPE Analysis Specify Open Window (OW) Engineering and Container System or Closed Window (CW) Units Tritium in Liquid Sample Beckman LS6500 Tritium in Gas Sparger Beckman LS6500 Sample Alpha in Evaporated Liquid Alpha Counting Sample In Planchet System Alpha Filter Sample in Alpha Counting Planchet System