L-12-446, 2013 Perry Nuclear Power Plant Initial License Examination Proposed Exam Files

From kanterella
Jump to navigation Jump to search
2013 Perry Nuclear Power Plant Initial License Examination Proposed Exam Files
ML13175A088
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 02/25/2013
From: Bielby M E
NRC/RGN-III/DRS/OLB
To:
FirstEnergy Nuclear Operating Co
Shared Package
ML11354A275 List:
References
L-12-446
Download: ML13175A088 (6)


Text

2013 PERRY NUCLEAR POWER PLANT INITIAL LICENSE EXAMINATION PROPOSED EXAM FILES FENOCTM .irstEnmgy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road Perry, Ohio 44081 Vito A. Kaminskas 440-280-5382 Fax.* 440-280-8029 Vice President

  • December 18, 2012 L-12-446 ATIN: Mr. Michael Bielby U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352

SUBJECT:

Perry Nuclear Power Plant Docket No. 50-440, License No. NPF-58 NRC Initial License Examination Submittal 10 CFR 55 In accordance with NUREG-1 021, ES-201, "Initial Operator Licensing Examination Process," enclosed are the proposed examinations, supporting documentation, and reference materials for the NRC initial license examination scheduled to be administered at the Perry Nuclear Power Plant starting February 25, 2013. The examination materials were developed in accordance with the guidelines specified in NUREG-1 021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement

1. NUREG-1021 Forms ES-201-3, ES-301-1, ES-301-2, ES-301-3, ES-301-4, ES-301-5, ES-301-6, ES-401-1, ES-401-3, ES-401-4, ES-401-6, ES-D-1 and ES-D-2 are enclosed with the supporting documentation.

Form ES-301-6 has been completed based on the projected class size and license type at this time. The class size and makeup may change prior to the examination date. The NRC initial license examination outlines were previously sent to you on November 20, 2012. A complete set of outline forms for both the Reactor Operator (RO) and Senior Reactor Operator (SRO) examinations are included in this submittal.

It is requested that the enclosed examination materials be withheld from public disclosure until after the initial license examinations are completed.

None of the materials being sent are considered Safeguards information.

There are no regulatory commitments contained in this letter. If there are questions or if additional information is required, please contact Mr. Raymond Torres at (440) 280-5277. DtC J 6 20tt Perry Nuclear Power Plant L-12-446

  • Page2

Raymond orres David W. O'Donnell Nuclear Qualification Instructor Authorized Facility Representative Vito Kaminskas

Enclosures:

A Operator License Examination with Technical References B Reference Material to be Provided to Candidates for Written Examination C Job Performance Measures Examination D Form ES-201-3, Examination Security Agreement E Form ES-301-1, Administrative Topics Outline (RO & SRO) F Form ES-301-2, Control Room/In-Plant Systems Outline (RO, SR0-1, SRO-U) G Form ES-301-3, Operating Test Quality Checklist H Form ES-301-4, Simulator Scenario Quality Checklist I Form ES-301-5, Transient and Event Checklist J Form ES-301-6, Competencies Checklist K Form ES-401-1, BWR Examination Outline L Form ES-401-3, Generic Knowledge and Abilities Outline-Tier 3 M Form ES-401-4, Record of Rejected K/As N Form ES-401-6, Written Examination Quality Checklist 0 Form ES-D-1, Scenario Outlines P Form ES-D-2, Required Operator Actions cc: NRC Document Control Desk w/o Enclosures NRC Project Manager w/o Enclosures NRC Region Ill Branch Chief w/o Enclosures NRC Resident Inspector w/o Enclosures

  • *

Perry Date of Examination:

February 2013 Operating Test Number: 2013-01 a. b. c. d. e. a. 1. General Criteria The operating test conforms with the previously approved outline; changes are consistent with sampling requirements (e.g., 10 CFR 55.45, operational importance, safety function distribution).

There is no day-to-day repetition between this and other operating tests to be administered during this examination.

The operating test shall not duplicate items from the applicants' audit test(s). (see Section D.1.a.) Overlap with the written examination and between different parts of the operating test is within acceptable limits. It appears that the operating test will differentiate between competent and less-than-competent applicants at the designated license level. 2. Walk-Through Criteria Each JPM includes the following, as applicable:

  • initial conditions
  • initiating cues
  • references and tools, including associated procedures
  • reasonable and validated time limits (average time allowed for completion) and specific designation if deemed to be time-critical by the facility licensee
  • operationally important specific performance criteria that include: -detailed expected actions with exact criteria and nomenclature

-system response and other examiner cues -statements describing important observations to be made by the applicant

-criteria for successful completion of the task -identification of critical steps and their associated performance standards

-restrictions on the sequence of steps, if applicable Initials a b* c# b. Ensure that any changes from the previously approved systems and administrative walk-through outlines (Forms ES-301-1 and 2) have not caused the test to deviate from any of the acceptance criteria (e.g., item distribution, bank use, repetition from the last 2 NRC 1 ./1, .. (\ A examinations) specified on those forms and Form ES-201-2.

r/JrV \JN1

3. Simulator Criteria The associated simulator operating tests (scenario sets) have been reviewed in accordance with Form ES-301-4 and a copy is attached.

Printed Name I Signature Date a. Author Rav Torres -/riJ 12/12/12 b. Facility Reviewer(*)

c. NRC Chief Examiner (#) d. NRC Supervisor NOTE:
  • The facility signature is not applicable for NRC-developed tests. # Independent NRC reviewer initial items in Column "c"; chief examiner concurrence required . NUREG-1 021, Revision 9 Supplement 1 FENOC Facsimile Rev.1 ES-301 Simulator Scenario Quality Checklist Form ES-301-4 Facility:

Perry Date of Exam: Feb. 2013 Scenario Numbers: 1 I 2 I 3 Operating Test No.: 2013-01 Initials

  • QUALITATIVE ATTRIBUTES
  • 1. 2. The initial conditions are realistic, in that some equipment and/or instrumentation may be out of service, but it does not cue the operators into expected events. The scenarios consist mostly of related events. 3. Each event description consists of 4. 5. 6. 7. 8 . 9. 10. 11. 12. 13.
  • the point in the scenario when it is to be initiated
  • the malfunction(s) that are entered to initiate the event
  • the symptoms/cues that will be visible to the crew
  • the expected operator actions (by shift position)
  • the event termination point (if applicable)

No more than one non-mechanistic failure (e.g., pipe break) is incorporated into the scenario without a credible preceding incident such as a seismic event. The events are valid with regard to physics and thermodynamics.

Sequencing and timing of events is reasonable, and allows the examination team to obtain complete evaluation results commensurate with the scenario objectives.

If time compression techniques are used, the scenario summary clearly so indicates.

Operators have sufficient time to carry out expected activities without undue time constraints.

Cues are given. The simulator modeling is not altered. The scenarios have been validated.

Pursuant to 10 CFR 55.46(d}, any open simulator performance deficiencies or deviations from the referenced plant have been evaluated to ensure that functional fidelity is maintained while running the planned scenarios.

Every operator will be evaluated using at least one new or significantly modified scenario.

All other scenarios have been altered in accordance with Section 0.5 of ES-301. N/A All new All individual operator competencies can be evaluated, as verified using Form ES-N'ltlr (\ {) 301-6 (submit the form along with the simulator scenarios).

/[Jf_ \\..lV Each applicant will be significantly involved in the minimum number of transients and Jl'vtt-r (\ (\ events specified on Form ES-301-5 (submit the form with the simulator scenarios).

./Jflltf \YJ) The level of difficulty is appropriate to support licensing decisions for each crew , (PER IADin* , "'"-' IIVI'I 0.5.d) Actual Attributes

1. Total malfunctions (5-8) 5 I 6 I 7 2. Malfunctions after EOP entry (1-2) 2 I 2 I 3 3. Abnormal events (2-4) 5 I 3 I 2 4. Major transients ( 1-2) 1 I 1 I 1 5. EOPs entered/requiring substantive actions (1-2) 1 I 1 I 0 ldll11\\j 6 . EOP contingencies requiring substantive actions 1 I 2 I 2 (0-2) 7. Critical tasks (2-3) 3 I 4 I 6 NUREG-1 021, Revision 9 Supplement 1 FENOC Facsimile Rev.1
  • *

Perry Date of Exam: February 2013 Exam Level: RO SRO Initial Item Description a b* c# 1. Questions and answers are technically accurate and applicable to the facility.

2. a. NRC K/As are referenced for all questions.
b. Facility learning objectives are referenced as available.

l t--3-. __ S_R_O_q_u_e_s-ti-on_s_a_r_e_a_p_p-ro_p_r-ia-te-in_a_c_c_o-rd_a_n:....ce-w-it_h_S_e_c_tio_n_D_.2_._d_o_f_E_S_-4_0:....1--::.--------£ 1

4. The sampling process was random and systematic

{If more than 4 RO or 2 SRO questions were repeated from the last 2 NRC licensing exams, consult the NRR OL program office). 5. Question duplication from the license screening/audit exam was controlled as indicated below (check the item that applies) and appears appropriate: .Qil .lL the audit exam was systematically and randomly developed; or )1 6. .JL the audit exam was completed before the license exam was started; or w1 _ the examinations were developed independently; or .JL the licensee certifies that there is no duplication; or other (explain)

Bank use meets limits (no more than 75 percent from the bank, at least 10 percent new, and the rest new or modified);

enter the actual RO I SRO-only question distribution(s) at right. Bank 37.3%/ 20.0% Memory Modified 29.3%/ 28.0% New 33.3%/ 52.0% CIA 7. Between 50 and 60 percent of the questions on the RO exam are written at the comprehension/

analysis level; the SRO exam may exceed 60 percent if the randomly selected K/As support the higher cognitive levels; enter the actual RO I SRO question distribution(s) at right. 45.3%/12.0%

54.7% I 88.0% 8. References/handouts provided do not give away answers or aid in the elimination of distractors.

9. Question content conforms with specific KIA statements in the previously approved examination outline and is appropriate for the tier to which they are assigned; deviations are justified.
10. Question psychometric quality and format meet the guidelines in ES Appendix B. 11. The exam contains the required number of one-point, multiple choice items; the total is correct and agrees with the value on the cover sheet. Printed Name I
a. Author Ray Torres _.-fjlj"'Lfj-

// v b. Facility Reviewer{*)

Dave O'Donnell

c. NRC Chief Examiner(#)
d. NRC Regional Supervisor , Note: *The facility reviewer's initials/signature are not applicable for NRC-developed examinations.
  1. Independent NRC reviewer initial items in Column "c"; chief examiner concurrence required.

Date 12/12/12 jJ-13-12-1/J 'I"' I I I NUREG-1021, Revision 9 Supplement 1 FENOC Facsimile Rev.1