L-11-127, Occupational Radiation Exposure Report for 2010
| ML11123A153 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 04/22/2011 |
| From: | Noble D FirstEnergy Nuclear Operating Co |
| To: | Office of Nuclear Regulatory Research |
| References | |
| L-11-127 | |
| Download: ML11123A153 (1) | |
Text
FENOC FirstEnergy Nuclear Operating Company Davis-Besse Nuclear. Power Station 5501 N. State Route 2 Oak Harbor, Ohio 43449 April 22, 2011 L-11-127 10 CFR 20.2206 ATTN: REIRS Project Manager Office of Nuclear Regulatory Research United States Nuclear Regulatory Commission Washington, DC 20555
SUBJECT:
Davis-Besse Nuclear Power Station, Unit 1 Docket Number 50-346, License Number. NPF-3 Occupational Radiation Exposure Report for 2011 On April 19, 2011, the Davis-Besse Nuclear Power Station (DBNPS) staff electronically submitted 2,947 reports showing the results of occupational radiation exposure at the DBNPS during 2010. The Windows operating system file NRC5_DB_2010.dat was submitted successfully on www.reirs.com. This submittal contained data of the reports on NRC Form 5 maintained for the individuals concerned. This information is provided in accordance with 10 CFR 20.2206.
There are no regulatory commitments contained in this letter. If there are any questions or-'if additional infbrrmation is required, please contact Mr. Patrick J. McCloskey, Manager - Site Regulatory Compliance, at 419-321-7274.
Sincerely, 444,*
t Douglas L. Noble.
Manager - Site Radiation Protection Davis-Besse Nuclear Power Station JCS/JLS cc:
USNRC Document Control Desk DB-1 NRC Senior Resident Inspector DB-1 NRC/NRR Project Manager Utility Radiological Safety Board