Forwards Third ISI Interval Insp Program Plan for JAFNPP & Requests for Relief from Snubber Insp Requirements of ASME Section Xi,Article IWF-5000
ML20199G515
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 01/26/1998
From: James Knubel
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20199G519 List:
References
RTR-NUREG-0578, RTR-NUREG-578 JPN-98-002, JPN-98-2, NUDOCS 9802040291
Download: ML20199G515 (2)


Text

a 123 Abn Stfcot WNto F% ins, New York 1C301 f

v b

914 681 6840 914 287.3309 (FAX)

M MMF eIE[ve scent and g g Chief Nucles Offcer January 26,1998 JPN-98-002 U.S. Nuciear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

Subject:

James A. FitzPatrick Nuclear Power Plant Docket No. 50 333 Third laservice insoection Interval inspection Proaram Plan

Reference:

1. NYPA letter to NRC, " Proposed Changes to the Technical Specifications to Relocate Requirements for Snubbers to Plant Controlled Documents (JPTS-96-001)", dated November 26,1996.
2. NRC Generic Letter 90-09, " Alternative Requirements for Snubber Visual Intervals and Corrective Actions", dated December 11,1990.
3. NRC letter to NYPA," Issuance of Amendment For James A. FitzPatrick Nuclear Power Plant (TAC No, M82183)", dated Apnl 13,1992.

Dear Sir:

This letter submits the Third Inservice Inspection (ISI) Interval Inspection Program Plan for the James A. FitzPatrick Nuclear Power Plant. Pursuant to 10 CFR 50.55a, requests for relief from ASME Code requirements are included in this submittal as Appendx F to the Program Plan.

In accordance with 10 CFR 50.55a(g)(5)(ii), Reference 1 requested that snubber operability, surveillance, and records requirements in the Technical Specifications (TS) be relocated to plant I controlled documents. Approval of the proposed amendment was requested prior to the start of _j the third ten year interval to avoid cnnflicts between the requirements of the ASME Code and the TS. Since this amendment has not been issued as of the date of this letter, a request for relief from the snubber inspection requirements of ASME Secti:n XI, Article IWF-5000 is included in the ISI Program Plaa. Current TS snubber requirements are based on NRC Generic Letter 90-09 W.

(Ref. 2) rather than ASME Code requirements and were issued as License Amendment 180 (Ref.

3). The proposed attemative inspection in Relief Request 11 is in accordance with current TS requirements.

980204 "

?" ^0291 " *990126#g!3 Ill1111ll1

'"- illl!Illlllll vby Qeg. m wx cs _

.~ . .- -- . -

45 i

No new comm!'ments are made by the Authority in this letter. If you have any questions, please contact Ms. C. D. Falson.

Very truly y rs, J. nubel Senior Vice President and c- Chief Nuclear Officer Attachments: as stated cc:- Ragional Admin:strator U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident inspector's Office

-James A. FitzPatrick Nuclear Power Plant U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093

- Mr. D&niel H, Dorman, Project Manager

- Project Directorate 1-1 Division of Reactor Projecis -l/II U.S. Nuclear Regule'.ory Commission