JPN-92-055, Forwards Application for Amend to License DPR-59,revising Table 3.2-1, Instrumentation That Initiates Primary Containment Isolation to Reflect Installation of Addl Temp Elements in RWCU Pump Suction Primary Containment

From kanterella
(Redirected from JPN-92-055)
Jump to navigation Jump to search
Forwards Application for Amend to License DPR-59,revising Table 3.2-1, Instrumentation That Initiates Primary Containment Isolation to Reflect Installation of Addl Temp Elements in RWCU Pump Suction Primary Containment
ML20106C746
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/25/1992
From: Ralph Beedle
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20106C749 List:
References
JPN-92-055, JPN-92-55, NUDOCS 9210060331
Download: ML20106C746 (2)


Text

-_-_-

t n.

..._..o, e'4 q J i M4

  1. > NewYorkPower
n. m n -.

September 25,1992 JPN-92 055 U.S. Nuclear Ro0Llatory Commission ATTN: Document Control Desk Mail Station P1 137 Washington, D.C. 20555 3

SUBJECT:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Proposed Change to the Technical Specifications Reactoi Water Cleanup Leak Detection System Table 3.2-1 ReyistonJJPTS-91-0231

REFERENCE:

1. NRC letter, C. J. Cowgill, to NYPA dated October 18, 1990 regarding NRC Inspection Report 50 333/90 06.
2. NRC totter, C. J. CowgHl, to NYPA dated November 21, 1991 re0ardin0 NRC inspection Report 50-333/91-20.

Dear Sir,

This application for an amendment to the James A. FitzPatrick Technical Specifications revisos Table 3.2-1

  • Instrumentation that Initiatos Prima'y Containment isolation" to reflect a plant modification which installed two additional temperature elements, associated cabhng, temperature switches and circuitry in the area of the Reactor Water Cleanup (RWCU) pump suction primary containment penetration.

The Authority's equipment qualification pro 0 ram postulated a high ener0y tir'o break in a nineteen foot section of RWCU pipe that runs between the containment peneratinn and the RWCU "A' pump room. As a result, two naw temperaturo elements were added to isolate the RWCU system from the reactr.r vesselin the event of a line break in this area. Six existin0 temperature elements monitor other RWCU system areas.

The NRC (in References 1 and 2) identified that Tablo 3.2-1 of the FitzPatrick Technical Specifications only listed six RWCU area high temperature ins'rument channels when eight channels were installed in the plant, This proposed chant e adds these two new channels to correct Table 3.2-1 and to reflect the modification.

The signed original of the Appli ' ion for Amendment to Operating Licenso is enclosed ior filing. Att'

'le'its I and 11 to this application contain the proposed :,hanges to the Technmal Specifications and the associated

)

a Safet', Evaluation.

s.

e.-

9??'.000131 920925 i

PDK

\\DL;K 05000333 P

PDR

.. _............ -.. _ =

i j

=

a A copy of this application and the associated attachments are being provided to the designated New York State officiat in accordance with 10 CFR 50.91.

if you have any questions, please contact J. A. Gray, Jr.

Very truly yours, alhi t. uoouiu ~

N

r att: as stated cc: Regional Administrator U.S. Nuclear Regulatory Comrnission 475 Allendale Road King of Prussia, PA 19406 Of fice of the ilosident int.poctor 4

U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 i

Mr. Brian C. McCabe j

Project Directorato 11 Division of Reactor Projects 1/11 U.S. Nuclear Regulatory Commission Mail Stop 14 B2 Washington, DC 20555 l

l Ms. Donna Ross l

New York Stato Energy Offico 3

2 Empire Stato Plaza l

16"' Floor Albany, NY 12223

.