MONTHYEARJAFP-99-0277, Monthly Operating Rept for Sept 1999 Fpr Ja FitzPatrick Nuclear Power Plant.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 Fpr Ja FitzPatrick Nuclear Power Plant.With JAFP-99-0261, Monthly Operating Rept for Aug 1999 for Jafnpp.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Jafnpp.With JAFP-99-0236, Monthly Operating Rept for July 1999 for Ja FitzPatrick Npp. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Ja FitzPatrick Npp. with JAFP-99-0211, Monthly Operating Rept for June 1999 for Ja FitzPatrick Nuclear Power Plant.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Ja FitzPatrick Nuclear Power Plant.With JAFP-99-0181, Monthly Operating Rept for May 1999 for Jafnpp.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Jafnpp.With JAFP-99-0166, Monthly Operating Rept for Apr 1999 for Ja FitzPatrick Nuclear Plant.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Ja FitzPatrick Nuclear Plant.With JAFP-99-0142, Monthly Operating Rept for Mar 1999 for Ja FitzPatrick Nuclear Power Plant.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Ja FitzPatrick Nuclear Power Plant.With JAFP-99-0092, Monthly Operating Rept for Feb 1999 for Ja FitzPatrick Nuclear Power Plant.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Ja FitzPatrick Nuclear Power Plant.With JAFP-99-0011, Monthly Operating Rept for Dec 1998 for Ja FitzPatrick Nuclear Power Plant.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Ja FitzPatrick Nuclear Power Plant.With JAFP-98-0396, Monthly Operating Rept for Nov 1998 for Ja FitzPatrick Npp. with1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Ja FitzPatrick Npp. with JAFP-98-0360, Monthly Operating Rept for Oct 1998 for Ja FitzPatrick Nuclear Power Plant.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Ja FitzPatrick Nuclear Power Plant.With JAFP-98-0322, Monthly Operating Rept for Sept 1998 for Ja Fitzpatrick Nuclear Power Plant.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Ja Fitzpatrick Nuclear Power Plant.With ML20151X6891998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0264, Monthly Operating Rept for July 1998 for Ja FitzPatrick Nuclear Plant1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Ja FitzPatrick Nuclear Plant JAFP-98-0222, Monthly Operating Rept for June 1998 for Ja FitzPatrick Nuclear Power Plant1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0193, Monthly Operating Rept for May 1998 for Ja FitzPatrick Nuclear Plant1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Ja FitzPatrick Nuclear Plant JAFP-98-0168, Monthly Operating Rept for Apr 1998 for Ja FitzPatrick Nuclear Power Plant1998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0128, Monthly Operating Rept for Mar 1998 for Ja FitzPatrick Nuclear Power Plant1998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0091, Monthly Operating Rept for Feb 1998 for JAFNPP1998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for JAFNPP JAFP-98-0058, Monthly Operating Rept for Jan 1998 for Ja FitzPatrick Nuclear Power Plant1998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0009, Monthly Operating Rept for Dec 1997 for Ja FitzPatrick Nuclear Power Plant1997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0474, Monthly Operating Rept for Nov 1997 for Ja FitzPatrick Nuclear Power Plant1997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0435, Monthly Operating Rept for Oct 1997 for Ja FitzPatrick Nuclear Power Plant1997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0375, Monthly Operating Rept for Sept 1997 for Ja FitzPatrick Nuclear Plant1997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Ja FitzPatrick Nuclear Plant JAFP-97-0341, Monthly Operating Rept for Aug 1997 for Jfnpp1997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Jfnpp JAFP-97-0297, Monthly Operating Rept for Jul 1997 for Ja FitzPatrick Nuclear Power Plant1997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0242, Monthly Operating Rept for June 1997 for Ja FitzPatrick Nuclear Power Plant1997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0203, Monthly Operating Rept for May 1997 for Ja FitzPatrick Npp1997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Ja FitzPatrick Npp JAFP-97-0178, Monthly Operating Rept for Apr 1997 for Ja FitzPatrick Nuclear Power Plant1997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0126, Monthly Operating Rept for Mar 1997 for JAFNPP1997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for JAFNPP JAFP-97-0093, Monthly Operating Rept for Feb 1997 for James A. FitzPatrick Nuclear Power Plant1997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for James A. FitzPatrick Nuclear Power Plant JAFP-97-0056, Monthly Operating Rept for Jan 1997 for Ja FitzPatrick Nuclear Power Plant1997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Ja FitzPatrick Nuclear Power Plant JAFP-97-0012, Monthly Operating Rept for Dec 1996 for Ja FitzPatrick Nuclear Power Plant1996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0476, Monthly Operating Rept for Nov 1996 for James A. FitzPatrick Nuclear Power Plant1996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for James A. FitzPatrick Nuclear Power Plant JAFP-96-0448, Monthly Operating Rept for Oct 1996 for Ja FitzPatrick Nuclear Power Plant1996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0401, Monthly Operating Rept for Sept 1996 for Jfnpp1996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Jfnpp JAFP-96-0352, Monthly Operating Rept for Aug 1996 for Ja FitzPatrick Nuclear Power Plant1996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0300, Monthly Operating Rept for Jul 1996 for Ja FitzPatrick Nuclear Power Plant1996-07-31031 July 1996 Monthly Operating Rept for Jul 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0275, Monthly Operating Rept for June 1996 for Ja FitzPatrick Nuclear Power Plant1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0240, Monthly Operating Rept for May 1996 for Ja FitzPatrick Nuclear Power Plant1996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0196, Monthly Operating Status Rept for Apr 1996 for Ja FitzPatrick Nuclear Power Plant1996-04-30030 April 1996 Monthly Operating Status Rept for Apr 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0156, Monthly Operating Rept for Mar 1996 for Ja FitzPatrick Nuclear Power Plant1996-03-31031 March 1996 Monthly Operating Rept for Mar 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0113, Monthly Operating Rept for Feb 1996 for Ja FitzPatrick Nuclear Power Plant1996-02-29029 February 1996 Monthly Operating Rept for Feb 1996 for Ja FitzPatrick Nuclear Power Plant JAFP-96-0066, Monthly Operating Rept for Jan 1996 for JAFNPP1996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for JAFNPP JAFP-96-0023, Monthly Operating Rept for Dec 1995 for Ja Fitzpatrick Nuclear Power Plant1995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Ja Fitzpatrick Nuclear Power Plant JAFP-95-0535, Monthly Operating Rept for Nov 1995 for Jafnpp1995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for Jafnpp JAFP-95-0486, Monthly Operating Rept for Oct 1995 for Ja FitzPatrick Nuclear Plant1995-10-31031 October 1995 Monthly Operating Rept for Oct 1995 for Ja FitzPatrick Nuclear Plant JAFP-95-0444, Monthly Operating Rept for Sept 1995 for Ja FitzPatrick Nuclear Power Plant1995-09-30030 September 1995 Monthly Operating Rept for Sept 1995 for Ja FitzPatrick Nuclear Power Plant JAFP-95-0413, Monthly Operating Rept for Aug 1995 for Ja Fitzpatrick Nuclear Power Plant1995-08-31031 August 1995 Monthly Operating Rept for Aug 1995 for Ja Fitzpatrick Nuclear Power Plant JAFP-95-0372, Monthly Operating Rept for July 1995 for Ja FitzPatrick Nuclear Power Plant1995-07-31031 July 1995 Monthly Operating Rept for July 1995 for Ja FitzPatrick Nuclear Power Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARJAFP-99-0277, Monthly Operating Rept for Sept 1999 Fpr Ja FitzPatrick Nuclear Power Plant.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 Fpr Ja FitzPatrick Nuclear Power Plant.With ML20217A9931999-09-30030 September 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data JAFP-99-0261, Monthly Operating Rept for Aug 1999 for Jafnpp.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Jafnpp.With JAFP-99-0236, Monthly Operating Rept for July 1999 for Ja FitzPatrick Npp. with1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Ja FitzPatrick Npp. with ML20216D9541999-07-28028 July 1999 Safety Evaluation Authorizing Proposed Alternatives for Second 10-year Interval Pursuant to 10CFR50.55a(a)(3)(ii) ML20196H8621999-06-30030 June 1999 NRC Regulatory Assessment & Oversight Pilot Program, Performance Indicator Data, June 1999 Rept JAFP-99-0211, Monthly Operating Rept for June 1999 for Ja FitzPatrick Nuclear Power Plant.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Ja FitzPatrick Nuclear Power Plant.With JAFP-99-0175, Annual Summary of Changes,Tests & Experiments for 1997/1998. with1999-06-0202 June 1999 Annual Summary of Changes,Tests & Experiments for 1997/1998. with JAFP-99-0181, Monthly Operating Rept for May 1999 for Jafnpp.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Jafnpp.With JAFP-99-0166, Monthly Operating Rept for Apr 1999 for Ja FitzPatrick Nuclear Plant.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Ja FitzPatrick Nuclear Plant.With JAFP-99-0142, Monthly Operating Rept for Mar 1999 for Ja FitzPatrick Nuclear Power Plant.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Ja FitzPatrick Nuclear Power Plant.With JAFP-99-0092, Monthly Operating Rept for Feb 1999 for Ja FitzPatrick Nuclear Power Plant.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Ja FitzPatrick Nuclear Power Plant.With ML20207E9311999-02-26026 February 1999 Part 21 Rept Re Sprague Model TE1302 Aluminum Electrolytic Capacitors with Date Code of 9322H.Caused by Aluminum Electrolytic Capacitors.Affected Capacitors Replaced ML20202J0891999-02-0303 February 1999 Safety Evaluation Accepting Rev 2 of Third Interval Inservice Testing Program for Pumps & Valves for James a FitzPatrick Nuclear Power Plant ML20199M0891999-01-22022 January 1999 Part 21 Rept Re Failure of Square Root Converters.Caused by Failed Aluminum Electrolytic Capacitory Spargue Electric Co (Model Number TE1302 with Mfg Date Code 9322H).Sent Square Root Converters Back to Mfg,Barker Microfarads,Inc JAFP-99-0011, Monthly Operating Rept for Dec 1998 for Ja FitzPatrick Nuclear Power Plant.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Ja FitzPatrick Nuclear Power Plant.With ML20198F9991998-12-0404 December 1998 Assessment of Licensing Basis for Use of Containment Overpressure Credit for Net Positive Suction Head Analyses Power Authority of State of New York,James a Fitzpatrick Nuclear Power Plant ML20196J3501998-12-0404 December 1998 SER Accepting License Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves JAFP-98-0396, Monthly Operating Rept for Nov 1998 for Ja FitzPatrick Npp. with1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Ja FitzPatrick Npp. with ML20196F9251998-11-25025 November 1998 Safety Evaluation Re Thrid 10-year Interval Inservice Insp Program Relief Requests for Plant ML20195J7521998-11-18018 November 1998 Rev 7 to Jaf Colr ML20195K4211998-11-17017 November 1998 Safety Evaluation Authorizing Proposed Alternative in Relief Request VRR-05 Per 10CFR50.55a(a)(3)(i) & PRR-01,PRR-02R1, PRR-03,PRR-04,VRR-02,VRR-03 & VRR-04 Per 10CFR50.55a(a)(3)(ii) ML20195E1051998-11-13013 November 1998 Safety Evaluation Accepting Licensee Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves, Issued 950817 ML20197G6221998-11-0606 November 1998 Non-proprietary Rev 7 to HI-971661, Licensing Rept for Reracking of Ja FitzPatrick Sfp ML20155H5321998-11-0303 November 1998 Safety Evaluation Authorizing Alternative to ASME Code Requirements for CRD Bolting ML20155H5801998-11-0303 November 1998 Safety Evaluation Authorizing Postponement of Beginning of Augmented Exam Requirements of 10CFR50.55a(g)(6)(ii)(A)(2) Re ASME Code,Section XI JAFP-98-0360, Monthly Operating Rept for Oct 1998 for Ja FitzPatrick Nuclear Power Plant.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Ja FitzPatrick Nuclear Power Plant.With ML20155C2821998-10-30030 October 1998 Non-proprietary Rev 0 to GENE-187-30-1598 Np, CRD Bolting Flaw Evaluation for Ja FitzPatrick Nuclear Power Plant ML20154L6591998-10-14014 October 1998 Safety Evaluation Accepting Licensee Proposed Alternative to Snubber Visual Inservice Exam Intervals & Sampling Rates Requirements Contained in ASME Code,Section Xi,Subsection Iwf,Article IWF-5000 JAFP-98-0322, Monthly Operating Rept for Sept 1998 for Ja Fitzpatrick Nuclear Power Plant.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Ja Fitzpatrick Nuclear Power Plant.With ML20153D2591998-09-21021 September 1998 SER Accepting Proposed Alternative Testing of Containment Following ECCS Suction Strainer Replacement ML20153B5611998-09-0101 September 1998 Rev 1 to JAF-SE-98-013, RHR & Core Spray Suppression Pool Suction Strainer Replacement ML20151X6891998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Ja FitzPatrick Nuclear Power Plant ML20237E8361998-08-25025 August 1998 Rev 6 to Colr ML20237E9471998-08-0808 August 1998 Rev 6 to Colr JAFP-98-0264, Monthly Operating Rept for July 1998 for Ja FitzPatrick Nuclear Plant1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Ja FitzPatrick Nuclear Plant ML20236X5881998-07-29029 July 1998 Safety Evaluation Supporting Amend 245 to License DPR-59 ML20236V8181998-07-29029 July 1998 Safety Evaluation Accepting Request for Relief from Implementation of Requirements of 10CFR50.55a Related to Containment Repair & Replacement Activities for James a FitzPatrick Nuclear Power Plant ML20153B5781998-07-28028 July 1998 Rev 0 to JAF-SE-98-025, HPCI & RCIC Suppression Pool Suction Strainer Replacement ML20236X3831998-07-14014 July 1998 Rev 2 to JAF-RPT-MULTI-02671, Summary of Detailed Evaluation for NRC Generic Ltr 96-06 ML20154L9201998-07-10010 July 1998 SER Accepting Rev to Reactor Vessel Surveillance Capsule Withdrawal Schedule for James a Fitzpatrick Nuclear Power Plant JAFP-98-0222, Monthly Operating Rept for June 1998 for Ja FitzPatrick Nuclear Power Plant1998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0193, Monthly Operating Rept for May 1998 for Ja FitzPatrick Nuclear Plant1998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Ja FitzPatrick Nuclear Plant ML20248F3531998-05-21021 May 1998 Part 21 Rept Re Electronic Equipment Repaired or Reworked by Integrated Resources,Inc from Approx 930101-980501.Caused by 1 Capacitor in Each Unit Being Installed W/Reverse Polarity. Policy of Second Checking All Capacitors Is Being Adopted JAFP-98-0168, Monthly Operating Rept for Apr 1998 for Ja FitzPatrick Nuclear Power Plant1998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Ja FitzPatrick Nuclear Power Plant JAFP-98-0128, Monthly Operating Rept for Mar 1998 for Ja FitzPatrick Nuclear Power Plant1998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Ja FitzPatrick Nuclear Power Plant ML20217A4631998-03-23023 March 1998 Safety Evaluation Accepting Use of Three Heats/Lots of Hot Rolled XM-19 Matl in Core Shroud Repair Assemblies Re Licenses DPR-16 & DPR-59,respectively JAFP-98-0091, Monthly Operating Rept for Feb 1998 for JAFNPP1998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for JAFNPP ML20202G9081998-02-0606 February 1998 Safety Evaluation Re Amend to License DPR-59 to Revise TS Tables 3.2-2 & 4.2-2 JAFP-98-0058, Monthly Operating Rept for Jan 1998 for Ja FitzPatrick Nuclear Power Plant1998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Ja FitzPatrick Nuclear Power Plant 1999-09-30
[Table view] |
Text
.
OPERATING DATA REPORT DOCKETNO. 50-333 DATE August 1983 COMPLETED BY J. Cook TELEPHONE (315)342-3840 OPERATING STATUS FitzPatrick Notes
- 1. Unit Name:
- 2. Reporting Pen.o d:
830701-830731 2436
- 3. Licensed Thermal Power (MWt):
- 4. Nameplate Rating (Gross MWe): 883
- 5. Design Electrical Rating (Net MWe):. 821
- 6. Maximum Dependable Capacity (Gross MWe):
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons:
None
- 9. Power Level To W!.ich Restricted. If Any (Net MWe): None
- 10. Reasons For Restrictions. lf Any:
This Month Yr.-to.Date Cumulative 744 5087 70224
- 11. Hours in Reporting Pen.o d
- 12. Numter Of Hours Reacter Was Critical 0 3390.9 49646.6
- 13. Reactor Reserve Shutdown flours 0 0 0
- 14. Honts Generator On-Line 0 3353 , , , _ 48368.2
- 15. Unit Reserve Shutdown flours 0 0 0
- 16. Gross Thermal Energy Generated (MWH) 0 7669944 1011'3802
- 17. Gross Electrical Energy Generated (MWH) 0 2598480 35033260
- 18. Net Electrical Energy Generated (MWH) 0 2518780 33383165
- 19. Unit Service Factor 0% 65.9% 68.9%
- 20. Unit Availability Factor 0% 65.9% 68.9%
- 21. Unit Capacity Factor (Using MDC Net) . 0% 61.1% 62.4%
- 22. Unit Capacity Factor (Using DER Net) . 0% 60.3% 57.9%
- 21. Unit Forced Outage Rate 0% 9.1% 15.3%
- 24. Shutdowns Scheduled Over Next 6 Months (Type. Date.and' Duration of Each):
l
- 25. If Shut Down At End Of Report Period. Estimated Dste of Startup: Late August 1983
- 26. Units in Test Status (Prior to Commercial Operation): Forecast Achieved '
INITIAL CRITICALITY _
INITIAL ELECTRICITY 1 COMMERCIAL OPERATION 1
8308120083 830000 FDR ADOCK 05000333 - - '
R PDR l
s AVERAGE DAILY UNjT POWER LEVEL DOCKET NO. 50-333 FitzPatrick UNIT August 1983 DATE COMPLETED BY J. Cook (315j342-3840 TELEPHONE MONT11 July 1983 DAY AVER AGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe Net) (MWe Net) 1 0 0 17 2
0 0 18 0
3 19 0 4 0 0 20 0
5 M 0 0
6 22 0 7 0 0 23 0
8 24 0 9 0 0 25 10 0 0 26 0
II 27 0 12 0 0 28 13 0
29 0 14 0 30 0 15 0 0 31 0
16
SUMMARY
- The FitzPatrick plant continued it's Fifth Refueling Outage through this reporting period.
J
DOCKET NO.
50-333 UNITSIIUTDOWNS AND POWER REDUCTIONS UNIT NAME FitzPartick ,
DATE Aucust 1983 REPORT MONTil July 1983 COMPLETED BY J. Cook ,
TELEPl!ONE (315)3423840 r.
- E a
$? g j .Y E Licensee ,E r, {% Cause & Corrective No. Date g 3g g jg5 Event g? o- Action to H
$~ $ 5 ;5 c Report # MV 5"1 Prevent Recurrence e
{
c v
8 830603 s 744 c 1 N/A N/A N/A Refueling outage (cumulative hours to date 1398.6)
I 2 3 4 F: Forced Reason: Method:
S: Scheduled A Equipment Failure (Explain) Exhibit G Instructions 1-Manual for Preparation of Data B-Maintenance of Test 2 Manual Scram- Entry Sheels for Licensee C-Refueling 3 Automatic Scram.
D-Regulatory Restriction Event Report (LER) File (NUREG-4-Other (Explain) 0161)
E Operator Training & License Examination F Administrative 5 G Operational Erros (Explain)
Il-Other (Explain) Exhibit I Same Source
NEW YORK POWER AUTHORITY JAMES A. FITZPA'1 RICK NUCLEAR POWER PLANT NARRITIVE
SUMMARY
OF OPERATING EXPERIENCE JULY 1983 The refueling and maintenance outage which began June 3, 1983, continued throughout this reporting period. The major areas of work are scram discharge modification, turbine generator maintenance, LLRT testing, TORUS modification, and post accident sampling system modi-fications. Presently the outage activities are on schedule with an expected start up in late August.
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT SAFETY RELATED ELECTRICAL a MECHANICAL MAINTENANCE
SUMMARY
DATE SYSTEM O EST HOW LETECTED CAUSE OF MALFUNCTION ACTION TAKEN TO PRECLUDE RECURRENCE
'7/27 29 26640 LLRT Seat Leakage Machined seat, lapped disc and pilot 206 A0V-86B seat and disc 7/25 29 27294 Visual Loose Packing Freed frozen packing gland, and adjusted 16 A0V-86C 7/27 10 27365 LLRT Seat Leak Replaced valve 60 RHR-52A 7/20 10 25213 N/A No Failure Replaced motor and limit switches per 32 MOV-12A NRCB 79-01B 7/26 23 24429 Operations Seat Leakage Replaced internals 11 A0V-53 7/26 23 24430 Operations Seat Leakage Replaced seat ring 11 A0V-42 7/28 39 25791 LLRT Seat Leakage Ground & lapped 60 IAS-22 7/26 39 25916 LLRT Seat Leakage Ground & lapped 69 SAS-10 7/21 71 25058 N/A No Malfunction Preventive Maintenance 40 L-25 7/25 71 25057 N/A No Malfunction Preventive Maintenance 40 L-15 7/29 02 25849 LLRT Seat Leatrage Ground & lapped seat & plug 21 A0V-39 81 7/26 23 18330 Visual Leaking packing & Pressure Replaced pressure seal, lapped seat &
Seal disc, repacked MOV-14
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT .
SAFETY RELATED ELECTRICAL a MECHANICAL MAINTENANCE
SUMMARY
DATE ST SYSTEM HOW DETECTED CAUSE OF MALFUNCTION ACTION TAKEN TO PRECLUDE RECURRENCE 7/18 03 24499 OPS Packing leak on 111 valve Replaced 111 valve 1 HCU-34-23 6/30 93 15242 N/A No Malfunction Preventive Maintenance 320 EDG B&D 6/30 08 26685 Refuel, Bridge OPS Worn bushing in mast Replaced nylon bushings and stop pins 30 7/26 27 18760 Visual Various air leaks in Tightened fittings, replaced tubing, & 32 Various drywell fittings. Replaced 14S0V-13A & B 7/22 27 25907 LLRT Seat Leak Replaced "T" ring 120 A0V-112 7/22 27 25908 LLRT Seat Leak Replaced "T" ring 120 A0V-111 7/25 27 25906 LLRT Seat Leak Replaced "T" ring 60 A0V-116 7/25 27 25905 LLRT Seat Leak Replaced "T" ring 60 A0V-115 7/25 27 18774 OPS Air Leak, bad solder joint re-soldered 1 A0V-115 7/26 23 25670 Visual Loose fitting - oil leak Tightened fitting 1 TU-2 7/26 23 25669 Visual Loose fitting - oil leak Tightened fitting 1 HPI-906
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT SAFETY RELATED ELECTRICAL a MECHANICAL MAINTENANCE
SUMMARY
l WORK REQUEST # REPAIR DATE SYSTEM HOW DETECTED CAUSE OF MALFUNCTION ACTION TAKEN TO PRECLUDE RECURRENCE i M M ENT #
\
7/18 03 18646 OPS Pilot valve chatter Rebuilt pilot valve 1 HCU-06-23 7/18 03 18647 OPS Pilot valve chatter Rebuilt pilot valve 1 HCU-26-51 7/18 03 18859 OPS 111 Valve packing leak Replaced 111 valve 1 HCU-10-39 worn packing 7/18 03 i9427 OPS 117 Valve air leak Rebuilt 117 valve 1 HCU-26-35 7/20 12 25848 LLRT Seat Leak Ground seat & disc 60 RWC-62 7/19 27 25913 LLRT Seat Leak Replaced "T" ring 45 A0V-118 7/19 27 25912 LLRT Seat Leak Replaced "T" ring 45 A0V-ll7 3/10 34 20258 Visual Leaking packing & gaskets rurmanited during operating cycie 350 NRV-lllA 7/21 34 25794 LLRT Seat Leak Replaced Furmanite fittings, replaced 892 NRV-Illa shaft dog, ground seat and adjusted disc angle. Replaced disc 3/2 34 20259 Visual Leaking packing & gaskets Furmanited during operating cycle 129 NRV-111B 7/13 34 25797 LLRT Seat Leak Replaced Furmanite fittings, ground seat 453 NRV-lllB and disc, adjusted disc angle a
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT -
SAFETY RELATED ELECTRICAL a MECHANICAL MAINTENANCE
SUMMARY
DATE SYSTEM ST HOW DETECTED CAUSE OF MALFUNCTION ACTION TAKEN TO PRECLUDE RECURRENCE Ti 7/22 03 19497 OPS Accumulator Leak Rebuilt accumulator 20 HCU-42-47 7/8 10 25889 LLRT Seat Leakage Replaced seats and wedge, weld built up 206 MOV-26B and machined seats, repaired Limitorque torque switch 6/30 13 25796 LLRT Seat Leakage Machined seat rings, ground seat and 202 RCI-105 disc 6/22 23 25775 LLRT Seat Leakage Ground seat and disc 150 HPI-12 7/1 23 25774 LLRT Seat Leakage Replaced disc arm, ground seat and disc 240 HPI-65 6/25 39 25781 LLRT Seat Leakage Ground seat & disc 20 BAS-04 6/24 39 25914 LLRT Seat Leakage Ground seat & disc 15 BAS-05 7/19 17 26674 OPS Worn belts Replaced belts 12 RC-456A 7/20 10 25218 N/A No Malfunction Replaced motor and limit switches per 34 MOV-89B NRCB 79-01B 7/20 10 25217 N/A No Malfunction Replaced motor & limit switches per 18 MOV-89A NRCB 79-01B 7/19 12 16282 OPS Worn packing Repacked 6 MOV-15
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT -
SAFETY RELATED ELECTRICAL a MECHANICAL MAINTENANCE
SUMMARY
O EST ACTION TAKEN TO PRECLUDE RECURRENCE T DATE SYSTEM g HOW DETECTED CAUSE OF MALFUNCTION Installed flanges and set valve per 80 7/18 14 $4463 N/A No Malfunction SV-20A F1-79-018 Replaced motor and limit switches per 18 7/20 15 25226 N/A No Malfunction MOV-163 NRCB 79-01B Replaced key 9 27373 OPS Key fell out 7/16 10 RHR-450 .
N/A No Malfunction Disassembled and inspected for 163 6/30 10 02355 P-1D Preventive Maintenance P&V ISI 10 7/7 46 13535 N/A No Malfunction ESW-13A 22996 N/A No Malfunction Electrical Preventive Maintenance 231 6/30 71 EDG "D" 25950 OPS Valve Binding Disassembled, repaired seat, repacked, 166 6/30 10 reassembled MOV-32 No Malfunction P&V ISI 10 7/6 46 27351 N/A ESW-6A & B Improper previous Replaced bonnet gasket 16 7/6 46 25989 Incidental ESW-9B Observation maintenance P&V ISI 6 7/7 46 20741 N/A No Malfunction ESW-13B 7/7 46 13538 N/A No Malfunction P&V ISI - Found valve full of marine 7 SWS-60A growth 25795 LLRT Seat Leakage Ground seat & disc 232 7/8 13 RCI-04
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT .
SAFETY RELATED ELECTRICAL a MECHANICAL MAINTENANCE
SUMMARY
DATE SYSTEM OR Q S HOW DETECTED CAUSE OF MALFUNCTION ACTION TAKEN TO PRECLUDE RECURRENCE T
'7/8 03 21029 N/A No Malfunction Disassembled and dried 8 CRDS-30-50 &
30-54 !
I 25783 l 6/26 20 A0V-95 LLRT Seat Leakage Replaced valve internals 20 7/12 10 27374 OPS Broken disc hanger Replaced disc hanger 49 RHR-42B 7/12 00 07639 N/A No Malfunction Installed cable markers 60 IIPCI Leak Detection Sys.
7/12 14 21525 Would not Loose seat Tightened seat 53 MOV-5B stroke shut fully l 7/8 29 25847 LLRT Seat Leakage Disassembled, machined, lapped, 180 A0V-80D reassembled 7/16 10 25214 N/A No Malfunction Replaced motor per NRCB 79-01B and PM'd 21 MOV-12B 7/14 01-125 01832 N/A No Malfunction Performed Preventive Maintenance 70 MOV-11, 12 13A & B 14A & B 15A & B 100A & B 7/14 46 26720 N/A Disassemble & inspect due Cleaned valve internals 4 SWS-60B to condition of 46-SWS-60A
__ m
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT SAFETY RELATED ELECTRICAL 8 MECHANICAL MAINTENANCE
SUMMARY
DATE SYSTEM
- O HOW DETECTED CAUSE OF MALFUNCTION ACTION TAKEN TO PRECLUDE RECURRENCE E
7/13 10 25220 N/A No Malfunc. tion Replaced motor per NRCB 79-01B and PM'd 30 MOV-149A 7/16 10 25219 N/A No Malfunction Replaced motor per NRCB 79-01B and PM'd 24 MOV-148 7/12 16 16582 Incidental Operator Misadjusted Adjusted linkage 6 Drywell- Observation Emerg. Air Lock Door 6/25 20 25782 LLRT Seat leakage Replaced wedge, ground seats 79
?iOV-94 7/27 05 20163 N/A No Malfunction Performed Preventive Maintenance 30 Scram Contactors 7/23 02 24821 OPS Seat Leaks Replaced Valve Internals 22 A0V-17 & 18 l
l M
POWER AUTHORITY OF THE STATE OF NEW YORK ;
JAMES A. FITZPATRICK NUCLEAR POWER PLANT MAINTENANCE
SUMMARY
I & C JULY 1983 RESULTS OF ACTION TAKEN REPAIR WORK REQUEST # DUECTED CAUSE OF TO PRECLUDE TIME DATE SYSTEM H MALFUNCTION MALFUNCTION COMPONENT # RECURRENCE HOURS 7/1/83 63 26587 OPS Post Refuel Test Perform Friction Cal. CRD-10-31 24 l CRD-10-31 Test on Drive & 42-23 7/1/83 67 27308 OPS Input Cable Does Not Follow Checked 2 PR-46C Input Signal Calibration 7/5/83 17 17799 JIC Broken Pot Out of Replaced Pot 20 RM-251A Tolerance
~
7/6/83 11 25888 OPS Defective No Loss of Replaced Relay 15 MTR RL 67B Relay Continuity Alarm 13273 JIC Out of Out of Check Calibratioi 2 7/11/83 27 .
PS-110B Tolerance Tolerance l
7/11/83 93 26716 OPS Defective Failed to Replaced 36 EDG-D Tacometer Accelerate Tacometer 7/12/83 11 25967 OPS Set Point Drift Alarm Temp Will Ran Calibration 26 Annuciator Not Clear Check 7/12/83 93 26723 OPS Out of Adjustment Could Not Unload Adjusted & 22 EDG-D & Deftet Pot Generator Replaced Pot 7/13/83 02 17442 JIC Performance Test Need Testing Tested RTD's 38 RTD's 7/13/83 11 26307 JIC Calibration Check Calibration Perfo rmed 5 LS-70 Check ISP-82 7/14/83 93 26309 JIC Defective Air Leaks on Replaced 26 PS-11B, 11D Pressure Switch Pressures Pressure Switche!
7/15/83 76 26613 OPS Broken Fuse Spurious Alarm Replaced Fuse 6 IIolder lloider MUX #3
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT MAINTENANCE
SUMMARY
I & C JULY 1983 ACTION TAKEN REPAIR WORK REQUEST # CAUSE OF RESULTS OF TIME DATE SYSTEM H EMED MALFUNCTION TO PRECLUDE COMPONENT # MALFUNCTION RECURRENCE HOURS Pen Assembly Recorder Not Realigned 8 j 7/19/81 02-3 26682 OPS LR-98 Was Bent Working Properly Assembly & Cal. )
04216 OPS Old Age Failed Power Replaced 16 1' 7/21/83 07 SRM/IRM On/Off Indicator Switch 17828 JIC Check Perform Maint. Performed 45 7/22/83 07 IMP-7.I8 I SRM/IRM on Drives l
24937 JIC Old Age and Use Leaky Isolation Replaced 20 7/22/83 02-3 FT-64K Valve Whitney Manifold 02-3 24938 JIC Old Age and Use Leaky Isolation Replaced 20 7/22/83 Whitney Manifold FT-64P Valve 25547 JIC Defective LPRM Replaced LPRM Replaced LPRM 77 7/23/83 07 LPRM-44-29 Det. String 44-29 Det. String 44-M9 JIC Defective Wiper Broken Wiper Replaced Wiper 8 7/25/83 06 26253 PR/LR-97 Ass. & Cal. Out Arm Ass. & Cal.
7/25/83 03 26616 OPS Bulbs Damaged Indicator Lights Replaced Bulbs 10 CRD-42-31 Broken OPS Switch Stuck Relays Picked Up Open Switch & 8 7/25/33 02-3 2689@
LIS-72B For No Reason Perform ISP-3.2 26312 JIC Old Age Air Leaks Around Replaced Switch 6 7/26/83 93 PS-11A, 12C Gaskets & Calibrated Switches Out Of Cycling Open- Calibrated 32 7/26/83 14 26684 .0PS MOV-5B Tolerence .
Close-Open Cont. 14-FIS-45B mum
POWER AUTHORITY OF THE STATE OF NEW YORK JAMES A. FITZPATRICK NUCLEAR POWER PLANT MAINTENANCE
SUMMARY
I & C JULY 1983
- EST #
DATE SYSTEM CO NE T g HOW DETECTED p[ALF C ON MAL CI T EC R H S 7/28/83 76 26743 OPS Defective 2H-30 Doesn't Respond Replaced 10 Smoke Det. (CT 82-2468) to Test Gas Defective Part i
l
Jame0 A. FitzPatrick
"~ Nuclear Power Plant
~ ~ P.o. Box 41 Lycormng, New York 13093 315 342.3840
- > NewYorkPbwer l tv Authority August 8, 1983 JAFP-83-0817 Director, Office of Inspection and Enforcement U.S. Regulatory Coramission Washington, D.C. 2'-555 ATTENTION: Docuruent Control Desk
REFERENCE:
Docket No. 50-333
Dear Sir:
.s.
The Operating Status Report for the month of July, 1983 is enclosed. The refueling information remains the same as previously submitted.
If there are any questions concerning this report, contact John Cook at (315/342-3840, Ext. 439.
Very truly yours, Corbin A. McNeill, Jr.