Text

  • -=-Entergy Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

Jam es A. FitzPatri ck NP P P.O. Box 110 Lycom ing, NY 13093 Tel 3 15-342-3840 Chris M. Adner Regu latory Assurance Manager - JAF JAFP-15-0017 February 2, 2015 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555

Subject:

Response to Regulatory Issue Summary 2014-13 James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-59

Reference:

1) Letter from NRC to JAF, "NRC Regulatory Issue Summary 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees, dated December 17, 2014

Dear Sir or Madam:

In response to your request for information (Reference 1) James A. FitzPatrick (JAF) submits the attached enclosure with the projected Licensing Activities for the next 3 calendar years. JAF does not have a plan for a power uprate in the next 5 calendar years.

There are no commitments contained in this letter.

If you have any questions in this regard, please me at (315) 349-6766.

Sincere ly,

~<<L:__

Chris M. Adner Regulatory Assurance Manager

Attachment:

JAF Planned Licensing Action Submittals CMA/ble cc: USNRC, Region 1 USNRC, Project Directorate USNRC, Resident Inspector NYSE RDA

Docket No. 50-333 JAFP-15-0017 JAFP-15-0017 Attachment JAF Planned Licensing Action Submittals (1 Page)

Attachment to JAFP-15-0017 Page 1 of 1 JAF Planned Licensing Action Submittals Licensing Action Type Description Submittal Date Outage Required Comments and Date Amendment Drywell Pressure 7/1/2015 No Elimination of Drywell to Torus D/P Amendment Primary Containment 7/1/2015 Yes, Early 2018 Change surveillance frequency of ILRT ILRT Amendment OPDRV 7/1/2015 Yes, Mid 2016 Implement TSTF-542 Amendment Reactor Building DP 7/1/2015 No Approval of TSTF-551 Amendment SRV Lift Set point 12/31/2015 No To support fuel simmer margin.

Amendment Ultimate Heat Sink 12/31/2015 No Adjustment of Maximum allowed lake temperature Amendment TSTF-545 SR Frequency 12/31/2015 No NRC TSTF approval in late 2015 Amendment RWCU set point change 10/15/2015 No Change in TS 3.3.6.1 for RWCU