JAFP-15-0017, J.A. Fitzpatrick - Response to Regulatory Issue Summary 2014-13
| ML15033A024 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 02/02/2015 |
| From: | Chris Adner Entergy Nuclear Northeast, Entergy Nuclear Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| JAFP-15-0017 | |
| Download: ML15033A024 (3) | |
Text
-=-Entergy JAFP-15-0017 February 2, 2015 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A. FitzPatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315-342-3840 Chris M. Adner Regulatory Assurance Manager - JAF
Subject:
Response to Regulatory Issue Summary 2014-13 James A. FitzPatrick Nuclear Power Plant
Reference:
Docket No.
50-333 License No.
- 1) Letter from NRC to JAF, "NRC Regulatory Issue Summary 2014-13, Planned Licensing Action Submittals for all Power Reactor Licensees, dated December 17, 2014
Dear Sir or Madam:
In response to your request for information (Reference 1) James A. FitzPatrick (JAF) submits the attached enclosure with the projected Licensing Activities for the next 3 calendar years. JAF does not have a plan for a power uprate in the next 5 calendar years.
There are no commitments contained in this letter.
If you have any questions in this regard, please me at (315) 349-6766.
Sincerely,
~<<L:__
Chris M. Adner Regulatory Assurance Manager
Attachment:
JAF Planned Licensing Action Submittals CMA/ble cc:
USNRC, Region 1 USNRC, Project Directorate USNRC, Resident Inspector NYSE RDA
Docket No. 50-333 JAFP-15-0017 JAFP-15-0017 Attachment JAF Planned Licensing Action Submittals (1 Page)
Attachment to JAFP-15-0017 Page 1 of 1 JAF Planned Licensing Action Submittals Licensing Action Type Description Submittal Date Outage Required and Date Comments Amendment Drywell Pressure 7/1/2015 No Elimination of Drywell to Torus D/P Amendment Primary Containment ILRT 7/1/2015 Yes, Early 2018 Change surveillance frequency of ILRT Amendment OPDRV 7/1/2015 Yes, Mid 2016 Implement TSTF-542 Amendment Reactor Building DP 7/1/2015 No Approval of TSTF-551 Amendment SRV Lift Set point 12/31/2015 No To support fuel simmer margin.
Amendment Ultimate Heat Sink 12/31/2015 No Adjustment of Maximum allowed lake temperature Amendment TSTF-545 SR Frequency 12/31/2015 No NRC TSTF approval in late 2015 Amendment RWCU set point change 10/15/2015 No Change in TS 3.3.6.1 for RWCU