JAFP-14-0006, License Amendment Request - Cyber Security Plan Implementation Schedule Milestone 8

From kanterella
Jump to navigation Jump to search
License Amendment Request - Cyber Security Plan Implementation Schedule Milestone 8
ML14036A363
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 01/31/2014
From: Coyle L
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
JAFP-14-0006
Download: ML14036A363 (11)


Text

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

James A. FitzPatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315-349-6024 Fax 315-349-6480 Lawrence M. Coyle Site Vice-President - JAF JAFP-14-0006 January 31, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

Subject:

License Amendment Request - Cyber Security Plan Implementation Schedule Milestone 8 James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 License No. DPR-59

References:

1. NRC Internal Memorandum to Barry Westreich from Russell Felts, Review Criteria for 10 CFR 73.54, Cyber Security Implementation Schedule Milestone 8 License Amendment Requests, dated October 24, 2013 (ML13295A467)
2. NRC letter to Entergy, James A. FitzPatrick Nuclear Power Plant -

Issuance of Amendment Re: License Amendment Request - Cyber Security Plan (TAC No. ME4267), dated August 19, 2011 (ML11152A011)

3. NRC Internal Memorandum to Directors of Regional Divisions of Reactor Safety from Barry Westreich, Enhanced Guidance For Licensee Near-Term Corrective Actions To Address Cyber Security Inspection Findings And Licensee Eligibility For Good- Faith Attempt Discretion, dated July 1, 2013 (ML13178A203)

Dear Sir or Madam:

Pursuant to 10 CFR 50.4 and 10 CFR 50.90, Entergy Operations, Inc. (Entergy) hereby requests an amendment to the Renewed Facility Operating Licenses for James A. Nuclear Power Plant (JAF). In accordance with the guidelines provided by Reference 1, this request proposes a change to the JAF Cyber Security Plan Milestone 8 full implementation date as set forth in the Cyber Security Plan Implementation Schedule approved by Reference 2. provides an evaluation of the proposed change. Attachment 2 contains proposed marked-up operating license pages for the Physical Protection license condition for JAF to reference the commitment change provided in this submittal. Attachment 3 contains the proposed revised operating license pages. Attachment 4 contains a change to the date of Implementation Milestone 8. Entergy requests that Attachments 1 (Sections 1, 2, and 3) and Attachments 1 and 4 contains Sensitive Unclassified Non-Safeguards Information.

When separated from Attachments 1 and 4, this transmittal document is decontrolled.

JAFP-14-0006 Page 2 of 3 SECURITY-RELATED INFORMATION-WITHHOLD UNDER 10 CFR 2.390 and 3) and 4, which contain security-related information (SRI) , be withheld from public disclosure in accordance with 10 CFR 2.390.

The proposed changes have been evaluated in accordance with 10 CFR 50.91(a)(1) using criteria in 10 CFR 50.92(c), and it has been determined that the changes involve no significant hazards consideration. The bases for these determinations are included in .

Entergy requests this license amendment be effective as of its date of issuance. Although this request is neither exigent nor emergency, your review and approval is requested prior to December 15, 2014.

The revised commitment contained in this submittal is summarized in Attachment 5. Should you have any questions concerning this letter, or require additional information, please contact Chris M. Adner, Regulatory Assurance Manager, at 315-349-6676.

I declare under penalty of perjury that the foregoing is true and correct. Executed on January 31, 2013.

Sincerely,

~,Pj~/f LmC Lawrence M. Coyle Site Vice President LMC/CMA/mh Attachments: 1. Analysis of Proposed Operating License Change (contains SRI)

2. Proposed JAF Operating License Changes (mark-up)
3. Revised JAF Operating License Pages
4. Revised Cyber Security Plan Implementation Schedule (contains SRI)
5. List of Regulatory Commitments cc: next page Attachments 1 and 4 contains Sensitive Unclassified Non-Safeguards Information.

When separated from Attachments 1 and 4, this transmittal document is decontrolled.

JAFP-14-0006 Page 3 of 3 SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 cc:

Mr. William Dean Regional Administrator, Region I U. S. Nuclear Regulatory Commission 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 Resident Inspectors Office U.S. Nuclear Regulatory Commission James A. FitzPatrick Nuclear Power Plant P.O. Box 136 Lycoming, NY 13093 Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Mr. Mohan Thadani, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Ms. Bridget Frymire New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223 Mr. Francis J. Murray Jr., President New York State Energy and Research Development Authority 17 Columbia Circle Albany, NY 12203-6399 Document Component(s):

001 Transmittal Letter JAFP-14-0006 002 JAFP-14-0006 Attachments 2, 3, and 5 003 JAFP-14-0006 Attachments 1 and 4 (Security-Related information)

Attachments 1 and 4 contains Sensitive Unclassified Non-Safeguards Information.

When separated from Attachments 1 and 4, this transmittal document is decontrolled.

Attachment 2 JAFP-14-0006 Proposed JAF Operating License Changes (mark-up)

(4) ENO pursuant to the Act and 10 CFR Parts 30, 40, and 70 to receive, possess, and use, at any time, any byproduct, source and special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration; or associated with radioactive apparatus, components or tools..

(5) Pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

C. This renewed operating license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1) Maximum Power Level ENO is authorized to operate the facility at steady state reactor core power levels not in excess of 2536 megawatts (thermal).

(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 304, are hereby incorporated in the renewed operating license.

The licensee shall operate the facility in accordance with the Technical Specifications.

(3) Fire Protection ENO shall implement and maintain in effect all provisions of the approved fire protections program as described in the Final Safety Analysis Report for the facility and as approved in the SER dated November 20, 1972; the SER Supplement No. 1 dated February 1, 1973; the SER Supplement No. 2 dated October 4, 1974; the SER dated August 1, 1979; the SER Supplement dated October 3, 1980; the SER Supplement dated February 13, 1981; the NRC Letter dated February 24, 1981; Technical Specification Amendments 34 (dated January 31, 1978), 80 (dated May 22, 1984), 134 (dated July 19, 1989), 135 (dated September 5, 1989), 142 (dated October 23, 1989), 164 (dated August 10, 1990), 176 (dated January 16, 1992), 177 (dated February 10, 1992), 186 (dated February 19, 1993),

190 (dated June 29, 1993), 191 (dated July 7, 1993), 206 (dated February 28, 1994) and 214 (dated June 27, 1994); and NRC Exemptions and associated safety evaluations dated April 26, 1983, July 1, 1983, January 11, 1985, April 30, 1986, September 15, 1986 and September 10, 1992 subject to the following provision:

Amendment 304

Safeguards Contingency Plan, Revision 0, submitted by letter dated October 26, 2004, as supplemented by letter dated May 17, 2006.

ENO shall fully implement and maintain in effect all provisions of the Commission-approved cyber security plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). ENO CSP was approved by License Amendment No. 300, as supplemented by a changes approved by License Amendment Nos. 303 and XXX.

E. Power Uprate License Amendment Implementation The licensee shall complete the following actions as a condition of the approval of the power uprate license amendment.

(1) Recirculation Pump Motor Vibration Perform monitoring of recirculation pump motor vibration during initial Cycle 13 power ascension for uprated power conditions.

(2) Startup Test Program The licensee will follow a startup testing program, during Cycle 13 power ascension, as described in GE Licensing Topical Report NEDC-31897P-1, Generic Guidelines for General Electric Boiling Water Reactor Power Uprate. The Startup test program includes system testing of such process control systems as the feedwater flow and main steam pressure control systems. The licensee will collect steady-state operational data during various portions of the power ascension to the higher licensed power level so that predicted equipment performance characteristics can be verified. The licensee will do the startup testing program in accordance with its procedures. The licensees approach is in conformance with the test guidelines of GE Licensing Topical Report NEDC-31897P-1, Generic Guidelines for General Electric Boiling Water Reactor Power Uprate. June 1991 (proprietary), GE Licensing Topical Report NEDO-31897, Generic Guidelines for General Electric Boiling Water Reactor Power Uprate. February 1992 (nonproprietary), and NEDC-31897P-AA, Class III (proprietary), May 1992.

(3) Human Factors The licensee will review the results of the Cycle 13 startup test program to determine any potential effects on operator training. Training issues identified will be incorporated in Licensed Operator training during 1997. Simulator discrepancies identified will be addressed in accordance with simulator Configuration Management procedural requirements.

F. Additional Conditions The Additional Conditions contained in Appendix C, as revised through Amendment No. 289, are herby incorporated into this renewed operating license. ENO shall operate the facility in accordance with the Additional Conditions.

Amendment 303

Attachment 3 JAFP-14-0006 Revised JAF Operating License Pages

(4) ENO pursuant to the Act and 10 CFR Parts 30, 40, and 70 to receive, possess, and use, at any time, any byproduct, source and special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration; or associated with radioactive apparatus, components or tools..

(5) Pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

C. This renewed operating license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Sections 50.54 and 50.59 of Part 50, and Section 70.32 of Part 70; and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1) Maximum Power Level ENO is authorized to operate the facility at steady state reactor core power levels not in excess of 2536 megawatts (thermal).

(2) Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. , are hereby incorporated in the renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.

(3) Fire Protection ENO shall implement and maintain in effect all provisions of the approved fire protections program as described in the Final Safety Analysis Report for the facility and as approved in the SER dated November 20, 1972; the SER Supplement No. 1 dated February 1, 1973; the SER Supplement No. 2 dated October 4, 1974; the SER dated August 1, 1979; the SER Supplement dated October 3, 1980; the SER Supplement dated February 13, 1981; the NRC Letter dated February 24, 1981; Technical Specification Amendments 34 (dated January 31, 1978), 80 (dated May 22, 1984), 134 (dated July 19, 1989), 135 (dated September 5, 1989), 142 (dated October 23, 1989), 164 (dated August 10, 1990), 176 (dated January 16, 1992), 177 (dated February 10, 1992), 186 (dated February 19, 1993),

190 (dated June 29, 1993), 191 (dated July 7, 1993), 206 (dated February 28, 1994) and 214 (dated June 27, 1994); and NRC Exemptions and associated safety evaluations dated April 26, 1983, July 1, 1983, January 11, 1985, April 30, 1986, September 15, 1986 and September 10, 1992 subject to the following provision:

Amendment

Safeguards Contingency Plan, Revision 0, submitted by letter dated October 26, 2004, as supplemented by letter dated May 17, 2006.

ENO shall fully implement and maintain in effect all provisions of the Commission-approved cyber security plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). ENO CSP was approved by License Amendment No. 300, as supplemented by changes approved by License Amendment Nos. 303 and .

E. Power Uprate License Amendment Implementation The licensee shall complete the following actions as a condition of the approval of the power uprate license amendment.

(1) Recirculation Pump Motor Vibration Perform monitoring of recirculation pump motor vibration during initial Cycle 13 power ascension for uprated power conditions.

(2) Startup Test Program The licensee will follow a startup testing program, during Cycle 13 power ascension, as described in GE Licensing Topical Report NEDC-31897P-1, Generic Guidelines for General Electric Boiling Water Reactor Power Uprate. The Startup test program includes system testing of such process control systems as the feedwater flow and main steam pressure control systems. The licensee will collect steady-state operational data during various portions of the power ascension to the higher licensed power level so that predicted equipment performance characteristics can be verified. The licensee will do the startup testing program in accordance with its procedures. The licensees approach is in conformance with the test guidelines of GE Licensing Topical Report NEDC-31897P-1, Generic Guidelines for General Electric Boiling Water Reactor Power Uprate. June 1991 (proprietary), GE Licensing Topical Report NEDO-31897, Generic Guidelines for General Electric Boiling Water Reactor Power Uprate. February 1992 (nonproprietary), and NEDC-31897P-AA, Class III (proprietary), May 1992.

(3) Human Factors The licensee will review the results of the Cycle 13 startup test program to determine any potential effects on operator training. Training issues identified will be incorporated in Licensed Operator training during 1997. Simulator discrepancies identified will be addressed in accordance with simulator Configuration Management procedural requirements.

F. Additional Conditions The Additional Conditions contained in Appendix C, as revised through Amendment No. 289, are herby incorporated into this renewed operating license. ENO shall operate the facility in accordance with the Additional Conditions.

Amendment

Attachment 5 JAFP-14-0006 List of Regulatory Commitments

JAFP-14-0006 Attachment 5 List of Regulatory Commitments The following table identifies those actions committed to by Entergy in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments.

TYPE SCHEDULED (Check One) COMPLETION COMMITMENT DATE ONE-TIME CONTINUING (If Required)

ACTION COMPLIANCE Full implementation of JAF Cyber Security X June 30, 2016 Plan for all safety, security, and emergency preparedness functions will be achieved.

Page 1 of 1