JAFP-05-0180, Registration of Spent Fuel Cask Use

From kanterella
Jump to navigation Jump to search

Registration of Spent Fuel Cask Use
ML053360112
Person / Time
Site: FitzPatrick  
Issue date: 11/22/2005
From: Ted Sullivan
Entergy Nuclear Northeast, Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
References
JAFP-05-0180
Download: ML053360112 (2)


Text

Entergy Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

James A. Fitzpatrick NPP P.O. Box 110 Lycoming, NY 13093 Tel 315 349 6024 Fax 315 349 6480 November 22, 2005 JAFP-05-0180 T.A. Sullivan Site Vice President - JAF U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

James A FitzPatrick Nuclear Power Plant Docket No.s 50-333 and 72-12 License No. DPR-59 Registration of Spent Fuel Cask Use

Dear Madam or Sir:

Entergy Nuclear Operations, Inc. (ENO), operates the James A. FitzPatrick (JAF) Nuclear Power Plant Independent Spent Fuel Storage Installation (ISFSI) in accordance with the general license provisions of 10 CFR 72.2 10. The conditions of 10 CFR 72.212(b)(IlXii) include the registration of a spent fuel cask within 30 days of using a cask for storage of spent nuclear fuel. Accordingly, JAF provides the following registration information associated with three (3) HI-STORM 100 spent fuel cask systems that were recently placed into storage in the JAF ISFSI.

Cask Certificate:

Cask Model:

MPC Serial Number:

Overpack Serial Number:

Number of Fuel Bundles:

Placed in Service:

Cask Certificate:

Cask Model:

MPC Serial Number:

Overpack Serial Number:

Number of Fuel Bundles:

Placed in Service:

Cask Certificate:

Cask Model:

MPC Serial Number:

Overpack Serial Number:

Number of Fuel Bundles:

Placed in Service:

Total Cask Systems stored in the JAF ISFSI:

72-1014 HI-STORM 100, Version B 159 186 68 10/25/2005 7241014 HI-STORM 100, Version B 160 187 68 11/8/2005 72-1014 HI-STORM 100, Version B 161 188 68 11/21/2005 Nine (9) HI-STORM 100 Cask Systems W4 vTVSSDI

This letter contains no new commitments. Should you have any questions or require further information, please contact Mr. James Costedio, Regulatory Compliance Manager, at (315) 349-6358.

Very truly yours, T..

cc:

Mr. Samuel J. Collins Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 U.S. Nuclear Regulatory Commission James A. FitzPatrick Nuclear Power Plant P.O. Box 136 Lycoming, NY 13093 Mr. John P. Boska, Project Manager Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop: O-8-C2 Washington, DC 20555 Mr. Paul Eddy Electric Division New York State Department of Public Service 3 Empire State Plaza, I0th Floor Albany NY 12223 Mr. Peter Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203