IR 05000461-06-003 on 01/30/2006 - 02/02/2006 for Exelon Nuclear Corporate; 10/23/2006 - 10/27/2006; Clinton Power Station - Cover Letter
ML063400404
Person / Time
Site: Clinton Constellation icon.png
Issue date: 11/30/2006
From: Kenneth Riemer
Plant Support Branch II
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-06-003
Download: ML063400404 (4)


Text

ber 30, 2006

SUBJECT:

CLINTON POWER STATION NRC SECURITY BASELINE INSPECTION REPORT NO. 05000461/2006003(DRS)

Dear Mr. Crane:

On October 27, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Clinton Power Station and Exelon Nuclear Corporate.

The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on October 27, 2006, with Mr. B. Hansen, and February 2, 2006, with Mr. G. Kaegi, and other members of your staff.

This inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observations of activities, and interviewed personnel.

No findings of significance were identified.

EXEMPT FROM PUBLIC DISCLOSURE May be exempt from public release under the Freedom of Information Act (5 U.S.C. 552)

Exemption number: 5 Nuclear Regulatory Commission review required before public release Enclosure Contains Sensitive Unclassified Non-Name and organization of person making determination. Safeguards Information. Upon separation, this D. Funk, RIII/DRS/PSB page is decontrolled.

Date of determination: 10/31/06 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA/

Kenneth Riemer, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-461 License No. NPF-62 Nonpublic Enclosure: Inspection Report 05000461/2006003(DRS)

w/Attachment: Supplemental Information cc w/encl: B. Westriech (NSIR/DNS)

NSIR/DNS/RSS/Licensing Assistant C. Williamson, Clinton Site Security Manager State Liaison Officer, State of Illinois cc w/o encl: Site Vice President - Clinton Power Station Plant Manager - Clinton Power Station Regulatory Assurance Manager - Clinton Power Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Manager Licensing - Clinton Power Station Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency Chairman, Illinois Commerce Commission