IR 05000423/2003008
| ML032670587 | |
| Person / Time | |
|---|---|
| Site: | Millstone |
| Issue date: | 09/19/2003 |
| From: | Doerflein L NRC Region 1 |
| To: | Christian D Dominion Nuclear Connecticut, Dominion Resources |
| References | |
| IR-03-008 | |
| Download: ML032670587 (19) | |
Text
September 19, 2003
SUBJECT:
MILLSTONE POWER STATION UNIT 3 - NRC INSPECTION REPORT 05000423/2003008
Dear Mr. Christian:
On August 14, 2003, the U. S. Nuclear Regulatory Commission (NRC) completed an engineering team inspection at Millstone Power Station Unit 3. The enclosed report presents the results of that inspection, which were discussed at an exit meeting on August 14, 2003, with Mr. J. Alan Price and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety, and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspection consisted of system walkdowns; examination of selected procedures, drawings, modifications, calculations, surveillance tests and maintenance records; and interviews with station personnel.
Based on the results of this inspection, no findings of significance were identified.
In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web-site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Lawrence T. Doerflein, Chief Systems Branch Division of Reactor Safety Docket Nos.: 50-423 License Nos.: NPF-49 Enclosure:
Inspection Report 05000423/2003008 w/Attachment: Supplemental Information
Mr. David