APPENDIX B NOTICE OF DEVIATION Pennsylvania Power
& Light Company Susquehanna Steam Electric Station Units 1 and
Docket Nos.
50-387
, 50-388 License Nos.
'PF-22 EA 85-73 During an NRC inspection conducted on April 22 May 8, 1985, a deviation from the Final Safety Analysis Report (FSAR) was identified.
In accordance with the
"General Statement of Policy and Procedure for NRC Enforcement Actions,"
CFR Part 2 Appendix C (1985), the deviation is set forth below:
The Final Safety Analysis Report (FSAR),
and Regulatory Guide (RG) 1. 106, Revision 1 specifies that thermal overloads in safety related motor,'perated valves be continuously bypassed.
Section C. 1 of this RG specifies that the non-bypassing of these thermal overloads be continuously indicated in the control room.
Contrary to the above, thermal overloads on safety-related motor operated valves can be unbypassed by switches on Panel OC697 and this condition is not indicated in the control room.
This is a deviation.
Pennsylvania Power 5 Light Company is hereby requested to submit to this,',office within>30 days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including:
(1) the corrective steps which have been taken and the results achieved, (2) the corrective steps which, will be taken to avoid further deviations, and (3) the date when corrective action will be completed.
8507220353 8507ib PDR ADOCK 05000387
PDR OFFICIAL RECORD COPY CP PKG SUSQUEHANNA REV 2 - 0006.0.0 07/12/85