UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 November 6, 2008 Mr. William R. Campbell, J Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 SUBJECT: WATTS BAR NUCLEAR PLANT - RESULTS OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES USING TEMPORARY INSTRUCTION 2515/171 INSPECTION REPORT N /2008008 On October 3, 2008, the United States Nuclear Regulatory Commission (NRC) completed a team inspection at your Watts Bar Nuclear Plant. The enclosed report documents the inspection results, which were discussed with Mr. Mike Skaggs and other members of your staff on October 3, 2008 The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commissions rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observation of activities, and interviews with station personne This report documents no findings of significanc In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). 2 However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspectio

Sincerely,

/RA/

Eugene Guthrie, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No.: 50-390, 50-391 License No.: NPF-90, CPPR-92 Nonpublic Enclosure: Inspection Report 05000390/2008008 w/Attachment: Supplemental Information cc w/encl: (See Page 3) ___________________

OFFICE RII:DRP RII:DRS RII:DRP HQ:NRR HQ:NRR RII: DRP RII:DRP SIGNATURE /RA/ /RA by email/ /RA/ /RA by email/ /RA by email/ /RA/ /RA by email/

NAME E. Gutherie R. Fanner L. Garner D. Nelson J. Shedlosky J. Baptist R. Monk DATE 11/06/2008 11/04/2008 11/06/2008 11/04/2008 10/31/2008 11/06/2008 11/06/2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO 3 cc w/encl:

Ashok S. Bhatnagar Masoud Bajestani Senior Vice President Vice President Watts Bar Unit 2 Nuclear Generation Development & Watts Bar Nuclear Plant Construction Tennessee Valley Authority Tennessee Valley Authority Watts Bar Unit 2 6A Lookout Place P.O. Box 2000 1101 Market Street Spring City, TN 37381 Chattanooga, TN 37402-2801 Beth A. Wetzel Tom Coutu Manager Vice President Corporate Licensing Nuclear Support Tennessee Valley Authority Tennessee Valley Authority 4K Lookout Place 3R Lookout Place 1101 Market Street 1101 Market Street Chattanooga, TN 37402-2801 Chattanooga, TN 37402-2801 Michael J. Lorek Walter M. Justice, II Interim Vice President Interim Vice President Nuclear Engineering & Projects Nuclear Engineering & Technical Services Tennessee Valley Authority Tennessee Valley Authority 3R Lookout Place 6A Lookout Place 1101 Market Street 1101 Market Street Chattanooga, TN 37402-2801 Chattanooga, TN 37402-2801 Michael K. Brandon Michael D. Skaggs Manager Site Vice President Licensing and Industry Affairs Watts Bar Nuclear Plant Tennessee Valley Authority Tennessee Valley Authority Watts Bar Nuclear Plant P. O. Box 2000 P.O. Box 2000 Spring City, TN 37381 Spring City, TN 37381 General Counsel Tennessee Valley Authority 6A West Tower 400 West Summit Hill Drive Knoxville, TN 37902 John C. Fornicola General Manager Nuclear Assurance Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 4 cc: w/o Encl:

County Executive 375 Church Street Suite 215 Dayton, TN 37321 County Mayor P.O. Box 156 Decatur, TN 37322 Lawrence Edward Nanney Director Division of Radiological Health TN Dept. of Environment & Conservation 3rd Floor, L&C Annex 401 Church Street, 3rd Floor Nashville, TN 37243-1532 Ann Harris 341 Swing Loop Rockwood, TN 37854 James H. Bassham Director Tennessee Emergency Management Agency P.O. Box 41502 Nashville, TN 37204-1502 5 Letter to William R. Campbell, Jr from Eugene Guthrie dated November 6, 2008 SUBJECT: WATTS BAR NUCLEAR PLANT - RESULTS OF INSPECTION OF THE IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES REPORT NO. 05000390/2008008 Distribution w/encl:

L. Reyes, RA V. McCree, DRA L. Wert, DRP J. Moorman, DRP (Acting)

K. Kennedy, DRS R. Croteau, DRS H. Christensen, DRS E. Guthrie, DRP L. Garner, DRP J. Baptist, DRP R. Monk, DRP R. Fanner, DRS P. Milano, NRR (PM - WB 1)

L. Raghavan, NRR E. Bowman, NRR L. Slack, RII EICS OE Mail (email address if applicable)

RIDSNRRDIRS Distribution w/o encl:

PUBLIC