September 1, 2011
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - ST. LUCIE NUCLEAR PLANT UNIT 1 AND UNIT 2 (NRC INSPECTION REPORT 05000335/2011006 AND 05000389/2011006)
Dear Mr. Nazar:
On August 10, 2011, the NRC staff completed its performance review of the St. Lucie Nuclear Plant. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010, through June 30, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.
The NRC determined the performance at St. Lucie Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP)
Action Matrix because all inspection findings had very low (i.e., green) safety significance and all PIs indicated performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2012.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines
(SAMGs) at your facility. Results of these inspections can be found here:
http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident. The NRC is currently reviewing the Task Forces recommendations to determine what additional actions may be warranted.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (404) 997-4721 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Daniel W. Rich, Chief Reactor Projects Branch 3 Division of Reactor Projects
Docket Nos.: 50-335, 50-389 License Nos.: DPR-67, NPF-16
Enclosure: St. Lucie Nuclear Plant Inspection/Activity Plan (09/01/11 - 12/31/12)
PKG.: ML112440323______
X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRP RII:DRP
SIGNATURE GJW DWR1
NAME GWilson DRich
DATE 09/01/2011 09/01/2011
E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
cc w/encl:
Richard L. Anderson Site Vice President St. Lucie Nuclear Plant Electronic Mail Distribution
Robert J. Hughes Plant General Manager St. Lucie Nuclear Plant Electronic Mail Distribution
Gene St. Pierre Vice President, Fleet Support Florida Power & Light Company Electronic Mail Distribution
Daniel D. DeBoer Operations Site Director St. Lucie Nuclear Plant Electronic Mail Distribution
Eric Katzman Licensing Manager St. Lucie Nuclear Plant Electronic Mail Distribution
Larry Nicholson Director Licensing Florida Power & Light Company Electronic Mail Distribution
Alison Brown Nuclear Licensing Florida Power & Light Company Electronic Mail Distribution
Mitch S. Ross Vice President and General Counsel Nuclear Florida Power & Light Company Electronic Mail Distribution
Marjan Mashhadi Senior Attorney Florida Power & Light Company Electronic Mail Distribution
William A. Passetti Chief Florida Bureau of Radiation Control Department of Health Electronic Mail Distribution
Bryan Koon Director Florida Division of Emergency Management Electronic Mail Distribution
Donna Calabrese Emergency Preparedness Manager St. Lucie Plant Electronic Mail Distribution
J. Kammel Radiological Emergency Planning Administrator Department of Public Safety Electronic Mail Distribution
Senior Resident Inspector St. Lucie Nuclear Plant U.S. Nuclear Regulatory Commission P.O. Box 6090 Jensen Beach, FL 34957-2010
Seth B. Duston Training Manager St. Lucie Nuclear Plant Electronic Mail Distribution
Faye Outlaw County Administrator St. Lucie County Electronic Mail Distribution
Jack Southard Director Public Safety Department St. Lucie County Electronic Mail Distribution
Letter to Mano Nazar from Daniel W. Rich dated September 1, 2011
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - ST. LUCIE NUCLEAR PLANT UNIT 1 AND UNIT 2 (NRC INSPECTION REPORT 05000335/2011006 AND 05000389/2011006)
Distribution w/encl:
C. Evans, RII EICS L. Douglas, RII EICS OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMStLucie Resource Institute of Nuclear Power Operations (INPO)
ROPReports