IR 05000315/2006011
From kanterella
Jump to navigation
Jump to search
ML062780378 | |
Person / Time | |
---|---|
Site: | Cook |
Issue date: | 10/04/2006 |
From: | Christine Lipa NRC/RGN-III/DRP/RPB4 |
To: | Nazar M Indiana Michigan Power Co |
References | |
IR-06-011 | |
Download: ML062780378 (3) | |
Similar Documents at Cook | |
---|---|
Category:Inspection Report
MONTHYEARIR 05000315/20240022024-07-24024 July 2024
[Table view]Integrated Inspection Report 05000315/2024002 and 05000316/2024002 IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 IR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 IR 05000315/20224202022-10-19019 October 2022 Cover Letter - Donald C. Cook Nuclear Plant Units 1 and 2 - Security Baseline Inspection Report 05000315/2022420 and 05000316/2022420 IR 05000315/20224012022-09-21021 September 2022 Security Baseline Inspection Report 05000315 2022401 05000316 2022401 Independent Spent Fuel Storage Security Inspection Report 07200072 2022401 IR 05000315/20223012022-08-31031 August 2022 NRC Initial License Examination Report 05000315/2022301; 05000316/2022301 IR 05000315/20220052022-08-24024 August 2022 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) IR 05000315/20220022022-08-0808 August 2022 Integrated Inspection Report 05000315/2022002 and 05000316/2022002 IR 05000315/20224022022-07-0505 July 2022 Material Control and Accounting Program Inspection Report 05000315/2022402 and 05000316/2022402 ML22165A2012022-06-14014 June 2022 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2022001 and 05000316/2022001 ML22129A2052022-05-10010 May 2022 Integrated Inspection Report 05000315/2022001 and 05000316/2022001 IR 05000315/20220012022-05-10010 May 2022 Integrated Inspection Report 05000315/2022001 and 05000316/2022001 IR 05000315/20220102022-04-0505 April 2022 Triennial Fire Protection Inspection Report 05000315/2022010 and 05000316/2022010 ML22084A5812022-03-25025 March 2022 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000315/2022011 05000316/2022011 IR 05000315/20210062022-03-0202 March 2022 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) IR 05000315/20210042022-02-0707 February 2022 Integrated Inspection Report 05000315/2021004 and 05000316/2021004 and Exercise of Enforcement Discretion IR 05000315/20210132021-12-0606 December 2021 Inspection Report 05000315/2021013 and 05000316/2021013 IR 05000315/20214032021-11-17017 November 2021 Security Baseline Inspection Report 05000315/2021403 and 05000316/2021403 IR 05000315/20210112021-11-15015 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000315/2021011 and 05000316/2021011 IR 05000315/20210032021-10-26026 October 2021 Integrated Inspection Report 05000315/2021003; 05000316/2021003; and 07200072/2021001 IR 05000315/20214012021-10-21021 October 2021 Cyber Security Inspection Report 05000315/2021401 and 05000316/2021401 IR 05000315/20215012021-10-0606 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2021501 and 05000316/2021501 IR 05000315/20210102021-09-0707 September 2021 Biennial Problem Identification and Resolution Inspection Report 05000315/2021010 and 05000316/2021010 IR 05000315/20210052021-09-0101 September 2021 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) IR 05000315/20210122021-08-0202 August 2021 Donald Cook Nuclear Plant - NRC Inspection Report 05000315/2021012 and 05000316/2021012 IR 05000315/20210022021-07-22022 July 2021 Integrated Inspection Report 05000315/2021002 and 05000316/2021002 IR 05000315/20214022021-06-0909 June 2021 Donald D. C. Cook Nuclear Plant - Security Baseline Inspection Report 05000315/2021402 and 05000316/2021402 ML21158A1732021-06-0909 June 2021 Review of the Fall 2017 Steam Generator Tube Inspections Report IR 05000315/20210012021-04-28028 April 2021 Integrated Inspection Report 05000315/2021001 and 05000316/2021001 IR 05000315/20200062021-03-0404 March 2021 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) IR 05000315/20200042021-02-0808 February 2021 Integrated Inspection Report 05000315/2020004 and 05000316/2020004 IR 05000315/20204032020-12-16016 December 2020 Security Baseline Inspection Report 05000315/2020403 and 05000316/2020403 IR 05000315/20204022020-11-0404 November 2020 Security Baseline Inspection Report 05000315/2020402 and 05000316/2020402 IR 05000315/20200032020-10-28028 October 2020 Integrated Inspection Report 05000315/2020003 and 05000316/2020003 IR 05000315/20203012020-10-19019 October 2020 NRC Initial License Examination Report 05000315/2020301; 05000316/2020301 2024-07-24 Category:Letter MONTHYEARAEP-NRC-2024-62, Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask2024-08-0808 August 2024
[Table view]Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring IR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump 2024-08-08 |
Inspection Report - Cook - 2006011 | |
---|---|