August 18, 2025

SUBJECT:

UPDATED INSPECTION PLAN FOR DIABLO CANYON POWER PLANT (REPORT 05000275/2025005 AND 05000323/2025005)

Dear Paula A. Gerfen:

The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for Diablo Canyon Power Plant, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025, (ML25042A278), the NRC determined that a broad, comprehensive review of the Reactor Oversight Process (ROP) is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented. The NRC will perform Inspection Procedure 60859, Independent Spent Fuel Storage Installation (ISFSI) License Renewal Inspection, at your facility as indicated in the enclosed inspection plan, because your ISFSI has entered its Period of Extended Operation.

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding. Please contact me at (817) 200-1144 with any questions you have regarding this letter.

Sincerely, Patricia J. Vossmar, Chief Reactor Projects Branch A Division of Operating Reactor Safety Docket Nos. 05000275; 05000323; 07200026 License Nos. DPR-80; DPR-82; SNM-2511 Enclosure:

Inspection Plan cc w/ encl: Distribution via LISTSERV Signed by Vossmar, Patricia on 08/18/25

ML25227A017

SUNSI Review By: RLB

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE SPE:DORS/PBA BC:DORS/PBA NAME RBywater PVossmar SIGNATURE

/RA/

/RA/

DATE 08/15/25 08/18/25

Site Inspection Activity Plan Diablo Canyon 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Fire Protection Inspection-DC

1,2 7/6/2025 7/12/2025 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

1,2 7/20/2025 7/26/2025 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

Security Access Control (71130.02), Security Plan Changes (71130.09), Security PIV (71151)

1,2 7/7/2025 7/10/2025 IP 71130.02 000734 Access Control 1,2 7/7/2025 7/10/2025 IP 71130.09 001656 Security Plan Changes 1,2 7/7/2025 7/10/2025 IP 71151 001338 Performance Indicator Verification Cybersecurity - DC

1,2 8/10/2025 8/16/2025 IP 71130.10 000741 Cybersecurity EP 2025 Program Inspection - DC

1,2 8/25/2025 8/29/2025 IP 71114.02 000717 Alert and Notification System Testing 1,2 8/25/2025 8/29/2025 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 8/25/2025 8/29/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 8/25/2025 8/29/2025 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 8/25/2025 8/29/2025 IP 71151 001397 Performance Indicator Verification Inservice Inspection-DC (U2)

2 10/6/2025 10/17/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

DC 2025 INITIAL EXAM

1,2 9/14/2025 9/20/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 10/26/2025 11/8/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

RP 5,8 - DC

1,2 3/2/2026 3/6/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation 1,2 3/2/2026 3/6/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Diablo Canyon 2026 PI&R

1,2 5/4/2026 5/8/2026 IP 71152B 000747 Problem Identification and Resolution 1,2 5/11/2026 5/22/2026 IP 71152B 000747 Problem Identification and Resolution Security 71130.02/.04/.05

1,2 6/8/2026 6/11/2026 IP 71130.02 000734 Access Control 1,2 6/8/2026 6/11/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1,2 6/8/2026 6/11/2026 IP 71130.05 000737 Protective Strategy Evaluation 1,2 6/8/2026 6/11/2026 IP 71130.09 001656 Security Plan Changes 1,2 6/8/2026 6/10/2026 IP 71130.14 000743 Review of Power Reactor Target Sets 1,2 6/8/2026 6/11/2026 IP 71151 001338 Performance Indicator Verification Prepared on 8/13/2025 1:27:32 PM 1 of 3

Site Inspection Activity Plan Comprehensive Engineering Team Inspection - Diablo Canyon

1,2 7/13/2026 7/17/2026 IP 71111.21M 000713 Comprehensive Engineering Team Inspection 1,2 7/27/2026 7/31/2026 IP 71111.21M 000713 Comprehensive Engineering Team Inspection MC&A - DC

1,2 8/17/2026 8/21/2026 IP 71130.11 000742 Material Control and Accounting (MC&A)

EP Exercise & PI Inspection (2026) - DC

1,2 8/31/2026 9/4/2026 IP 71114.01 000716 Exercise Evaluation 1,2 8/31/2026 9/4/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 8/31/2026 9/4/2026 IP 71151 001397 Performance Indicator Verification Inservice Inspection - DC (U1)

1 10/19/2026 10/30/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,3,PI - DC

1,2 10/19/2026 10/23/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 10/19/2026 10/23/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 10/19/2026 10/23/2026 IP 71151 000746 Performance Indicator Verification DC 2027 BRQ

1,2 2/28/2027 3/6/2027 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance DC 2027 INITIAL EXAM

1,2 2/21/2027 2/27/2027 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 4/11/2027 4/17/2027 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Inservice Inspection-DC (U2)

2 4/26/2027 5/8/2027 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,4,PI - DC

1,2 4/26/2027 4/30/2027 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 4/26/2027 4/30/2027 IP 71124.04 000728 Occupational Dose Assessment 1,2 4/26/2027 4/30/2027 IP 71151 000746 Performance Indicator Verification Focused Engineering Inspection 1 - DC

1,2 6/7/2027 6/11/2027 IP 71111.21N 000714 Focused Engineering Inspections (FEI Placeholder)

1,2 6/21/2027 6/25/2027 IP 71111.21N 000714 Focused Engineering Inspections (FEI Placeholder)

Prepared on 8/13/2025 1:27:32 PM 2 of 3

Site Inspection Activity Plan Diablo Canyon 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Diablo Canyon ISFSI Aging Management Inspection during canister baseline (one-week, TBD)

6/1/2026 8/31/2026 IP 60859 001921 Independent Spent Fuel Storage Installation (ISFSI) License Renewal Inspection Prepared on 8/13/2025 1:27:32 PM 3 of 3