Operator Licensing Written Examination Approval 05000259-10-301, 05000260-10-301 and 05000296-10-301
ML110330552
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 02/02/2011
From: Widmann M
NRC/RGN-II/DRS/OLB
To: Morris J
Tennessee Valley Authority
References
IR-11-301
Download: ML110330552 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION ary 2, 2011

SUBJECT:

BROWNS FERRY NUCLEAR POWER PLANT - OPERATOR LICENSING WRITTEN EXAMINATION APPROVAL 05000259/2011301, 05000260/2011301 AND 05000296/2011301

Dear Mr. Morris:

The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Browns Ferry Nuclear Power Plant.

The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to your office. The NRC staff will administer the operating tests to individuals, as applicable, during the weeks of February 7, 2011, and February 14, 2011. Note that any examination waivers and application denials have been addressed in separate correspondence.

The NRC has approved the subject written examination and hereby authorizes you to administer the written examination in accordance with Revision 9, Supplement 1, of NUREG-1021, Operator Licensing Examination Standards for Power Reactors, on February 18, 2011.

This examination has undergone extensive review by my staff and representatives responsible for operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operators at your facility.

Please contact the Chief Examiner, Mr. Ronald F. Aiello, at (404) 997-4641 if you have any questions or identify any errors or changes in license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant on the list of approved applicants.

Sincerely,

/RA/

Malcolm T. Widmann, Chief Operations Branch

SUBJECT:

BROWNS FERRY NUCLEAR POWER PLANT - OPERATOR LICENSING WRITTEN EXAMINATION APPROVAL 05000259/2011301, 05000260/2011301 AND 05000296/2011301

Dear Mr. Morris:

The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Browns Ferry Nuclear Power Plant.

The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to your office. The NRC staff will administer the operating tests to individuals, as applicable, during the weeks of February 7, 2011, and February 14, 2011. Note that any examination waivers and application denials have been addressed in separate correspondence.

The NRC has approved the subject written examination and hereby authorizes you to administer the written examination in accordance with Revision 9, Supplement 1, of NUREG-1021, Operator Licensing Examination Standards for Power Reactors, on February 18, 2011.

This examination has undergone extensive review by my staff and representatives responsible for operator training at your facility. Based on this review I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines, and is appropriate for measuring the qualifications of licensed operators at your facility.

Please contact the Chief Examiner, Mr. Ronald F. Aiello, at (404) 997-4641 if you have any questions or identify any errors or changes in license level (RO or SRO) or type of examination (partial or complete written examination and/or operating test) specified for each applicant on the list of approved applicants.

Sincerely,

/RA/

Malcolm T. Widmann, Chief Operations Branch Division of Reactor Safety Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68 X PUBLICLY AVAILABLE G NON-PUBLICLY AVAILABLE G SENSITIVE X NON-SENSITIVE ADAMS: Yes ACCESSION NUMBER:ML110330552 X SUNSI REVIEW COMPLETE OFFICE RII:DRS RII:DRS SIGNATURE RFA WTM NAME RAIELLO MWIDMANN DATE 2/2/11 2/2/11 2/ /2011 2/ /2011 2/ /2011 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO