October 11, 2018

SUBJECT:

INDIAN POINT NUCLEAR GENERATING - EVALUATED EMERGENCY PREPAREDNESS EXERCISE INSPECTION REPORT 05000247/2018501 AND 05000286/2018501

Dear Mr. Vitale:

On September 27, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Indian Point Nuclear Generating, Units 2 and 3. The NRC inspectors discussed the results of this inspection with Mr. John Ferrick, General Manager of Plant Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Raymond R. McKinley, Chief Plant Support Branch Division of Reactor Safety

Docket Numbers: 50-247 and 50-286 License Numbers: DPR-26 and DPR-64

Enclosure:

Inspection Report 05000247/2018501 and 05000286/2018501

Inspection Report

Docket Numbers:

50-247 and 50-286

License Numbers:

DPR-26 and DPR-64

Report Numbers:

05000247/2018501 and 05000286/2018501

Enterprise Identifier: I-2018-501-0036

Licensee:

Entergy Nuclear Northeast (Entergy)

Facility:

Indian Point Nuclear Generating, Units 2 and 3

Location:

450 Broadway, General Services Building

Buchanan, NY 10511-0249

Inspection Dates:

September 24 - September 27, 2018

Inspectors:

J. Ambrosini, Senior Emergency Preparedness Inspector, Division of Reactor

Safety (DRS)

J. DeBoer, Emergency Preparedness Inspector, DRS

B. Haagensen, Senior Resident Inspector, Division of Reactor Projects (DRP)

L. McKown, Resident Inspector, DRP

P. Ott, Operations Engineer, DRS

Approved By:

Raymond R. McKinley, Chief

Plant Support Branch

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergys performance at Indian Point Nuclear Generating, Units 2 and 3, by conducting an evaluated emergency preparedness exercise inspection in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

No findings or more-than-minor violations were identified.

INSPECTION SCOPE

The inspectors conducted the inspection using the appropriate portions of the inspection procedure in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection procedures with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. The inspectors determined the following samples were complete when the inspection procedure requirements were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

REACTOR SAFETY

71114.01 - Exercise Evaluation (1 sample)

The inspectors evaluated the adequacy of Entergys conduct of the exercise and its capability to assess staff performance via a formal critique process, as required by Title 10 of the Code of Federal Regulations (10 CFR) 50.47(b)(14).

71114.08 - Exercise Evaluation - Scenario Review (1 sample)

The inspectors reviewed and evaluated the proposed scenario for biennial emergency plan exercise on August 24.

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicator submittals listed below for the period from April 2017 through June 2018.

(1) Drill and Exercise Performance
(2) Emergency Response Organization Drill Participation
(3) Alert and Notification System

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On September 27, the inspectors presented the inspection results to Mr. John Ferrick, General Manager of Plant Operations, and other members of the Indian Point staff.

DOCUMENTS REVIEWED

71114.01: Exercise Evaluation

Indian Point Emergency Preparedness Plan

Indian Point Emergency Preparedness Plan Implementing Procedures

Indian Point September 25, 2018 Evaluated Exercise Scenario Package

Indian Point Drill Reports 2016-2018

Condition Reports

CR-IP2-2018-05350

CR-IP2-2018-05351

CR-IP2-2018-05352

CR-IP2-2018-05353

CR-IP2-2018-05354

CR-IP2-2018-05355

CR-IP2-2018-05356

CR-IP2-2018-05357

CR-IP2-2018-05358

CR-IP2-2018-05363

CR-IP2-2018-05365

CR-IP2-2018-05369

CR-IP2-2018-05370

CR-IP2-2018-05371

CR-IP2-2018-05373

CR-IP2-2018-05374

CR-HQN-2018-02125

71114.08: Exercise Evaluation - Scenario Review

Indian Point Emergency Preparedness Plan

Indian Point Emergency Preparedness Plan Implementing Procedures

Indian Point September 25, 2018 Evaluated Exercise Scenario Package

Indian Point Drill Reports 2016-2018

71151: Performance Indicator (PI) Verification

DEP PI data, April 2017 - June 2018

ERO Drill Participation PI data, April 2017 - June 2018

ANS Reliability PI data, April 2017 - June 2018