GO2-94-008, Monthly Operating Rept for Dec 1993 for WNP-2

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Dec 1993 for WNP-2
ML17290A889
Person / Time
Site: Columbia 
Issue date: 12/31/1993
From: Embree D, Parrish J
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-94-008, GO2-94-8, NUDOCS 9401240227
Download: ML17290A889 (6)


Text

~ ACCELERATED D~~UTION DEMONS~TION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

DOCKET I FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH.NAME AUTHOR AFFILIATION EMBREE,D.G.

Washington Public Power Supply System PARRISH,J.V.

Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept for Dec 1993 for WNP-2.

DISTRIBUTION CODE:

IE24D COPIES RECEIVED:LTR ENCL TITLE: Monthly Operating Report (per Tech Specs)

NOTES'0110 tr.

SIZE D

RECIPIENT ID CODE/NAME PDV PD INTERNAL: ACRS AEOD/DSP/TPAB NRR/DRIL/RPEB RGN5 EXTERNAL EG&G BRYCE IJ

~ H NSIC COPIES LTTR ENCL 1

1 10 10 1

1 1

1 1

1 1

1 1

1 RECIPIENT ID CODE/NAME CLIFFORD,J AEOD/DOA RR/DORS/OEAB REG FI 01 NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

1 D

D R

D NOTE TO ALL"RIDS" RECIPIENTS:

A D

D PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 21 ENCL 21

  • I

WASHINGTONPUBLIC POWER SUPPLY SYSTEM P.O. Bm 968 ~ 3000 George Washtngton Way ~ Rtchland, Washtngton 993524968

~ (509) 372-5000 January 10, 1994 GOS"94"008 Docket No. 50-397 U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555

Dear Sirs:

Subject:

NUCLEAR PLANT NO. 2 MONTHLYOPERATING REPORT,

., DECEMBER 1993

'l Transmitted herewith is the Monthly Operating Report for the month of December, 1993 as required by our Technical Specifications 6,9.1.6.

Sincerely,

. V.

A sis Man w v'r ging Director, Operations (MD 1023)

JVP:DGE CC:

Mr. W,H, Lovelace, NRC, Washington, DC Mr. B.H. Faulkenburry, NRC Region V Mr. R.C. Barr, NRC Resident Inspector (901A)

Ms. D. Sherman, ANILibrary Mr. J.T. Wheelock, INPO Mr. C. Bergesen, UtilityData Institute Mr. J.T. Irish, BPA (399) 940i240227 93i23i

',RDR, ADOCK.05000397

, "R,,';i,.

~,

PDR 4~9 V a-6--

jl li lf

OPERATING STATUS REPORT for WNP-2 Date:

January 1, 1994 2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

Docket:

50-397 Reporting Period:

DECEMBER 1993 Outage + On-Line Hours:

744.0 UtilityContact:

David G. Embree (509) 377-8448 Licensed Thermal Power (MW, ):

3323 Nameplate Rating (Gross MW, ):

1200.9 Design Electrical Rating (Net MW,):

1120 Maximum Dependable Capacity (Gross MW,):

1132*

Maximum Dependable Capacity (Net MW, ):

1086*

Ifchanges occur above since last report, give reasons:

  • Re-calculated MDC for most restrictive month due to environmental effects, back to Jan.

1, 1993.

Power to which restricted, ifany (Net MW,):

n/a Reasons for restrictions, ifany:

n/a 12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

24.

25.

Report Period Hours Hours Reactor Critical Rx Reserve Shutdown Hours Hours Generator On-Line Unit Reserve Shutdown Hours Gross Thermal Energy (MV6Q Gross Electrical Energy (MWH)

Net Electrical Energy (MWH)

Unit Service Factor Unit AvailabilityFactor Unit Capacity Factor (MDC Net)

Unit Capacity Factor (DER Net)

Unit Forced Outage Rate Forced Outage Hours MONTH 744.0, 744.0 0.0 744.0 0.0 2,461,177 858,560 826,914 100.0%

100.0%

102.3%

99.2%

0.0%

0.0 YEAR 8,760.0 6,961.5 0.0 6,759.3 0.0 21,596,656 7,463,120 7,134,966 77.2%

77.2%

75.0%

72.7%

8.3%

612.0 CUMULATIVE 79,328.2 56,110.2 340.4 54,067.0 381.7 158,761,306 53,312,210 51,085,385 68.2%

68.6%

58.9%

58.5%

12.7%

7,885.3 26.

27.

Shutdowns scheduled over the next 6 months (type, date, duration):

Refueling Outage, April 15, 1994, 60 Days.

Ifcurrently shutdown estimated startup date:

n/a Note:

n Cumualtive Unit Capacity Factors (MDC &DER) are calculated with weighted averages.

AVERAGE DAILY UNIT POWER 'LEVEL REPORT PERIOD:

DECEMBER 1993 DOCKET NO.:

50-397 UNIT:

WNP-2 DATE:

January 1, 1994 COMPLETED BY:

D. G. Embree TELEPHONE:

(509) 377-8448 DAY AVERAGE DAILYPOWER LEVEL (Net MWe)

AVERAGE DAILYPOWER LEVEL DAY (Net MWe) 8 10 12 13 14 15 1114 1105 1000 1119 1120 1119 1115 1110 1100 1112 1115 1117 1116 1117 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1120 1116 1120 1119 1117 1117 1115 1116 1116 1120 1120 1119 1119 1118 1118 1048 INSTRUCTIONS On this form, list the average daily unit power level in MWe (net) for each day in the reporting month.

Compute to the nearest whole megawatt.

These figures willbe used to plot a graph for each reporting month.

Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100Fo line (or th'e restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

UNIT SHVIDOWNS AND POWER REDUCTIONS REPORT PERIOD:

DECEMBER 1993 DOCKET NOat 50-397 UNIT NAME:

WNP-2 DATE:

January 1, 1994 COMPLETED BY:

D.G. Embree TELEPHONE:

(509) 377-8448 No.

Date Type Hours Reason Method LER Number System Component Cause and Corrective Action To Prevent Recurrence NONE SUIKVCARY:

WNP-2 operated near full power during the month with no outages or significant power reductions ()20%).

TYPE F - Forced S - Scheduled REASON A - Equipment Failure B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training &

License Examination F - Administration G - Operational Error H - Other METHOD 1 - Manual 2 - Manual Scram 3 - Auto Scram 4 - Continued 5 - Reduced Load 9 - Other SYSTEM & COMPONENT NUREG-0161 Exhibits F &H