|
---|
Category:Letter type:GNRO
MONTHYEARGNRO-2013/00079, 2013-10-13 (GNRO-2013-00079) Response to RAI Set 49 (Dated Sep-12-2013)2023-10-11011 October 2023 2013-10-13 (GNRO-2013-00079) Response to RAI Set 49 (Dated Sep-12-2013) GNRO-2023/00015, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-06-0606 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors GNRO-2023/00014, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0606 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b GNRO-2021/00037, 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 12021-11-30030 November 2021 2021 Annual Report of Changes and Errors to 10 CFR 50.46 Analysis Grand Gulf Nuclear Station, Unit 1 GNRO-2021/00017, Notification of Readiness for Supplemental Inspection2021-06-22022 June 2021 Notification of Readiness for Supplemental Inspection GNRO-2021/00014, Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency2021-06-0101 June 2021 Inservice Testing Program Relief Request VRR-GGNS-2021-1 Pressure Isolation Valve Testing Frequency GNRO-2021/00015, Annual Radioactive Effluent Release Report2021-04-28028 April 2021 Annual Radioactive Effluent Release Report GNRO-2021/00011, Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 20202021-04-19019 April 2021 Revision of Original Report of 10CFR50.59 and Commitments Change Evaluations - July 1, 2018 Through May 21, 2020 GNRO-2021/00012, Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.22062021-04-13013 April 2021 Annual Report of Individual Monitoring - NRC Form 5 for 2020 Per 10 CFR 20.2206 GNRO-2020/00045, 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis2020-12-16016 December 2020 2020 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2020/00034, Notification of Spent Fuel Cask Use2020-10-0808 October 2020 Notification of Spent Fuel Cask Use GNRO-2020/00033, Response to NRC Integrated Inspection Report 05000416/20200022020-09-10010 September 2020 Response to NRC Integrated Inspection Report 05000416/2020002 GNRO-2020/00029, Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 20202020-08-18018 August 2020 Report of 10 CFR 72.48 Evaluations July 1, 2018 Through June 30, 2020 GNRO-2020/00022, Report of Technical Specification Bases Changes2020-07-21021 July 2020 Report of Technical Specification Bases Changes GNRO-2020/00027, Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-07-16016 July 2020 Core Operating Limits Report (COLR) Cycle 23 Revision 1 for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00023, Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-06-26026 June 2020 Response to Request for Additional Information - License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2020/00020, Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS)2020-05-0505 May 2020 Core Operating Limits Report (COLR) Cycle 23, and Pressure and Temperature Limits Report (PTLR) Update for Grand Gulf Nuclear Station, Unit 1 (GGNS) GNRO-2020/00018, Annual Radiological Effluent Release Report2020-04-30030 April 2020 Annual Radiological Effluent Release Report GNRO-2020/00016, Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.22062020-04-16016 April 2020 Annual Report of Individual Monitoring -NRC Form 5 for 2019 Per 10 CFR 20.2206 GNRO-2020/00015, Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test2020-04-0707 April 2020 Response to Request for Additional Information - License Amendment Request for One-Cycle Extension of Appendix J Type a Integrated Leakage Rate Test and Drywell Bypass Leakage Rate Test GNRO-2020/00007, Spent Fuel Storage Radioactive Effluent Release Report for 20192020-02-20020 February 2020 Spent Fuel Storage Radioactive Effluent Release Report for 2019 GNRO-2020/00006, License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies2020-02-19019 February 2020 License Amendment Request for Permanent Extension of Appendix J Type a Integrated Leakage Rate Test Frequencies GNRO-2019/00052, Report of Changes and Errors to 10 CFR 50.46 Analysis2019-12-13013 December 2019 Report of Changes and Errors to 10 CFR 50.46 Analysis GNRO-2019/00051, Notification of Readiness of 92723 Inspection2019-12-11011 December 2019 Notification of Readiness of 92723 Inspection GNRO-2019/00045, Emergency Plan, Revision 792019-10-29029 October 2019 Emergency Plan, Revision 79 GNRO-2019/00037, Notification of Spent Fuel Cask Use2019-09-20020 September 2019 Notification of Spent Fuel Cask Use GNRO-2019/00036, Correction to Gnro 2019-00017 Emergency Plan Revision 782019-08-0808 August 2019 Correction to Gnro 2019-00017 Emergency Plan Revision 78 GNRO-2019/00027, Notification of Readiness of 95001 Supplemental Inspections2019-07-0303 July 2019 Notification of Readiness of 95001 Supplemental Inspections GNRO-2019/00031, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report2019-06-25025 June 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 - Corrected Report GNRO-2019/00028, Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation.2019-06-13013 June 2019 Supplement to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation. GNRO-2019/00026, Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval2019-05-0606 May 2019 Response to Requests for Additional Information Regarding Relief Request Number GG-ISI-023, Inservice Inspection Impracticality - Limited Coverage Examinations During the Third 10-Year Inservice Inspection Interval GNRO-2019/00020, Annual Radiological Operating Report (AREOR)2019-04-30030 April 2019 Annual Radiological Operating Report (AREOR) GNRO-2019/00024, Annual Radioactive Effluent Release Report2019-04-30030 April 2019 Annual Radioactive Effluent Release Report GNRO-2019/00022, Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.22062019-04-22022 April 2019 Annual Report of Individual Monitoring - NRC Form 5 for 2018 Per 10 CFR 20.2206 GNRO-2019/00017, Emergency Plan, Revision 782019-03-14014 March 2019 Emergency Plan, Revision 78 GNRO-2019/00014, Snubber Testing Program for Fourth Inspection Interval2019-03-13013 March 2019 Snubber Testing Program for Fourth Inspection Interval GNRO-2019/00012, Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program2019-03-0606 March 2019 Internal Events Probabilistic Risk Assessment (PRA) Sensitivity Study Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program GNRO-2019/00016, Spent Fuel Storage Radioactive Effluent Release Report for 20182019-02-21021 February 2019 Spent Fuel Storage Radioactive Effluent Release Report for 2018 GNRO-2019/00003, Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation2019-01-23023 January 2019 Application to Revise Technical Specification (TS) 3.3.1.1, Reactor Protection System (RPS) Instrumentation, and TS 3.3.4.1, End of Cycle Recirculation Pump Trip (EOC-RPT) Instrumentation GNRO-2018/00057, Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan2018-12-0404 December 2018 Submittal of Revision 17 to the Grand Gulf Nuclear Station Physical Security, Safeguards Contingency, and Training and Qualification Plan GNRO-2018/00054, Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval2018-11-30030 November 2018 Relief Request No. GG-ISI-023, Inservice Inspection Impracticality: Limited Coverage Examination During the Third 10-Year Inservice Inspection Interval GNRO-2018/00055, Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ...2018-11-30030 November 2018 Response to Request for Additional Information for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a ... GNRO-2018/00052, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information2018-10-24024 October 2018 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Into Licensing Basis - Partial Response to Request for Additional Information and Extension of Response to Request for Additional Information GNRO-2018/00051, Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-10-23023 October 2018 Supplement to Revise Technical Specifications to Adopt Technical Specification Task Force Traveler TSTF-542, Reactor Pressure Vessel Water Inventory Control GNRO-2018/00047, Submittal of 2018 Inservice Inspection Summary Report2018-10-16016 October 2018 Submittal of 2018 Inservice Inspection Summary Report GNRO-2018/00046, Submittal of 2018 Report of Changes and Errors to 10CFR50.462018-10-16016 October 2018 Submittal of 2018 Report of Changes and Errors to 10CFR50.46 GNRO-2018/00048, Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 62018-10-10010 October 2018 Response to Request for Additional Information License Amendment Request, Adoption of Emergency Action Level Scheme Pursuant to NEI 99-01, Revision 6 GNRO-2018/00042, Core Operating Limits Report Cycle 22, Revision 12018-09-18018 September 2018 Core Operating Limits Report Cycle 22, Revision 1 GNRO-2018/00043, Revised Offsite Dose Calculation Manual2018-09-18018 September 2018 Revised Offsite Dose Calculation Manual GNRO-2018/00039, Report of Technical Specification Bases Changes2018-08-20020 August 2018 Report of Technical Specification Bases Changes 2023-06-06
[Table view] |
Text
Entergy Operations, Inc.
P.o. Box 756 Port Gibson, Mississippi 39150 David Ellis Acting - Regulatory Assurance Manager Grand Gulf Nuclear Station Tel: 601-437-2489 GNRO-2017/00049 July 17, 2017 u.s. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
SUBJECT:
NRC Form 536 Response to Regulatory Issue Summary 2017-03 Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29
Dear Sir or Madam:
Entergy Operations, Inc. in accordance with NRC Regulatory Issue Summary (RIS) 2017-03, "Preparation and Scheduling of Operator Licensing Examinations," is submitting NRC Form 536, "Operator Licensing Examination Data," to provide the estimated number of candidates to be examined during calendar years 2019 through 2022.
The updated information for Grand Gulf Nuclear Station is provided in the attached NRC Form 536. This information represents the best estimate currently available. This is a revision of GNRO 2017/00041 NRC Form 536 per discussion and request of NRC Region IV Chief, Operations Branch.
No Initial License examinations are scheduled for 2018 and there are no new commitments contained in this submittal.
If you have any questions or require additional information regarding this matter, please contact Mike Rasch at 601-437-2255.
Attachment:
NRC Form 536 "Operator Licensing Examination Data" cc: (See Next Page)
GNRO-2017/00049 Page 2 of 2 cc: NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission ATTN: Ms. Jennifer Bridges 1600 East Lamar Boulevard Arlington, TX 76011-4511 Mr. Vincent Gaddy Chief, Operations Branch U.S. Nuclear Regulatory Commission 1600 East Lamar Boulevard Arlington, TX 76011-4511
NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2017 (05-2016)
.. ~AR[QIJ( Estimated burden perresponse to comply withthisvoluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This
~r;; " >>. information collection is used to plan budgets and resources for operator examinations. Send
~
- 00p
. ~ OPERATOR LICENSING 10 0
II:
comments regarding burden estimate to the FOIA, Privacy, and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC20555-0001, or bye-mail to
~ ; EXAMINATION DATA Infocoliects.Resource@nrc.gov, and to the Desk Officer, Office of Information andRegulatory Affairs,
+"
....... ., ~o NEOB-10202, (3150-0131), Office of Management andBUdget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC maynotconduct or sponsor, anda person is notrequired to respond to,theinformation collection.
FACILITY NRC REGION GRAND GULF NUCLEAR STATION Docket # 50-416 IV L
A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2019 CY2020 CY 2021 CY2022 ESTIMATED NUMBER OF LICENSEE-PREPARED 0 2 1 0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 0 0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2019 CY2020 CY 2021 CY2022 NUMBER OF REACTOR OPERATORS 0 3/3 9 0 NUMBER OF SENIOR REACTOR OPERATORS -INSTANT 0 10/10 3 0 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 0 3/3 3 0 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 0 0 0 PROPOSED DATES PRIMARY DATE 1/27/20 & 5/4/20 11/29/21 ALTERNATE DATE 2/10/20 & 5/11/20 12/4/21 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2019 CY 2020 PROPOSED NUMBER MARCH SEPTEMBER MARCH SEPTEMBER ESTIMATED NUMBER OF 0 0 12 0 CANDIDATES NRC FORM536 (05-2016)