ENS 55328
ENS Event | |
---|---|
04:00 Jun 24, 2021 | |
Title | 10 Cfr 50.55(E) Report Regarding Electrical Construction and Measuring and Test Equipment Control |
Event Description | The following is a synopsis of information received via E-mail:
The individual informing the Commission is Michael J. Yox, 7825 River Road, Waynesboro, GA 30830. The activities which fail to comply include construction processes including, installation of some electrical and mechanical commodities, and control of measuring and test equipment at the Vogtle 3 and 4 construction project. The primary construction firm for the Vogtle 3 and 4 construction project is Bechtel Power Corporation (Bechtel). This report is being provided based on construction nonconformances including, installation of some electrical and mechanical commodities, and control of measuring and test equipment for Vogtle Units 3 and 4. The nonconformances affect cable separation and other raceway structural elements. The extent of condition for the measuring and test equipment issue is under evaluation and may impact additional safety-related work. The identified construction nonconformances are a small fraction of the overall structures and components. There is no specifically identified substantial safety hazard (SSH) for these nonconformances. The nonconformances identified affect some safety-related components and based on this it was conservatively judged that the issues could be related to an SSH. These issues were discovered while the facility is under construction. The identified conditions will be corrected prior to completion of the facility. The evaluation for this report was completed on June 24, 2021. As stated above, there are no specifically identified basic components that have been identified to contain a defect for Vogtle Units 3 and 4. The nonconformances identified affect some safety-related components and based on this it was conservatively judged that these conditions involve a failure to comply that could be related to an SSH. The corrective action which has been, is being, or will be taken include: Comprehensive extent-of-condition reviews and correction of identified conditions are being conducted. The actions to identify and resolve the nonconforming conditions are in process and will be completed in accordance with the site corrective action program. Bechtel, and other subcontractors as needed, will implement actions to correct the identified conditions and ensure that processes are in place to avoid future occurrences. Southern Nuclear Operating Company (SNC) is the organization responsible for ensuring Bechtel and the other subcontractors complete the required actions to correct the nonconforming conditions and ensuring that processes are in place to avoid future occurrences. |
Where | |
---|---|
Vogtle Georgia (NRC Region 2) | |
Reporting | |
10 CFR 50.55(e) | |
Time - Person (Reporting Time:+35.45 h1.477 days <br />0.211 weeks <br />0.0486 months <br />) | |
Opened: | Michael Yox 15:27 Jun 25, 2021 |
NRC Officer: | Donald Norwood |
Last Updated: | Jun 25, 2021 |
55328 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 55328\u003C/a\u003E - \u003Ca href=\"/Vogtle\" title=\"Vogtle\"\u003EVogtle\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E10 Cfr 50.55(E) Report Regarding Electrical Construction and Measuring and Test Equipment Control\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 55328 - Vogtle\n","link":"","lat":33.13062222222222,"lon":-81.77135277777778,"icon":"/w/images/1/14/Southern_Nuclear_icon.png"}],"imageoverlays":null} | |
Unit 3 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Under Construction (0 %) |
After | Under Construction (0 %) |
Unit 4 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Under Construction (0 %) |
After | Under Construction (0 %) |
WEEKMONTHYEARENS 553282021-06-24T04:00:00024 June 2021 04:00:00
[Table view]10 CFR 50.55(e) 10 Cfr 50.55(E) Report Regarding Electrical Construction and Measuring and Test Equipment Control ENS 507982014-08-25T13:00:00025 August 2014 13:00:00 10 CFR 50.55(e) Breakdown in the Quality Assurance Program for Vogtle 3&4 Construction Project ENS 504412014-03-13T12:00:00013 March 2014 12:00:00 10 CFR 50.55(e) Welding Program Deviations During Construction ENS 495952013-09-24T13:00:00024 September 2013 13:00:00 10 CFR 50.55(e) Deficiency Identified in Quality Assurance Program ENS 489062012-12-06T12:00:0006 December 2012 12:00:00 10 CFR 50.55(e) Failure to Comply with Conditions of Construction Permit 2021-06-24T04:00:00 | |