08:13 Mar 9, 2021 | |
| Title | |
| Event Description | At 0313 EST on March 9th, 2021, during performance of Unit 1 High Pressure Coolant Injection (HPCI) valve exercising, the inboard vacuum breaker isolation valve did not stroke closed as expected, but remained mid-position. The affected penetration of primary containment was isolated by closing the outboard HPCI vacuum breaker isolation valve. This results in an unplanned inoperability of the Unit 1 HPCI system.
This is being reported as a loss of an entire safety function condition in accordance with 10CFR50.72(b)(3)(v)(D). The licensee notified the NRC Resident Inspector. Unit 1 is in a 14-day LCO for Tech Spec 3.5.1(d), HPCI inoperability. Tech Spec 3.6.1.3(a), Containment Penetration Valve, was completed with closing the outboard HPCI vacuum breaker isolation valve. The Units are in a normal offsite power line-up. |
| Where | |
|---|---|
| Susquehanna Pennsylvania (NRC Region 1) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
| LER: | 05000387/LER-2021-001 Electri Station Unplanned Lnoperability of the High Pressure Coolant Injection (HPCI) System Due to a Primary Containment Isolation (PCIV) Valve Failure to Stroke Full Closed On-demand Due to an Intermittent Break |
| Time - Person (Reporting Time:+-0.08 h-0.00333 days <br />-4.761905e-4 weeks <br />-1.09584e-4 months <br />) | |
| Opened: | Darvin Duttry 08:08 Mar 9, 2021 |
| NRC Officer: | Bethany Cecere |
| Last Updated: | Mar 9, 2021 |
| 55128 - NRC Website
Loading map... | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |