ENS 53579
From kanterella
Jump to navigation
Jump to search
ENS Event | |
---|---|
04:00 Sep 3, 2018 | |
Title | Automatic Start of the Emergency Diesel Generator |
Event Description | At 1045 [EDT] on 9/3/18, with Unit 1 and Unit 2 at 100% power, off-site power feed to the 'A' Reserve Station Transformer was lost which resulted in a loss of power to Unit 1'J' Emergency Bus. As a result of the power loss, the 1'J' Emergency Diesel Generator started as designed and restored power to the Emergency Bus. During this event, the Unit 1 'A' Charging Pump, 1-CH-P-1A automatically started as designed due to the loss of power event.
The valid actuation of these ESF [Engineered Safety Features] components due to the loss of power is reportable per 10 CFR 50.72 (b)(3)(iv)(A). The Unit 1 'J' Emergency bus off-site power source was restored via the Unit 2 'B' Station Service bus and the 1 'J' Emergency Diesel was secured and returned to Automatic. The Unit 1 'A' Charging pump has been stopped and returned to Automatic. Both Units are in a stable condition. The apparent cause for the loss of power appears to be a bird strike to the 'A' RSST [Reserve Station Service Transformer] Overhead Cable. The licensee notified the NRC Resident Inspector. |
Where | |
---|---|
North Anna Virginia (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+11.33 h0.472 days <br />0.0674 weeks <br />0.0155 months <br />) | |
Opened: | David Mosser 15:20 Sep 3, 2018 |
NRC Officer: | Dong Park |
Last Updated: | Sep 3, 2018 |
53579 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 53579\u003C/a\u003E - \u003Ca href=\"/North_Anna\" title=\"North Anna\"\u003ENorth Anna\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EAutomatic Start of the Emergency Diesel Generator\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 53579 - North Anna\n","link":"","lat":38.06055555555555,"lon":-77.78944444444444,"icon":"/w/images/b/b0/Dominion_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |
WEEKMONTHYEARENS 571482024-05-29T10:24:00029 May 2024 10:24:00
[Table view]10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip ENS 558432022-04-14T13:28:00014 April 2022 13:28:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip During Control Rod Testing ENS 535792018-09-03T04:00:0003 September 2018 04:00:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Start of the Emergency Diesel Generator ENS 518922016-04-30T02:14:00030 April 2016 02:14:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Loss of Offsite Power to the a Reserve Station Service Transformer ENS 516782016-01-23T22:03:00023 January 2016 22:03:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Partial Loss of Power Results in Emergency Diesel Generators Starting ENS 509462015-04-02T08:26:0002 April 2015 08:26:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Main Generator Voltage Regulator Failure ENS 508512015-02-26T20:11:00026 February 2015 20:11:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Feedwater Regulating Valve Failing Closed ENS 501162014-05-15T23:20:00015 May 2014 23:20:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unit 1 and Unit 2 Emergency Diesel Generators Start and Load Due to Loss of One 34.5Kv Line ENS 497842014-02-02T13:59:0002 February 2014 13:59:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Following Loss of the "a" Main Feedwater Pump ENS 494292013-10-11T17:17:00011 October 2013 17:17:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Turbine and Reactor Trip Due to Station Service Transformer Lockout ENS 490752013-05-28T19:07:00028 May 2013 19:07:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to a Feedwater Transient ENS 490202013-05-10T10:12:00010 May 2013 10:12:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to High Turbine Bearing Vibration ENS 484362012-10-24T05:47:00024 October 2012 05:47:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip on Low Steam Generator Water Level ENS 460202010-06-16T23:20:00016 June 2010 23:20:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to a Lightning Storm ENS 459602010-05-28T04:03:00028 May 2010 04:03:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Loss of Reactor Coolant Pump ENS 458772010-04-27T20:37:00027 April 2010 20:37:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Reactor Trip Following a Generator Lockout During Automatic Voltage Regulator Testing ENS 455562009-12-09T19:23:0009 December 2009 19:23:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip on Unit 2 and Edg Start on Both Units Due to Inadvertent Loss of "C" Reserve Station Service Transformer ENS 450262009-04-28T13:53:00028 April 2009 13:53:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Emergency Diesel Auto-Start Due to Loss of the "B" Reserve Station Service Transformer ENS 439722008-02-08T23:12:0008 February 2008 23:12:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Control Rod Position Deviation ENS 438662007-12-26T02:10:00026 December 2007 02:10:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Trip of "B" Reactor Coolant Pump ENS 434622007-06-29T21:52:00029 June 2007 21:52:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation, 10 CFR 50.72(b)(2)(iv)(A), System Actuation - ECCS Discharge Reactor Trip and Spurious Safety Injection ENS 432172007-03-07T08:05:0007 March 2007 08:05:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Emergency Diesel Generator Autostart on Loss of "B" Reserve Station Service Transformer ENS 430722007-01-03T23:03:0003 January 2007 23:03:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to a Card Failure ENS 429962006-11-16T07:26:00016 November 2006 07:26:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Reactor Trip ENS 424832006-04-08T02:31:0008 April 2006 02:31:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Group Step Counter Failure During Reactor Startup ENS 418982005-08-06T02:28:0006 August 2005 02:28:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Apparently Due to Lightning Strike ENS 408042004-06-10T17:13:00010 June 2004 17:13:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip While Performing Scheduled Solid State Protection Testing ENS 407842004-05-29T06:02:00029 May 2004 06:02:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Control Rod Position Indication Failure During Hot Rod Drop Test 2024-05-29T10:24:00 | |