ENS 51075
ENS Event | |
---|---|
05:00 Mar 18, 2015 | |
Title | |
Event Description | MEASURING AND TEST EQUIPMENT DEFICIENCIES
The following information was received by facsimile: This report is being provided as an interim report in accordance with 10CFR 21.21. (i) Name and address of the individual or individuals informing the Commission. Adam Mohr; President, Fabrication and Manufacturing; CB&I; One CB&I Plaza; 2103 Research Forest Drive; The Woodlands, TX; 77380. (ii) Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect. This is an interim report. The deviations being evaluated pertain to deficiencies identified within the Measuring and Test Equipment program at Chicago Bridge and Iron (CB&I) Laurens, 366 Old Airport Road, Laurens, SC. (iii) Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect. This is an interim report. The construction activities for the V.C. Summer [Units 2 and 3] and Vogtle AP1000r [Units 3 and 4] nuclear projects, which include procurement of the piping assemblies, are being performed by CB&I Power, 128 S. Tryon St., Charlotte, NC 28202. (iv) Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply. This is an interim report. The evaluations of vendors and previously performed calibrations is under evaluation and equipment in question is being re-calibrated by an approved lab and evaluated for extent of condition. Additionally, causal analysis is being performed that is expected to provide relevant information pertaining to the cause of the deviations and if any quality assurance breakdowns may have occurred that could have produced a defect. Evaluation of the condition is expected to be completed by June 26, 2015. (v) The date on which the information of such defect or failure to comply was obtained. The discovery date of the deviations that require evaluation is March 18, 2015, based on the nonconformance reports and C/PAR that identify the deviations. Evaluation of reportability in accordance with 10 CFR Part 21 was not able to be completed within the 60 day evaluation period. Additional time is needed to collect additional data pertaining to the identified nonconformances, perform causal analysis, and complete the evaluation. (vi) In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured. or being manufactured for one or more facilities or activities subject to the regulations in this part. No basic components have been determined to fail to comply or contain a defect. This is an interim report. (vii) The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action. No basic components have been determined to fail to comply or contain a defect. This is an interim report. (viii) Any advice related to the defect or failure to comply about the facility, activity. Or basic component that has been, is being, or will be given to purchasers or licensees. None at this time. (ix) In the case of an early site permit, the entities to whom an early site permit was transferred. Not applicable." |
Where | |
---|---|
Chicago Bridge And Iron The Woodlands, Texas (NRC Region 4) | |
Organization: | Chicago Bridge And Iron |
Reporting | |
10 CFR 21.21(a)(2), Interim Report for Comply or Defect in Component | |
Time - Person (Reporting Time:+1446.47 h60.27 days <br />8.61 weeks <br />1.981 months <br />) | |
Opened: | Adam Mohr 11:28 May 17, 2015 |
NRC Officer: | Vince Klco |
Last Updated: | May 17, 2015 |
51075 - NRC Website | |
Chicago Bridge And Iron with 10 CFR 21.21(a)(2), Interim Report for Comply or Defect in Component | |
WEEKMONTHYEARENS 510752015-03-18T05:00:00018 March 2015 05:00:00
[Table view]10 CFR 21.21(a)(2), Interim Report for Comply or Defect in Component 2015-03-18T05:00:00 | |