ENS Event | |
---|---|
17:14 Sep 5, 2013 | |
Title | Failure to Align Control Element Assembly During Testing |
Event Description | CCNPP [Calvert Cliffs Nuclear Power Plant] U2 CEA [Control Element Assembly] #27 fully inserted (CEA dropped) into the core during testing per STP 0-029-2. Technical Specification 3.1.4, Action B was entered and required the CEA to be realigned within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. With this action not met Technical Specification 3.1.4, Action C required the Unit be reduced to < 70% rated thermal power (achieved at 1308 [EDT]) and the CEA to be realigned within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.
With the CEA being unable to be realigned, Technical Specification 3.1.4.F was entered at 1314 [EDT] which requires the Unit to be placed in Mode 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. A plant shutdown has been initiated in accordance with this Technical Specification. Therefore, this is reportable under 10 CFR 50.72(b)(2)(i), 'Plant Shutdown Required by Technical Specifications.' The licensee will notify the NRC Resident Inspector. |
Where | |
---|---|
Calvert Cliffs Maryland (NRC Region 1) | |
Reporting | |
10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown | |
Time - Person (Reporting Time:+-2.38 h-0.0992 days <br />-0.0142 weeks <br />-0.00326 months <br />) | |
Opened: | Ervin Lyson 14:51 Sep 5, 2013 |
NRC Officer: | Pete Snyder |
Last Updated: | Sep 5, 2013 |
49323 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 49323\u003C/a\u003E - \u003Ca href=\"/Calvert_Cliffs\" title=\"Calvert Cliffs\"\u003ECalvert Cliffs\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EFailure to Align Control Element Assembly During Testing\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 49323 - Calvert Cliffs\n","link":"","lat":38.434263888888886,"lon":-76.44219722222222,"icon":"/w/images/b/be/Constellation_icon.png"}],"imageoverlays":null} | |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (45 %) |
WEEKMONTHYEARENS 543252019-10-11T17:00:00011 October 2019 17:00:00
[Table view]10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown Initiated ENS 503072014-07-25T03:15:00025 July 2014 03:15:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown, 10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded Technical Specification Required Shutdown Due to Reactor Coolant System Pressure Boundary Leakage ENS 493232013-09-05T17:14:0005 September 2013 17:14:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Failure to Align Control Element Assembly During Testing ENS 487632013-02-17T18:45:00017 February 2013 18:45:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown, 10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded Pressure Boundary Leakage Discovered During Containment Walkdown ENS 481832012-08-12T16:34:00012 August 2012 16:34:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Shutdown Due to Fully Inserted Control Rod While Operating ENS 481242012-07-21T16:10:00021 July 2012 16:10:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown, 10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded Technical Specification Required Shutdown Due to Rcs Pressure Boundary Instrument Line Leakage ENS 481162012-07-17T04:00:00017 July 2012 04:00:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown, 10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded Technical Specification Required Shutdown Due to Small Rcs Pressure Boundary Instrument Line Leak ENS 473162011-10-03T14:35:0003 October 2011 14:35:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown, 10 CFR 50.72(b)(3)(ii)(A), Seriously Degraded Technical Specification (Ts) Required Shutdown Due to Both 'A' Train Edg'S Inoperable ENS 424842006-04-09T03:42:0009 April 2006 03:42:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Control Element Assembly Stuck During Physics Testing 2019-10-11T17:00:00 | |