ENS 49151
ENS Event | |
---|---|
18:07 May 2, 2013 | |
Title | 60 Day Optional Telephonic Notification of Invalid Primary Containment Isolation System (Pcis) Actuation |
Event Description | This 60-day telephone notification is being made under reporting requirements specified by 10CFR50.73(a)(2)(iv)(A) to describe an invalid actuation of a containment isolation signal affecting more than one system.
At 1307 CDT on May 2, 2013, with the Duane Arnold Energy Center (DAEC) operating at 100% power, an invalid Group 3 isolation on the 'A' side of the Primary Containment Isolation System occurred. Group 3 isolation signals were generated for Primary Containment Isolation Valves for Drywell and Torus Ventilation, and Purge, Containment Nitrogen Compressor Suction and Discharge, Recirculation Pump Seals, and Post Accident Sample System. This event was caused by a human performance error that led to a blown fuse. Specifically, the fuse failed during pre-planned maintenance on a differential pressure switch when a test clip made inadvertent contact with an energized part of the switch. All equipment responded in accordance with the plant design. Specifically, all actuations were complete and successful. There were no safety consequences or impacts on the health and safety of the public. The event was entered into DAEC's corrective action program for resolution. The licensee notified the NRC Resident Inspector. |
Where | |
---|---|
Duane Arnold Iowa (NRC Region 3) | |
Reporting | |
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation | |
Time - Person (Reporting Time:+1337.43 h55.726 days <br />7.961 weeks <br />1.832 months <br />) | |
Opened: | Bob Murrell 11:33 Jun 27, 2013 |
NRC Officer: | Donald Norwood |
Last Updated: | Jun 27, 2013 |
49151 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 49151\u003C/a\u003E - \u003Ca href=\"/Duane_Arnold\" title=\"Duane Arnold\"\u003EDuane Arnold\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E60 Day Optional Telephonic Notification of Invalid Primary Containment Isolation System (Pcis) Actuation\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 49151 - Duane Arnold\n","link":"","lat":42.10089166666667,"lon":-91.77759444444445,"icon":"/w/images/9/9b/NextEra_Energy_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |
WEEKMONTHYEARENS 531672017-12-01T04:30:0001 December 2017 04:30:00
[Table view]10 CFR 50.73(a)(1), Submit an LER 60-Day Optional Telephonic Notification for an Invalid Primary Containment Isolation System Actuation ENS 491512013-05-02T18:07:0002 May 2013 18:07:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Optional Telephonic Notification of Invalid Primary Containment Isolation System (Pcis) Actuation ENS 487672012-12-20T09:54:00020 December 2012 09:54:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Optional Telephonic Notification of Invalid Primary Containment Isolation System Actuation ENS 486012012-10-21T01:20:00021 October 2012 01:20:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Optional Telephonic Notification of Invalid Primary Containment Isolation System (Pcis) Actuation ENS 469542011-04-15T01:43:00015 April 2011 01:43:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System Actuation Due to Connector High Resistance ENS 467242011-02-04T18:54:0004 February 2011 18:54:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System Actuation Due to a Failed Relay Coil ENS 433872007-04-01T07:49:0001 April 2007 07:49:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System (Pcis) Actuation Due to a Failed Relay Coil ENS 417602005-04-14T20:40:00014 April 2005 20:40:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System (Pcis) Actuation While Performing Re-Termination. ENS 417592005-04-14T11:13:00014 April 2005 11:13:00 10 CFR 50.73(a)(1), Submit an LER Invalid Primary Containment Isolation System (Pcis) Actuation During Post Maintenance Testing 2017-12-01T04:30:00 | |