50.55(e) initial notification for failure to comply with requirements of
10 CFR 50 Appendix B, Criterion VII for procurement of safety-related components associated with AP1000 Nuclear Power Plant construction by
CB&I (formerly Shaw Nuclear).
This 50.55(e) initial notification addresses a failure to comply by CB&I, an agent of South Carolina Electric & Gas (SCE&G) for Virgil C. Summer 2 & 3, to meet the requirements of Appendix B, Criterion VII. It is concluded that the QA programmatic issues, as identified by the root cause analysis associated with NRC violation 05200025/2012-004-02, could have produced a defect and this condition is reportable in accordance with 10 CFR 50.55(e)(3)(iii)(C). The root cause of the programmatic procurement problems was that the existing Shaw Nuclear procurement and quality oversight and inspection program did not include a sufficiently strategic, integrated, and graded approach to assure the required quality of material, equipment, and services. This notification closes the interim report submitted on February 4, 2013 by SCE&G.
This 50.55(e) initial notification is being submitted pursuant to the requirements of 10 CFR 50.55(e)(3)(iii)(C).
The licensee has notified the NRC Resident Inspector.