ENS 47858
ENS Event | |
|---|---|
23:15 Apr 21, 2012 | |
| Title | Apparent Phase Imbalance Between Normal and Alternate Power Circuits |
| Event Description | On April 21, 2012, at 1615 PDT, Diablo Canyon Power Plant (DCPP) operators identified that an attempted manual transfer of the Unit 1 AC power sources from the normal offsite circuit (500 kv) to the alternate offsite circuit (230 kv) failed.
The attempted manual transfer of the offsite power source from the normal 500 kv to the alternate 230 kv was a planned activity to shut down Unit 1 for its 17th refueling outage. The failure to manually transfer was concluded to be caused by an indicated out of phase condition between the 500 kv and 230 kv system. DCPP control transfer systems prevent paralleling and transferring the power supplies from the normal to alternate offsite circuit with an out of phase condition. The offsite AC power sources remain capable of being manually transferred from the normal to the alternate source by way of transferring to diesels as an intermediate step. The 230 kv system ability to perform its accident mitigation safety function following a reactor trip or safety injection was not affected by the inability to perform a direct manual transfer from the 500 kv offsite power system. DCPP staff are currently troubleshooting the out of phase indication and will provide an update when the cause is concluded. The licensee notified the NRC Resident Inspector.
This is an update to EN#47858 reported on April 22, 2012, where Pacific Gas & Electric Company (PG&E) reported that an attempt to manually transfer the DCPP Unit 1 AC power sources from the normal offsite circuit (500 kV) to the alternate required offsite circuit (230 kV) failed. PG&E determined that the out-of-phase condition between the 500kV system and the 230 kV system resulted from the offsite power system configurations and conditions existing at the time of the attempted transfer. PG&E established alternate operating guidance to allow operators to perform bus transfers between the 500kV source and the 230 kV source in the event that an out-of-phase condition exists when bus transfer is desired. PG&E personnel informed the NRC Resident Inspector. Notified R4DO (Proulx). |
| Where | |
|---|---|
| Diablo Canyon California (NRC Region 4) | |
| Reporting | |
| Information Only | |
| Time - Person (Reporting Time:+3.58 h0.149 days <br />0.0213 weeks <br />0.0049 months <br />) | |
| Opened: | Dan Stermer 02:50 Apr 22, 2012 |
| NRC Officer: | Pete Snyder |
| Last Updated: | Apr 25, 2012 |
| 47858 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 47858\u003C/a\u003E - \u003Ca href=\"/Diablo_Canyon\" title=\"Diablo Canyon\"\u003EDiablo Canyon\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EApparent Phase Imbalance Between Normal and Alternate Power Circuits\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 47858 - Diablo Canyon\n","link":"","lat":35.21169166666667,"lon":-120.85504166666666,"icon":"/w/images/f/ff/Pacific_Gas_%26_Electric_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (82 %) |
| After | Power Operation (20 %) |
Unit 2 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
WEEKMONTHYEARENS 478582012-04-21T23:15:00021 April 2012 23:15:00
[Table view]Information Only Apparent Phase Imbalance Between Normal and Alternate Power Circuits ENS 477282012-03-09T02:50:0009 March 2012 02:50:00 Information Only Inoperable Steam Generator Narrow Range Level Transmitters Due to Part 21 Concern ENS 431022007-01-14T23:42:00014 January 2007 23:42:00 Information Only Information Regarding Wildfire in the Vicinity of the Plant Site 2012-04-21T23:15:00 | |