ENS 47225
From kanterella
Jump to navigation
Jump to search
ENS Event | |
|---|---|
20:00 Aug 30, 2011 | |
| Title | Completion of Action Plan (Fabrication) Milestone |
| Event Description | In response to a Notice of Violation (NOV), Global Nuclear Fuels - America (GNFA) committed to perform a review of the existing Integrated Safety Analysis (ISA). An ISA Action Plan and schedule for performing the ISA review was described in GNF-A's response to the NOV and the second milestone (fabrication) was scheduled for completion by July 31, 2011. This milestone was subsequently extended by approximately 30 days. On 8/30/11, GNF-A completed the ISA review for the fabrication area and has identified 125 existing safety controls that are now being designated as Items Relied On For Safety (IROFS). Implementation of the revised safety basis, IROFS and application of management measures to the new IROFS will be completed within 90 days per the ISA Action Plan. Because the revised ISA has designated existing safety controls as additional IROFS, GNF-A is making a report of this completion pursuant to the reporting requirements of 10CFR70 Appendix A(b)(1) within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
The NOV inspection report (70-1113/2010-013) was dated June 9, 2010 with an NOV response on July 23, 2010. Milestone #1 was reported in EN#46710 on March 30, 2011. This report concerns milestone #2 of 3. The licensee will notify the NRC Region 2 Project Manager, the State of North Carolina, and Hanover County. |
| Where | |
|---|---|
| Global Nuclear Fuel Wilmington, North Carolina (NRC Region 2) | |
| License number: | SNM-1097 |
| Reporting | |
| 10 CFR 70.74 APP. A | |
| Time - Person (Reporting Time:+17.02 h0.709 days <br />0.101 weeks <br />0.0233 months <br />) | |
| Opened: | Scott Murray 13:01 Aug 31, 2011 |
| NRC Officer: | Mark Abramovitz |
| Last Updated: | Aug 31, 2011 |
| 47225 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 47225\u003C/a\u003E - \u003Ca href=\"/Global_Nuclear_Fuel\" title=\"Global Nuclear Fuel\"\u003EGlobal Nuclear Fuel\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003ECompletion of Action Plan (Fabrication) Milestone\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 47225 - Global Nuclear Fuel\n","link":"","lat":34.320930555555556,"lon":-77.92285,"icon":""}],"imageoverlays":null} | |
Global Nuclear Fuel with 10 CFR 70.74 APP. A | |
WEEKMONTHYEARENS 472692011-09-14T19:30:00014 September 2011 19:30:00
[Table view]Other Unspec Reqmnt, 10 CFR 70.74 APP. A 24 Hour Report Due to Double Contingency Not Maintained ENS 472252011-08-30T20:00:00030 August 2011 20:00:00 10 CFR 70.74 APP. A Completion of Action Plan (Fabrication) Milestone ENS 457852010-03-22T13:30:00022 March 2010 13:30:00 10 CFR 70.74 APP. A Loss of One of Two Required Contingency Controls 2011-09-14T19:30:00 | |