ENS 46179
ENS Event | |
---|---|
18:40 Aug 16, 2010 | |
Title | Npdes Limit Was Exceeded for River Temperature Discharge Requirements |
Event Description | Browns Ferry Nuclear Plant inadvertently exceeded a limitation of its National Pollutant Discharge Elimination System (NPDES) Permit for Tennessee River temperature conditions which was reported to the Alabama Department of Environmental Management (ADEM) at 1340 Central Daylight Time, on August 16, 2010. As such, this is being reported in accordance with 10 CFR 50.72(b)(2)(xi) as 'Any event or situation, related to the health and safety of the public or on-site personnel, or protection of the environment, for which a news release is planned or notification to other government agencies has been or will be made.'
The NPDES Permit requires that when the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ambient average river temperature exceeded 90 degrees Fahrenheit, the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> average downstream river temperature may equal but not exceed the upstream value. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> average upstream temperature was found to be 90.4 (rounded to 90) degrees Fahrenheit and the downstream temperature was found to be 90.6 (rounded to 91) degrees Fahrenheit. Browns Ferry had been maintaining compliance with the NPDES permit. The departure is thought to be due to a summer storm cooling off the upstream temperature. With the time delay between upstream temperature changes and the ensuing rate at which the downstream temperature changes are observed, the resultant 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> average downstream river temperature exceeded the upstream value. Duration of this condition was found to be only several hours. The three Browns Ferry units, which had already been derated to approximately 50 percent rated thermal power in order to maintain compliance with the NPDES Permit river temperature limits, were further derated to achieve compliance with the NPDES Permit. There is no corresponding requirement for written follow-up in accordance with 10 CFR 50.73. The licensee has notified the NRC Resident Inspector. |
Where | |
---|---|
Browns Ferry Alabama (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release | |
Time - Person (Reporting Time:+-0.63 h-0.0263 days <br />-0.00375 weeks <br />-8.62974e-4 months <br />) | |
Opened: | Ricky Givens 18:02 Aug 16, 2010 |
NRC Officer: | John Knoke |
Last Updated: | Aug 16, 2010 |
46179 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (50 %) |
After | Power Operation (45 %) |
Unit 2 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (50 %) |
After | Power Operation (45 %) |
Unit 3 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (50 %) |
After | Power Operation (45 %) |
WEEKMONTHYEARENS 569412024-02-01T18:17:0001 February 2024 18:17:00
[Table view]10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification - Workplace Injury ENS 563852023-03-02T19:12:0002 March 2023 19:12:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification ENS 539182019-03-08T17:13:0008 March 2019 17:13:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification for Oil Spill Into U.S. Waters ENS 520252016-06-17T17:22:00017 June 2016 17:22:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification Due to Elevated Tritium Detected Onsite ENS 518502016-04-06T20:45:0006 April 2016 20:45:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release, 10 CFR 50.72(a)(1)(i), Emergency Class Declaration Unusual Event Declared Due to Main Steamline High High Radiation Condition ENS 515712015-11-29T22:00:00029 November 2015 22:00:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification Due to Small Oil Spill ENS 507252015-01-08T22:26:0008 January 2015 22:26:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification Due to Low Level Tritium Spill ENS 507192015-01-06T18:27:0006 January 2015 18:27:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification Due to Oil Leak ENS 505822014-10-30T16:00:00030 October 2014 16:00:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification and Press Release Regarding Boone Dam Stability Issues ENS 502772014-07-13T22:40:00013 July 2014 22:40:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification of a One Gallon Diesel Fuel Oil Spill ENS 502222014-06-23T20:40:00023 June 2014 20:40:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Reportable Small Oil Spill Into U.S. Waters ENS 461792010-08-16T18:40:00016 August 2010 18:40:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Npdes Limit Was Exceeded for River Temperature Discharge Requirements ENS 459502010-05-24T20:20:00024 May 2010 20:20:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification - Oil Sheen at Intake Forebay ENS 458202010-04-07T21:10:0007 April 2010 21:10:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Spill of Water Containing Tritium ENS 443672008-07-27T08:40:00027 July 2008 08:40:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Cable Tray Fire Near Cooling Tower "C" Switchgear ENS 442442008-05-28T21:30:00028 May 2008 21:30:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Transportation Accident Involving a Radioactive Material Shipment ENS 438932008-01-10T22:00:00010 January 2008 22:00:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Inadvertent Actuation of Offsite Emergency Siren ENS 438912008-01-10T18:21:00010 January 2008 18:21:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification - Spill of Water Containing Tritium ENS 436642007-09-26T11:50:00026 September 2007 11:50:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Oil Sheen in Forebay Area That Is Not from Bfn ENS 435682007-08-15T13:38:00015 August 2007 13:38:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Notification to State Due to Contaminated Material Discovered in Free Release Scrap Material ENS 435382007-07-31T14:30:00031 July 2007 14:30:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification Due to Small Hydraulic Fluid Spill in Intake Bay ENS 429892006-11-07T21:26:0007 November 2006 21:26:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Actuation of an Offsite Emergency Siren ENS 420322005-10-01T15:59:0001 October 2005 15:59:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification Concerning an Industrial Accident ENS 408282004-06-18T17:04:00018 June 2004 17:04:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release Offsite Notification - Employee Fatality 2024-02-01T18:17:00 | |