ENS 43246
From kanterella
Jump to navigation
Jump to search
ENS Event | |
|---|---|
04:46 Mar 18, 2007 | |
| Title | Rps Trip Signal and Containment Isolations Received During Maintenance |
| Event Description | With the plant in refueling outage with all rods in and in Mode 5, a RPS trip and a containment isolation was received at 2347, 03/17/07. This event occurred when Div #2 Bus 16 Bus Pot Drawer was opened during isolation of 1AR Transformer Metering under C/O-17605. The opening of this Pot Drawer caused Div #2 4KV Bus 16, Div #2 480V LC-104 and Div #2 480V MCC-141, 142, 143, and 144 to open. 'B' RPS tripped causing full RPS trip due to SRM shorting removed. The loss of power caused RBV [Reactor Building Ventilation] and Spent Fuel Pool Radiation Monitors to trip and cause containment isolation to occur. Investigation into C/O-17605, restoration of power, resetting of RPS and containment isolation in progress.
The containment valves that received an isolation signal were: Primary Containment Atmosphere Control, Post Accident H2/O2 Control system, Post Accident Sampling system, O2 analyzing and SCTMT isolation (H&V). The licensee notified the NRC Resident Inspector. |
| Where | |
|---|---|
| Monticello Minnesota (NRC Region 3) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
| Time - Person (Reporting Time:+-0.08 h-0.00333 days <br />-4.761905e-4 weeks <br />-1.09584e-4 months <br />) | |
| Opened: | Randy Sand 04:41 Mar 18, 2007 |
| NRC Officer: | Jeff Rotton |
| Last Updated: | Mar 18, 2007 |
| 43246 - NRC Website