ENS 42194
From kanterella
Jump to navigation
Jump to search
ENS Event | |
---|---|
20:44 Dec 9, 2005 | |
Title | Rcs Pressure Boundary Leakage Identified |
Event Description | At 1450 hours0.0168 days <br />0.403 hours <br />0.0024 weeks <br />5.51725e-4 months <br /> on 12/5/05, Unit 2 entered abnormal operating procedure 18004-C 'RCS Leakage' due to increasing containment atmospheric radiation levels as identified on 2RE2562A. Per procedure, an RCS leak rate determination was commenced and completed as of 1629 hours0.0189 days <br />0.453 hours <br />0.00269 weeks <br />6.198345e-4 months <br />, 12/8/05 (identified = 0.032gpm, unidentified = 0.254gpm, total = 0.286gpm). While making preparations for a containment entry for leakage inspection, a second leak rate [determination] was completed at 2020 hours0.0234 days <br />0.561 hours <br />0.00334 weeks <br />7.6861e-4 months <br />, 12/8/05 (identified = 0.070gpm, unidentified = 0.267gpm, total = 0.337gpm). At 2240 hours0.0259 days <br />0.622 hours <br />0.0037 weeks <br />8.5232e-4 months <br />, 12/8/05, the team performing the containment leak inspection reported no leakage identified outside the bioshield. Another leak rate [determination] was completed at 0245 hours0.00284 days <br />0.0681 hours <br />4.050926e-4 weeks <br />9.32225e-5 months <br />, 12/9/05, the team performing the containment leak inspection reported that by using a robotic camera, water was observed coming down the inside wall of the bioshield in the area of loop 2. At 0433 hours0.00501 days <br />0.12 hours <br />7.159392e-4 weeks <br />1.647565e-4 months <br />, 12/9/05, a shutdown of Unit 2 was initiated to allow further investigation / repair of the RCS leak inside containment. Unit 2 was placed in Mode 3 at 1313 hours0.0152 days <br />0.365 hours <br />0.00217 weeks <br />4.995965e-4 months <br />, 12/9/05. At 1544 hours0.0179 days <br />0.429 hours <br />0.00255 weeks <br />5.87492e-4 months <br />, 12/9/05, the containment leak inspection team reported pressure boundary leakage at a welded connection where a 3/4 inch bypass line is welded to the RCS loop upstream of the RHR loop suction valve 2HV8701B. [Plant Vogtle personnel are] presently preparing to commence shutdown to Mode 5 for repair of the leak.
Technical specification 3.4.14 applies and requires no pressure boundary leakage. The plant is currently removing decay heat by steaming from the steam generators through the steam dump valves to the condenser. All safety related electrical buses are available. Emergency diesel generators are available and in standby. The licensee notified the NRC Resident Inspector.
Two corrections were communicated. The date of the initial event was "at 1450 hours0.0168 days <br />0.403 hours <br />0.0024 weeks <br />5.51725e-4 months <br /> on 12/8/05." The technical specification quoted is changed to 3.4.13. Notified the R2DO (Henson). |
Where | |
---|---|
Vogtle Georgia (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown | |
Time - Person (Reporting Time:+-2.55 h-0.106 days <br />-0.0152 weeks <br />-0.00349 months <br />) | |
Opened: | Steve Phillips 18:11 Dec 9, 2005 |
NRC Officer: | Pete Snyder |
Last Updated: | Dec 12, 2005 |
42194 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 42194\u003C/a\u003E - \u003Ca href=\"/Vogtle\" title=\"Vogtle\"\u003EVogtle\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003ERcs Pressure Boundary Leakage Identified\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 42194 - Vogtle\n","link":"","lat":33.13062222222222,"lon":-81.77135277777778,"icon":"/w/images/1/14/Southern_Nuclear_icon.png"}],"imageoverlays":null} | |
Unit 2 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Hot Standby (0 %) |
After | Hot Standby (0 %) |
WEEKMONTHYEARENS 524232016-12-10T01:42:00010 December 2016 01:42:00
[Table view]10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Technical Specification Required Shutdown ENS 424342006-03-20T18:00:00020 March 2006 18:00:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Plant Shutdown Due to Rcs Pressure Boundary Leakage ENS 423092006-02-04T02:24:0004 February 2006 02:24:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Identified Rcs Pressure Boundary Leakage ENS 421942005-12-09T20:44:0009 December 2005 20:44:00 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Rcs Pressure Boundary Leakage Identified 2016-12-10T01:42:00 | |