ENS 40440
ENS Event | |
---|---|
20:45 Jan 12, 2004 | |
Title | 24 Hour Notification Bulletin 91-01 Criticality Control |
Event Description | Reason for Notification: Thirteen polypaks of uranium powder were dumped into a bulk container without a documented visual inspection of the bulk container. A visual inspection is performed prior to introducing SNM into a bulk container.
Upon recognizing that the documentation was missing, the operator confirmed that a visual inspection had been performed prior to introducing SNM, but had not been documented. The operator then re-inspected the bulk container and found no trace of moderator. The powder dumped into the container was previously documented to contain leas than 0.3 weight percent moisture. Double Contingency Protection: Double contingency protection for the ADU Bulk Blending System is assured by preventing moderator from entering a bulk container. Empty bulk containers are inspected for the presence of moderator prior to introducing SNM. Failure to document the inspection left less than previously documented double contingency protection for the system. In accordance with Westinghouse Operating License (SNM-1107), paragraph 3.7.3 (c.5b), this event satisfies the criteria for a 24-hour notification. Summary of Activity: Bulk blending operations were discontinued. Training was performed for each shift prior to resuming operations. Conclusions: Less than previously documented double contingency protection remained. At no time was the health or safety to any employee or member of the public in jeopardy. No exposure to hazardous material was involved. The Incident Review Committee (IRC) determined that this is a significant incident in accordance with governing procedures. A causal analysis will be performed. |
Where | |
---|---|
Westinghouse Electric Corporation Columbia, South Carolina (NRC Region 2) | |
License number: | SNM-1107 |
Reporting | |
Response | |
Time - Person (Reporting Time:+14.22 h0.593 days <br />0.0846 weeks <br />0.0195 months <br />) | |
Opened: | Carl Snyder 10:58 Jan 13, 2004 |
NRC Officer: | Mike Ripley |
Last Updated: | Jan 13, 2004 |
40440 - NRC Website | |
Westinghouse Electric Corporation with Response | |
WEEKMONTHYEARENS 419332005-08-19T19:30:00019 August 2005 19:30:00
[Table view]Response Nrc Bulletin 91-01 Violation of Criticality Spacing Requirements ENS 417232005-05-20T22:40:00020 May 2005 22:40:00 Response, Part 70 App A (B)(5) Deviation from Integrated Safety Analysis, and a 24 Hour Notification - Bulletin 91-01 Criticality Control ENS 414182005-02-17T17:00:00017 February 2005 17:00:00 Response, Part 70 App A (B)(1) 24 Hour 91-01 Response Bulletin and Part 70 App a Unanalyzed Condition ENS 413722005-02-04T14:00:0004 February 2005 14:00:00 Response 24-Hour Notification-Bulletin 91-01 Criticality Control ENS 409852004-08-24T14:05:00024 August 2004 14:05:00 Response 24 Hour 91-01 Response Bulletin ENS 408882004-07-21T13:00:00021 July 2004 13:00:00 Response 4-Hour 91-01 Nrc Bulletin Notification Due to Adu in Non-Favorable Geometry Nitrogen Accumulator Tank ENS 408552004-07-07T21:00:0007 July 2004 21:00:00 Response Nrc Bulletin 91-01 - 4 Hour Report ENS 407932004-06-04T22:00:0004 June 2004 22:00:00 Response Licensee Reported a 4 Hour 91-01 Response Bulletin ENS 405672004-03-04T20:00:0004 March 2004 20:00:00 Response 24-Hour Notification - Bulletin 91-01 Criticality Control ENS 404402004-01-12T20:45:00012 January 2004 20:45:00 Response 24 Hour Notification Bulletin 91-01 Criticality Control ENS 402552003-10-16T19:30:00016 October 2003 19:30:00 Response 24 Hour Bulletin 91-01 Notification from Westinghouse Columbia Fuel Facility ENS 402462003-10-14T11:30:00014 October 2003 11:30:00 Response 24-Hour Nrc 91-01 Bulletin Report Involving Improper Mass Control ENS 401522003-09-12T14:32:00012 September 2003 14:32:00 Response Improper Scanning of Lead Rods for the Product Engineering Laboratory 2005-08-19T19:30:00 | |