Maureen R. Zawalick Vice President Decommissioning and Technical Services Diablo Canyon Power Plant Mail code 104/6/608 P.O. Box 56 Avila Beach, CA 93424 805.545.4242 Internal: 691.4242 A member of the STARS Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek PG&E Letter DCL-22-027 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 10 CFR 50.75(h)(2)
Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Pre-Notice of Disbursement from Decommissioning Trust
References:
- 1. NRC Letter, Diablo Canyon Power Plant, Units 1 and 2 - Exemptions from the Requirements of 10 CFR Part 50, Sections 50.82(a)(8)(i)(A) and 50.82(a)(8)(ii)
(EPID L-2018-LLE-0023), dated September 10, 2019 (ML19163A104)
Dear Sir or Madam:
Article 8, Section 8.13 of the Master Decommissioning Trust Agreement by and between Pacific Gas and Electric Company (PG&E) and The Bank of New York Mellon, successor by operation of law to Mellon Bank, N.A. as Trustee, except for withdrawals made pursuant to 10 CFR 50.82(a)(8) and for payments of administrative costs (including taxes) and other incidental expenses, provides that no disbursements or payments shall be made by the Trustee: (1) unless 30 working days prior written notice of such disbursement or payment has been made to the Nuclear Regulatory Commission, or (2) if the Trustee receives written notice of an objection from the Director of either the Office of Nuclear Material Safety and Safeguards or the Director of Nuclear Reactor Regulation.
In Reference 1, the NRC granted PG&E an exemption to 10 CFR Part 50, Sections 50.82(a)(8)(i)(A) and 50.82(a)(8)(ii), for the Diablo Canyon Power Plant (DCPP), Units 1 and 2 to fund radiological decommissioning, spent fuel management, and site restoration planning activities. In accordance with 10 CFR 50.75(h)(2), the purpose of this letter is to provide the NRC written notification of The Bank of New York Mellon's intent, upon receipt of a completed Disbursement Certificate from PG&E, to make a disbursement from the DCPP Nuclear Decommissioning Trust in an amount not to exceed (without a supplemental 30-day notice to the Director) $36,261,951, for the costs incurred through December 2019. The disbursement is being requested to fund, among other things, site-specific costs related to decommissioning permitting, licensing, and planning.
m PacHic Gas and Electric Company*
Document Control Desk Page 2 PG&E Letter DCL-22-027 A member of the STARS Alliance Callaway
- Diablo Canyon
- Palo Verde
- Wolf Creek The disbursement from the DCPP Nuclear Decommissioning Trust in the amount described above is planned to be made thirty (30) working days following the date of this letter unless the trustee receives prior written notice of objection from the Director of either the Office of Nuclear Material Safety and Safeguards or the Director of Nuclear Reactor Regulation.
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.
Should you have any questions, please contact Mr. Philippe Soenen at (805) 459-3701.
Sincerely, Maureen R. Zawalick Vice President Decommissioning and Technical Services Date cc:
Diablo Distribution William C. Allen, NMSS Project Manager Nicholas A. Hernandez, NRC Acting Senior Resident Inspector Samson S. Lee, NRC Senior Project Manager Scott A Morris, NRC Region IV Administrator April 8, 2022