Pacific Gas and Electric Company James R. Becker Diablo Canyon Power Plant Station Director Mail Code 104/5/504 P0. Box 56 Avila Beach, CA 93424 April 12, 2002 805.545.3462 Fax: 805.545.4234 PG&E Letter DCL-02-039 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Emergencv Plan Implementing Procedure Update
Dear Commissioners and Staff:
in accordance with Section V, "Implementing Procedures," of 10 CFR 50, Appendix E, enclosed is an update to the emergency plan (EP) implementing procedures for Diablo Canyon Power Plant, Units I and 2.
As provided under 10 CFR 50.54(q), the changes have been made without prior NRC approval since they do not decrease the effectiveness of the EP. The EP, as changed, continues to meet the standards of 10 CFR 50.47(b) and 10 CFR 50, Appendix E.
This update contains privacy/proprietary information that has been bracketed in accordance with NRC Generic Letter 81-27.
If there are any questions regarding this update, please contact Mr. Mark Lemke of my staff at (805) 545-4787.
Sincerel James R. Becker A member of the STARS (Strategic Teaming and Resource Shatring) Altiance 1& 6 Cattaway
- Comanche Peak D&ab.o Canyon
- Palo Verde
- South Texas Project a Wolf Creek
Document Control Desk PG&E Letter DCL-02-039 April 12, 2002 Page 2 kya/1345 Enclosures cc:
David L. Proulx Girija S. Shukla cclenc: Ellis W. Merschoff (2)
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Cattaway e Comanche Peak o Diablo Canyon
- Palo Verde
- South Texas Project o WoLf Creek PG&E Letter DCL-02-039 LOCATION OF PRIVACY/PROPRIETARY INFORMATION IN EMERGENCY PLAN IMPLEMENTING PROCEDURES FOR DIABLO CANYON POWER PLANT, UNITS I AND 2 Procedure Number Privacy/
Proprietary Information Title/Location of Privacy/Proprietary Information EP G-4 Revision 18 EP RB-14 Revision 7 EP RB-15 Revision 11 EP EF-2 Revision 26 Yes None Yes None Personnel Assembly, Accountability and Site Access Control During Emergencies Page 6 of 8 Page 1 of Attachment 7.2 Core Damage Assessment Procedure Post Accident Sampling System Pages 2, 8, and 10 of 12 Activation and Operation of the Operational Support Center PG&E Letter DCL-02-039 DIABLO CANYON POWER PLANT EMERGENCY PLAN IMPLEMENTING PROCEDURES Table of Contents - Emergency Plan Implementing Procedures Volume 1A (OM10.1D3 only), Volume 1B (OMI0.DC1 only), and Volume 3B Rev.
Title 6
Emergency Plan Training 2
Emergency Preparedness Drills and Exercises 30A Emergency Classification and Emergency Plan Activation 24 Activation and Operation of the Interim Site Emergency Organization (Control Room) 36 Notification of Off-Site Agencies and Emergency Response Organization Personnel 18 Personnel Assembly, Accountability and Site Access Control During Emergencies 9A Evacuation of Nonessential Site Personnel 19C Release of Airborne Radioactive Materials Initial Assessment 8C Release of Radioactive Liquids 13 Off-Site Transportation Accidents 6A Emergency Recovery 5B Personnel Dosimetry 4B Emergency Exposure Guides 4
Stable Iodine Thyroid Blocking 4A Access to and Establishment of Controlled Areas Under Emergency Conditions 4C Personnel Decontamination 14 Instructions for Field Monitoring Teams 11 Calculation of Release Rate 7A Protective Action Recommendations 12 Emergency Offsite Dose Calculations 6
Plant Vent Iodine and Particulate Sampling During Accident Conditions 7
Core Damage Assessment Procedure 11 Post Accident Sampling System 27 Activation and Operation of the Technical Support Center 26 Activation and Operation of the Operational Support Center 20 Activation and Operation of the Emergency Operations Facility 13A Activation of the Mobile Environmental Monitoring Laboratory 8
Backup Emergency Response Facilities 4
Joint Media Center Activation and Operation
- Procedure included in this submittal Proc. No.
OM10.1D3 OM10.DC1 EP G-1 EP G-2 EP G-3 EP G-4*
EP G-5 EP R-2 EP R-3 EP R-7 EP OR-3 EP RB-1 EP RB-2 EP RB-3 EP RB-4 EP RB-5 EP RB-8 EP RB-9 EP RB-10 EP RB-11 EP RB-12 EP RB-14*
EP RB-15*