CNL-19-109, Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update

From kanterella
Jump to navigation Jump to search

Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestone Status Update
ML19302D601
Person / Time
Site: Browns Ferry, Watts Bar, Sequoyah  Tennessee Valley Authority icon.png
Issue date: 10/28/2019
From: Polickoski J
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CNL-19-109
Download: ML19302D601 (3)


Text

Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-19-109 October 28, 2019 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390 and 50-391

Subject:

TENNESSEE VALLEY AUTHORITY - HYDROLOGIC ENGINEERING CENTER RIVER ANALYSIS SYSTEM (HEC-RAS) PROJECT MILESTONE STATUS UPDATE

Reference:

TVA letter to NRC, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System (HEC-RAS) Project Milestones, dated June 22, 2016 (ML16175A518)

By letter dated June 22, 2016, Tennessee Valley Authority (TVA) provided the Nuclear Regulatory Commission (NRC) with dates for several project deliverables associated with the ongoing HEC-RAS external flood modeling project (referenced letter). The HEC-RAS external flood modeling project was the subject of an April 4, 2016, public meeting to discuss technical details and a resolution plan for TVAs HEC-RAS external flood modeling issues. In the referenced letter, TVA committed to provide updates on the status of the specific project deliverables on a six-month frequency.

U.S. Nuclear Regulatory Commission CNL-19-109 Page 2 October 28, 2019 The purpose of this letter is to provide the seventh written update regarding the status of the project milestones consistent with the commitment made in the referenced letter.

Tasks 4, 5, and 6 have been completed since the update provided by letter dated April 29, 2019 (ML19119A349). Focused Evaluations were completed for Watts Bar, Sequoyah, and Browns Ferry and submitted by separate letters dated October 11, 2019 (ML19284F763, ML19284F762, and ML19284F761, respectively).

TABLE 1 PROJECT DELIVERABLE SUBMITTAL MILESTONES (Status Updates Shown in Bold Text)

Submittal Project Deliverable Milestone 1 Browns Ferry Mitigating Strategies Assessment (MSA) Complete 2 Sequoyah MSA Complete 3 Watts Bar MSA Complete 4 Watts Bar Focused Evaluation (FE) Complete 5 Sequoyah FE Complete 6 Browns Ferry FE Complete 7 Sequoyah Hydrology License Amendment Request (LAR) November 2019 8 Watts Bar Hydrology LAR January 2020 The projected milestones for the submittal of the Sequoyah and Watts Bar Hydrology LARs will be discussed with the NRC Project Manager.

TVA will provide the eighth status update on these project deliverable submittal milestones by April 30, 2020, consistent with the commitment made in the referenced letter.

U.S. Nuclear Regulatory Commission CNL-19-109 Page3 October 28, 2019 There are no new regulatory commitments made in this letter.

If additional information is needed regarding this update, please contact Russell Thompson at (423) 751-2567.

Respectfully,

~-

~ - Polickoski Director, Nuclear Regulatory Affairs cc:

NRR Director- NRC Headquarters NRC Regional Administrator - Region II NRC Project Manager - Browns Ferry Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant