Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402 CNL-1 3-146 December 24, 2013 10 CFR 50, Appendix E, Section V 10 CFR 50.4 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Units 1, 2, and 3 Renewed Facility Operating License Nos. DPR-33, DPR-52, and DPR-68 NRC Docket Nos. 50-259, 50-260, and 50-296 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390
Subject:
Central Emergency Control Center - Emergency Plan Implementing Procedure Revision In accordance with the requirements of 10 CFR Part 50, Appendix E, Section V, this submittal provides the Central Emergency Control Center (CECC) Emergency Plan Implementing Procedure (EPIP) revisions as listed below.
EPIP Revision Title Effective Date CECC EPIP-1 58 Central Emergency Control Center 12/05/2013 (CECC) Operations CECC EPIP-18 13 Transportation and Staffing Under 12/05/2013 Abnormal Conditions Printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 December 24, 2013 EPIP Revision Title CECC EPIP-21 CECC EPIP-22 CECC EPIP-23 15 27 24 Emergency Duty Officer Procedure for Notification of Unusual Event, Alert, Site Area Emergency, and General Emergency Operations Duty Specialist Transportation Incidents Involving a Shipment of Radioactive Materials Radioactive Material Transportation Incidents Effective Date 12/05/2013 12/05/2013 12/05/2013 provides a summary of the changes and the analysis performed that concluded the changes do not affect the outcome, results, functions, processes, responsibilities, or requirements of the performance of the EPIPs. Enclosure 2 provides a copy of the revised EPIPs.
There are no new regulatory commitments in this letter. If you have any questions regarding this submittal, please contact Edward D. Schrull at (423) 751-3850.
J. W. Shea Vice President, Nuclear Licensing
Enclosures:
- 1. Summary of Changes and Analysis
- 2. Central Emergency Control Center (CECC), Emergency Plan Implementing Procedure (EPIP) Revisions cc (Enclosures):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Senior Resident Inspector - Watts Bar Nuclear Plant