CLI-85-09, Accepts 850531 Power Ascension Schedule Per Condition 1 of CLI-85-09,in Response to 850531 Request.Satisfaction of License Conditions Required Prior to Concurrence to Proceed Beyond Hold Points
| ML20126H471 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 06/03/1985 |
| From: | Murley T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Hukill H GENERAL PUBLIC UTILITIES CORP. |
| References | |
| CON-#285-348 CLI-85-09, CLI-85-9, SP, NUDOCS 8506100342 | |
| Download: ML20126H471 (2) | |
Text
'
a f %
JUN 0 a 1985 Docket No. 50-289 GPU Nuclear Corporation ATTN: Mr. H. D. Hukill Vice President and Director of TMI-1 P.O. Box 480 Middletown, Pennsylvania 17057 Gentlemen:
Subject:
Restart License Condition - Power Ascension Schedule This is in response to your letter of May 31, 1985 in which you requested NRC staff approval of your power ascension schedule pursuant to Condition 1 of the Commission's Memorandum and Order CLI-85-09.
We have reviewed the schedule contained in your May 31, 1985 letter and find it acceptable.
In addition, the hold points beyond which you will not proceed without my verbal concurrence are acceptable as specified in your May 31, 1985 letter. Satisfaction of the appropriate license conditions will be required prior to my concurrence to proceed beyond the hold points.
?
fl OW&
$ 0vv1 6 h. $//lQ %
L Thomas E. Murley O'
Regional Administrator cc:
R. J. Toole, Operations and Maintenance Director, TMI-1 C. W. Smyth, Manager, TMI-1 Licensing R. J. McGoey, Manager, PWR Licensing G. F. Trowbridge, Esquire TMI-1 Hearing Service List Public document Room (PDR)
Local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector Commonwealth of Pennsylvania bec:
Region I Docket Room (with concurrences)
W. D. Travers, Deputy Program Director, TMI Program Office J. Goldberg, OELD:HQ DRP Section Chief John Thoma, PM, RR i
y 5
pki rm h-gol
\\
8506100342 850603 PDR ADOCM 05000G99 P
PDR L
p
.. g 3 p f JUN 0 3 1985 Docket No. 50-289 GPU Nuclear Corporation ATTN:
Mr. H. D. Hukill
-Vice President and Director of TMI-l P.O. Box 480 Middletown, Pennsylvania 17057 Gentlemen:
Subject:
Restart License Condition - Power Ascension Schedule This is in response to your letter of May 31, 1985 in which you requested NRC staff approval of your power ascension schedule pursuant to Condition 1 of the Commission's Memorandum and Order CLI-85-09.
We have reviewed the schedule contained in your May 31, 1985 letter and find it acceptable.
In addition, the hold points beyond which you will not proceed without my verbal concurrence are acceptable as specified in your May 31, 1985 1etter, & &/,sQ,m of 6(e 4 ),ce a Q, k aif be JW $ h/Afok.
n r k ng cia n w at /c w
fe +u A i
Thomas E. Murley Regional Administrator cc:
R. J. Toole, Operations and Maintenance Director, TMI-1 C. W. Smyth, Manager, TMI-l Licensing R. J. McGoey, Manager, PWR Licensing G. F. Trowbridge, Esquire TMI-l Hearing Service List Public document Room (PDR) local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector Commonwealth of Pennsylvania bec:
Region I Docket Room (with concurrences)
W. D. Travers, Deputy Program Director, TMI Program Office J. Goldberg, OELD:HQ DRP Section Chief John Thoma, PM, NRR b
N P,
g:
R
)
m ta tecki an
% rley f,g pf -
t 85 D
fd*W t
y p,wRS
$6A J<A k
D&
J av G utinaS y
-